Temp agency quotas on public sites: Supreme Court annuls Neuchâtel cap (ATF 151 I 113)
· 9 min read
Financial stake No amount in dispute: access to Neuchâtel public construction contracts for staff leasing companies. The annulled ceiling ranged from 2 temporary workers for 1 to 3 permanent employees to 20% from 21 permanent employees.
Legal basis ATF 151 I 113 (judgment 2C_587/2023 of 30 January 2025); Art. 9 para. 1 and Art. 10 of the Neuchâtel Public Procurement Act (LCMP/NE); Art. 27 and 63 para. 4 of the AIMP 2019 (Intercantonal Agreement on Public Procurement), as cited in the ruling; Art. 27, 49 and 94 Cst. (Federal Constitution of the Swiss Confederation).
Fatal error Setting a statutory quota of temporary workers for all public construction sites without any link to the ability to perform the contract; or, on the contracting authority's side, restricting temporary staffing without justifying it.
Immediate workaround Contracting authority: restrict or exclude staff leasing in the call for tenders with a contract-specific reason. Contractor: review the tender documents and challenge any restriction that does not relate to contract performance.
1. The facts: two Neuchâtel articles against temporary work
On 5 September 2023, the Grand Conseil of Neuchâtel approved accession to the AIMP 2019 and, on the same day, adopted its cantonal public procurement act (LCMP/NE). Art. 9 para. 1 allows the contracting authority to restrict or exclude subcontracting or staff leasing in the call for tenders. Art. 10 imposes, for construction contracts, ceilings on temporary workers on site based on the number of permanent employees (table below), subject to exceptions that the Conseil d'État may specify. It was not included in the draft bill of the Conseil d'État: it originated from a parliamentary committee, with the stated aim of promoting permanent employment and countering casualisation.
An association of employment services companies and four staff leasing firms, active notably in the construction sector, lodged an appeal with the Federal Supreme Court on 23 October 2023 directly against these provisions. The act was promulgated on 27 October, scheduled to enter into force on 1 January 2024. On 5 December 2023, the presiding judge granted suspensive effect, with the Grand Conseil's consent. The judgment was handed down on 30 January 2025.
2. What Swiss law says
The applicable law is the AIMP 2019 (articles cited as referenced in the judgment). It contains no express rule on staff leasing. While it allows cantons to enact "implementing provisions" (Art. 63 para. 4), this is only in close connection with one of its provisions, to clarify it or implement it in a specific direction. The review is abstract: the Federal Supreme Court examines whether the provision can be interpreted in conformity with superior law.
Art. 9 para. 1: a reasoned limitation remains possible
The Federal Supreme Court views this provision as a restatement of an option already available under Art. 27 of the agreement (qualification criteria, which must be objectively necessary and verifiable for the specific contract). A restriction on temporary agency work is comparable to a limitation on subcontracting (Art. 31): it must be based on legitimate, contract-related grounds and be duly justified by the contracting authority. The judgment gives as examples work requiring extensive experience or substantial know-how, high technical complexity, hazardous work, confidentiality, or specific quality requirements such as the restoration of a historical building. It also refers to a Ticino case (2C_661/2019, 17 March 2021), where a cantonal rule was annulled, but where the Federal Supreme Court observed that a canton could allow contracting authorities to require, on a case-by-case basis, long-serving management staff or even a majority of personnel already under employment contract.
The provision also withstands scrutiny under other standards: the Federal Act on Employment Services and the Hiring of Services (it pursues a different purpose, namely quality performance and the efficient use of public funds), economic freedom (Art. 27 and 94 Cst.: proportionate measure that does not favour a specific trade), the Internal Market Act (presumption of conformity of the AIMP 2019, which was not rebutted) and international agreements. The risk of abusive application does not warrant annulling the provision in an abstract review: an aggrieved undertaking can challenge a concrete application.
Art. 10: a systematic quota breaches the AIMP 2019
This cap applies bindingly to contracting authorities, leaving no margin of discretion, across all construction contracts regardless of their specific features, even if the works require no specialist expertise. The legislative preparatory materials reveal an intention to combat temporary agency work, not to ensure proper performance of the contract. It therefore does not constitute an implementing provision of Art. 27. ATF 140 I 285, relied upon by the canton, concerned award criteria under the old intercantonal agreement, not qualification criteria. Art. 10 is annulled. The other paragraphs of Art. 9 (declaring temporary staffing in the bid, equal participation conditions, subcontracting) were not challenged; the judgment does not address them.
3. What this mistake actually costs
| Permanent employees | Maximum temporary workers (Art. 10 para. 2, annulled) |
|---|---|
| 1 to 3 | 2 |
| 4 to 6 | 3 |
| 7 to 11 | 4 |
| 12 to 20 | 5 |
| From 21 | 20% temporary workers, rounded up to the nearest whole number |
With a single permanent employee, the ceiling permitted two temporary workers: two out of three individuals on site (calculation). The limit therefore did not follow a constant percentage, nor the specific requirements of the contract.
| Item | Figures from the judgment |
|---|---|
| Enactment → appeal | 5 September 2023 → 23 October 2023: 48 days (calculation) |
| Appeal → judgment | 465 days (calculation), judgment of 30 January 2025 |
| Planned entry into force → judgment | 1 January 2024 → 30 January 2025: 395 days (calculation), with suspensive effect from 5 December 2023 |
| Costs and compensation | CHF 2'000 in court costs charged to the appellants; reduced compensation of CHF 3'000 paid by the canton |
For businesses, the cost was primarily the waiting period: both articles remained suspended for over a year (422 days, calculation), before one was annulled and the other upheld. A parallel case (2C_662/2023, construction companies and trade associations) was decided on the same day: inadmissible for one association, rendered moot for Art. 10 para. 1, dismissed for the remainder.
4. Site protocol: four practical rules
- Read the tender documentation before putting the team together. According to the judgment, any contracting authority may, in certain circumstances, restrict or exclude staff leasing in its call for tenders: check the restriction and its stated justification.
- Demand the reason for any restriction. According to the judgment, it must be objectively necessary for performance and substantiated; a blanket restriction disconnected from the contract is open to challenge.
- Contracting authority: document the contract-specific requirement. Specialist skills, hazard, confidentiality or particular quality standards: the examples given in the ruling relate to performance of the works, not employment policy.
- Price your permanent/temporary workforce split. Before submitting a bid, compare the cost of a permanent employee against that of agency personnel: a restriction applicable to your tender alters the calculation.
Temporary staffing, costs and tenders. To compare both models, see the guide salarié fixe ou intérimaire : calcul du point de bascule financier; for the legal framework, the guide location de services (LSE), intérim ou embauche fixe et responsabilité solidaire (LDét); to identify relevant contract opportunities, the radar des appels d'offres publics.
5. Frequently asked practical questions about this case
Can a public procurement authority exclude temporary workers from a tender?
Yes, but not as a blanket rule. Under ATF 151 I 113, the contracting authority may restrict or exclude staff leasing in the call for tenders if objectively necessary for the proper performance of the contract, and it must justify this requirement. The ruling cites high technical complexity, dangerous work, confidentiality or the restoration of a historical building.
Why was the temporary worker quota in Art. 10 LCMP/NE annulled?
Because it applied bindingly to all construction contracts, without discretion and with no connection to the capability to perform the contract. The legislative preparatory materials aimed to combat temporary agency work. However, the AIMP 2019 only permits cantons to issue implementing provisions strictly tied to one of its rules: Art. 10 breached this agreement.
Does this ruling apply outside Neuchâtel?
It concerns Neuchâtel law and the AIMP 2019, which Neuchâtel joined with effect from 1 January 2024. Its reasoning regarding cantonal implementing provisions is relevant for all cantons party to the agreement. The judgment notes that Genève and Ticino had not acceded to it and does not rule on their cantonal laws.
Official sources
- ATF 151 I 113 (judgment 2C_587/2023 of 30 January 2025) — Federal Supreme Court
- Judgment 2C_587/2023 of 30 January 2025 (full text) — Federal Supreme Court
- Intercantonal Agreement on Public Procurement (AIMP 2019), text published in the Neuchâtel systematic compilation
- Federal Constitution, Art. 27, 49 and 94 — Fedlex
Compliance notice. This article is a technical and educational analysis based on Swiss law in force and published decisions; the parties are anonymised as in the judgments. It does not replace the advice of a specialist lawyer for an ongoing dispute. Art Construction is independent of the SIA and CRB: their standards are not reproduced. Legal texts and judgments reviewed on 18 November 2026. This version is an automatic translation of the French article, which remains the authoritative text in the event of any discrepancy.