Practical guide

Overtime (CO) vs Statutory Overtime (LTr): +25% Premium, Compensation or Lump Sum

Swiss HR guide: difference between overtime (CO) and statutory overtime (LTr), 25% premium, compensatory leave and lump-sum pay for managers.

Table of contents
The 3 Major Site Risks
  1. Financial / Margin: Retroactive wage premium claims of 25% spanning several years during a disputed final account, representing unexpected costs between 5 000 CHF and 15 000 CHF per worker under art. 321c CO and art. 13 LTr.
  2. Legal / Joint commission / SUVA: Joint commission penalties for exceeding statutory working hour limits or failing to record working hours as required by art. 73 OLT 1, resulting in audit costs and back-payment contributions.
  3. Administrative / Acceptance: Blocking of joint certificates of compliance required to bid on public procurement tenders, caused by disputes over payslips and working time compensation.

Managing working hours on Swiss construction sites requires employers and HR managers to draw a rigorous line between overtime governed by private law and statutory overtime governed by public labour protection law. This distinction governs the payability of a wage premium of at least one-quarter, the rules for potential compensation through equivalent time off, and the validity of contractual lump-sum clauses applied to technical managers or operational staff.

Misclassification exposes company management to substantial financial claims before the competent labour court or during audits conducted by joint bodies. This guide details the rules applicable to site workers and managerial roles to secure your employment contracts, formalise written opt-out agreements, and maintain mandatory working time records in compliance with federal statutory and collective agreement requirements.

Legal frameworks: overtime (CO) and statutory overtime (LTr)

The distinction between overtime and statutory overtime rests on the interface between the private law of the individual employment contract and the public law provisions protecting worker health. Contractual analysis requires identifying the agreed volume of hours before examining whether statutory ceilings have been breached.

Overtime under the Code of Obligations (CO)

Overtime corresponds to hours worked beyond the weekly working hours set by the individual employment contract or applicable collective agreement, up to the statutory maximum weekly limit. Under art. 321c CO, the worker is bound to perform overtime to the extent they are capable of doing so and good faith permits. The employer may, with the worker's consent, compensate overtime with time off of at least equal duration. In the absence of compensation, the employer pays the standard wage plus a premium of at least one-quarter, unless agreed otherwise by written agreement, standard employment contract, or collective agreement.

Statutory overtime under the Swiss Labour Act (LTr)

Statutory overtime refers to hours worked beyond the statutory maximum weekly limit set by art. 9 LTr, namely 45 hours for technical staff and office employees, or 50 hours for other categories of manual trades or construction workers. Art. 12 LTr permits this exceptional excess in cases of emergency or extraordinary workload, up to a limit of two hours per day, except on non-working days or in cases of necessity, and without exceeding 170 hours per calendar year for a 45-hour week, or 140 hours for a 50-hour week. Under art. 13 LTr, this statutory overtime entitles the worker to a wage supplement of at least 25%, payable to technical and office employees starting from the 61st hour in a calendar year, unless compensated by time off of equal duration with the worker's consent.

Comparative table of legal frameworks applicable on site

Assessment criterion Overtime (art. 321c CO) Statutory overtime (art. 12 and art. 13 LTr)
Trigger threshold Beyond contractual or CLA hours, up to 45 h or 50 h Beyond the statutory weekly maximum (45 h or 50 h under art. 9 LTr)
Default compensation Standard wage plus a premium of at least 25% Supplement of at least 25% (from 61st h for technical/office staff)
Written opt-out on premium Permitted by written agreement, standard contract or CLA Prohibited (mandatory public law); time off in lieu permitted
Lump-sum clause without premium Permitted for managers if clearly stated in the written contract Null and void against the mandatory requirements of the LTr
Recording obligation Contractual tracking of working time performed (art. 319 CO) Mandatory register retained for at least five years (art. 73 OLT 1)

Common contractual drafting errors and financial impacts

A clause stating that "any hours worked beyond normal schedule are included in the fixed salary" is ineffective for statutory overtime governed by the Labour Act. Art. 13 LTr requires payment of the 25% supplement as soon as the statutory ceiling is exceeded, rendering blanket lump sums applied to site managers or foremen who do not meet the criteria of a high managerial function null and void. Moreover, failing to secure an individual written agreement to waive the premium on ordinary contractual overtime obliges the firm to pay the additional quarter under art. 321c CO retroactively, generating back payments ranging from 6 000 CHF to 12 000 CHF per employee upon departure.

Illustrative practical cases (typical scenarios on Swiss construction sites)

The following situations are constructed examples rather than actual construction sites, illustrating the application of contractual and statutory rules in Romandy.

Scenario 1: Structural work crew on a residential development (Vaud)

On a housing project in the canton of Vaud, a contractor employs eight bricklayers under a 40-hour weekly collective agreement schedule. Due to earthwork delays, the crew works 48 hours per week for four consecutive weeks. The hours between 40 and 48 hours constitute overtime under art. 321c CO, since the 50-hour ceiling set by art. 9 LTr for manual workers is not exceeded. The employer pays the 25% premium in accordance with the local CLA, amounting to a payout of approximately 350 CHF per worker per week, avoiding any statutory overtime excess under the LTr.

Scenario 2: Site manager and statutory ceiling overrun (Geneva)

A technical site manager on an administrative refurbishment project in Geneva works 52 hours per week for two months to coordinate finishing work. His contract stipulated 42 hours with a fixed salary and no express provision. Because the 45-hour ceiling under art. 9 LTr is exceeded by 7 hours per week, these hours constitute statutory overtime under art. 12 LTr. Art. 13 LTr mandates a 25% supplement beyond the 60th annual hour, which cannot be compensated through time off without the employee's express consent. The employer settles the balance by granting equivalent time off scheduled over the following quarter, thereby eliminating direct wage liabilities estimated at over 4 500 CHF.

Wages and social charges: free tools

Real cost of a tradesperson, employer contributions by canton, meal and travel allowances, notice periods under the collective agreement.

View payroll and HR tools

Frequently asked questions

What is the fundamental difference between overtime and statutory overtime?

Overtime exceeds the contractual schedule under art. 321c CO. Statutory overtime exceeds the maximum weekly working hours set out in art. 9 LTr (45 or 50 hours depending on the sector).

Can an employment contract for a site worker completely exclude the 25% premium?

Art. 321c CO allows parties to waive the premium for overtime by written agreement, but the 25% premium for statutory overtime under art. 13 LTr remains mandatory under statutory law.

What annual limit applies to statutory overtime for an installation crew?

Under art. 12 LTr, statutory overtime cannot exceed two hours per day, nor 140 hours per calendar year where the maximum weekly working hours are set at 50 hours within the firm.

How should overtime be paid when there is no specific contractual clause?

Unless time off in lieu has been agreed, the employer pays the agreed wage under art. 322 CO plus a premium of at least one-quarter under art. 321c CO (for example, 45 CHF gross for a 36 CHF base rate).

Can a technical manager waive working time tracking?

Art. 73a OLT 1 permits this waiver via a collective agreement if the employee enjoys substantial autonomy and earns a gross annual salary exceeding 120 000 francs, subject to a written agreement.

How long must an employer keep site working hour records?

In accordance with art. 73 OLT 1, records showing actual daily and weekly hours worked as well as breaks of at least thirty minutes must be retained by the employer for at least five years.

Managing working hours effectively protects the company against labour court litigation and safeguards operational margins during cantonal labour inspectorate audits.

To examine contractual workforce management on Swiss construction sites in greater detail, consult our dedicated guides: