Skip to content
Practical guide

1:5 Installation Details for Triple-Glazed Windows and Barrier-Free Thresholds <= 25 mm (Norm SIA 500)

1:5 execution details in Switzerland: triple-glazed window installation, joint sealing, and barrier-free thresholds up to 25 mm according to SIA 500.

Table of contents
The 3 Major Site Risks
  1. list-item Financial / Margin: Water infiltration at the base of a glazed unit resulting in major screed and parquet remediation, with an additional cost of around 15 000 CHF to 45 000 CHF under art. 368 CO.
  2. list-item Legal / Joint Body / SUVA: Design or anchoring errors under wind loads compromising the stability of heavy glazing, incurring liability under art. 229 CP in the event of personal endangerment.
  3. list-item Administrative / Acceptance: Rejection of a French door threshold exceeding the maximum 25 mm upstand set for barrier-free access by norm SIA 500, preventing conformity of the works.

Drafting 1:5 scale execution details for triple-glazed window installations is a critical step for architects and draftspersons in Switzerland. Integrating barrier-free French door thresholds, limited to a maximum upstand of 25 mm in accordance with the requirements of norm SIA 500, demands strict geometric coordination between the structural work, the floating screed, and the external joinery profiles.

This level of technical detail requires the exact definition of the internal air barriers, drainage beneath the frame, and liquid waterproofing connections according to norm SIA 271. An error in detailing the thermal break or managing surface run-off exposes the contractor to the remediation obligation under art. 368 CO, while putting the acceptance of the work at risk.

1:5 drafting principles for triple-glazed windows and barrier-free thresholds

The 1:5 scale detail formalises the continuity of the thermal envelope and the gravity drainage of rainwater. For a sliding or tilt-and-turn element fitted with triple glazing, the dead weight of the panes requires a non-deformable structural base set on adjustable galvanised steel brackets or on high-density composite insulation profiles. The finished interior floor level must align precisely with the top edge of the frame to keep within the maximum upstand permitted under norm SIA 500, while securing an effective exterior drainage system.

The core rule of detail drawings lies in maintaining airtightness on the warm side and weatherproofing that remains vapour-permeable on the outside. In compliance with norm SIA 180, the internal airtight seal consists of a vapour barrier adhesive tape bonded to the frame and hermetically connected to the concrete or masonry beneath the screed build-up. On the outside, below the access threshold, the waterproofing tie-in must comply with norm SIA 271 by incorporating a synthetic or bituminous waterproofing membrane beneath the drainage grating to avoid residual ponding caused by the minimal drop.

Multi-layer coordination and thermal bridge management at the glazing base

At the bare slab level, linear thermal bridging is broken by vertically aligning the façade insulation with the thermal break of the frame profile. Connecting the internal floating screed requires an edge insulation strip to prevent any rigid bridge transmitting impact sound under norm SIA 181. The lower fixing of the frame must be engineered to take the imposed loads without crushing the underlying waterproofing layers. The 1:5 detail specifies the exact layering sequence: reinforced concrete slab, vapour barrier, compressive-strength thermal insulation, separating sheet, screed, and finally the interior floor finish.

Comparative table of French door threshold configurations

Technical configuration Measured vertical upstand Water management under norm SIA 271 Thermal insulation and thermal bridges Conformity with norm SIA 500
Standard single-rebate recessed threshold Greater than 40 mm Direct vertical traditional waterproofing upstand Thermal break integrated into the base profile Non-compliant (major barrier for persons with reduced mobility)
Flat threshold with slotted drainage channel 15 mm to 20 mm Slotted channel connected to rainwater pipework High-load composite insulating sub-base Compliant without exemption (usable access threshold)
Flush profile with mechanical drop-down seal Less than 5 mm Drainage trough beneath removable external grating Continuous thermal break with load-bearing bracket Complies with the strictest barrier-free access standard
Raised threshold with surface-mounted external ramp 25 mm at the apex Overflow gargoyle and underside waterproofing Moderate continuity, complex screed tie-in Tolerated subject to strictly limited ramp slope
Waterproof threshold with retractable magnetic flap 0 mm (continuous flush surface) Integrated water drainage in draining profile body Insulation via reinforced double thermal break Compliant, recommended for high-traffic openings

Graphic drafting errors and financial impacts on the project

Omitting the external drainage channel from the 1:5 drawing leads to standing water against the bottom seals. Without an adequate water upstand, moisture penetrates the screed base during driving rain events. Remedying these defects requires fully removing the joinery, stripping the screed, and applying a replacement liquid waterproofing membrane, generating remediation costs of around 18 000 CHF to 35 000 CHF under art. 368 CO. Furthermore, an incorrect level coordinate for the exterior finish relative to the profile can stall hand-over for failure to meet accessibility requirements. If the contractor identifies a technical drainage issue on the architect's drawing, they must report the defect without delay under art. 365 para. 3 CO.

Illustrative practical cases (typical scenarios on Swiss construction sites)

The following figures are illustrative examples intended for technical analysis and do not represent specific contractual situations.

On a multi-family housing development in the canton of Vaud, installing eight large triple-glazed sliding doors required a flush threshold towards the loggias. The original 1:5 execution plan omitted the installation tolerance for the external grating and showed direct bedding on simple mortar, producing a linear thermal bridge where it met the balcony slab. The planners corrected the drawing by incorporating a reinforced recycled-plastic thermal expansion profile beneath the bottom track, combined with a slotted drainage channel laid in front of the unit to maintain an effective upstand of 18 mm. This detail complies with norm SIA 500 while preventing water ingress under wind pressure.

During an administrative building conversion in the canton of Fribourg, the work involved creating a barrier-free access between a cafeteria and an internal courtyard. Finished height constraints set by the existing tile floor prevented any lowering of the structural work. The architectural firm opted for a 1:5 execution detail featuring a modular threshold with a mechanical sealing flap combined with a reinforced liquid membrane turned up beneath the profile. The sizing of cross fixings was coordinated to resist wind loads without puncturing the waterproofing tray, ensuring durability in line with Swiss technical rules.

Surfaces, standards and permits: free tools

SIA 416 floor areas and volumes, cantonal zoning ratios, U-values and dew points, acoustics, planning enquiry requirements.

View engineering tools

Frequently asked questions

How can the 25 mm maximum upstand of norm SIA 500 be reconciled with waterproofing?

The draftsperson combines a recessed grated drainage channel with a continuous waterproofing membrane. The joinery profile incorporates a pressure-tight mechanical seal, limiting additional costs to around 450 CHF.

Who bears the risk of water ingress under the Code of Obligations for a flat threshold?

Under art. 365 CO, the contractor must promptly notify the client of any risk. If the client insists on the detail without a channel, art. 369 CO releases the contractor from liability for defects attributable to those instructions.

Where should triple glazing be placed in the 1:5 section to minimise thermal bridging?

The glass unit is aligned with the axis of the façade insulation. This thermal continuity eliminates linear heat loss, preventing later remediation that could reach around 1200 CHF per opening.

What is the designer's criminal liability when detailing fixings for heavy sashes?

If a heavy frame fails and injures an occupant, the responsible party faces penalties under art. 229 CP if they intentionally or through negligence breached the recognised rules of the building trade.

Under art. 367 CO, for immovable work, the client has 60 days to report observed defects. Art. 371 CO sets the limitation period for defect claims at five years.

How can acoustic compatibility be ensured at the French door threshold under current standards?

The 1:5 detail must isolate the base profile from the internal screed. Installing a continuous resilient strip prevents structure-borne noise, with a material investment of around 35 CHF.

Accurate 1:5 sections ensure compliance with accessibility requirements and prevent water ingress issues on the thermal envelope. Explore execution detailing further with our technical guides:

Art Construction is an independent company: it is not affiliated with the SIA, CRB, SUVA, or KBOB. Referenced norms and standards point to publications from these bodies; only official versions are legally binding.