Table of contents
The 3 Major Site Risks
- Financial / Margin: Forfeiture of claims for adverse weather or unforeseen delays, potentially representing a financial impact ranging from 40'000 CHF to over 180'000 CHF on the final account, due to the lack of daily records enforceable under standard SIA 118 and art. 365 CO when circumstances jeopardise the regular or timely execution of the work without the contractor notifying the client.
- Legal / Joint Body / SUVA: Work stoppage ordered by labour inspectors or liability incurred by local site management and the foreman under art. 5 OTConst regarding the appointment of a competent person responsible for safety, exposing them to criminal penalties under art. 229 CP for knowingly endangering life or limb by violating recognised construction rules.
- Administrative / Acceptance: Gridlock during joint verification or rejection of claims for extra work during acceptance of the work under standard SIA 118 and art. 366 CO, in the absence of mutually verified records of work stoppages, actual workforce numbers, and successive technical operations.
On Swiss construction sites, keeping a meticulous daily site log is a core mutual duty shared between local site management under SIA 112 Phase 52 and the foreman representing the contractor under standard SIA 118. This document records hour by hour local weather data, exact headcounts by trade, heavy machinery in operation, and key technical events. Serving as the project's living record, it protects the client, lead consultants, and executing contractors alike against late disputes regarding deadlines and unforeseen ground or site conditions.
Failing to maintain daily records turns any construction dispute into an evidential dead end before ordinary courts or arbitral experts. The site log substantiates operational realities, the practical implementation of safety measures required under art. 6 OTConst regarding helmet-wearing, and the coordinated management of trade interfaces. Drafting it jointly and validating it on a regular basis provides watertight contractual security for all construction partners in French-speaking Switzerland.
Mandatory site log entries and daily logging protocol
In site supervision practice under SIA 112 Phase 52, local site management coordinates work traceability in direct collaboration with the structural work foreman and finishing work chargehands. Daily recording is not a mere administrative formality; it is a legal act documenting work progress. Accurate weather data must be entered every morning upon starting work: minimum and maximum temperatures, average wind speed, measured precipitation, and relative humidity. These records prove any technical impossibility of applying specific materials or justify special protective measures during severe heat or freezing temperatures pursuant to art. 37 OTConst.
Nominal and numerical headcounts form the second vital pillar of the log. The foreman logs the workers on site by main contractor and subcontractor, detailing their trade qualifications from apprentice to certified plant operator. This headcount is supplemented by an inventory of heavy plant mobilised on site—notably tower cranes, excavators, air compressors, and batching plants—distinguishing actual operating hours from downtime caused by breakdowns or bad weather. Regarding health and safety, the log records the name of the competent person responsible for occupational safety and health protection appointed on the construction site under art. 5 OTConst.
Recording technical events calls for unmistakable descriptive accuracy. Material deliveries to the site must be thoroughly tracked: delivery slip numbers for ready-mix concrete, exposure classes, incorporated admixtures, and the exact start and finish times of concrete pouring. Any unexpected situation affecting the foundation soil, any unmapped underground utility strikes, or any water ingress must be logged without delay. Under art. 365 CO, if the ground provided by the client or materials supplied by them are found to be defective, or if any other circumstance jeopardises the proper or timely execution of the work, the contractor must inform the client immediately, under penalty of bearing the consequences. The site log serves as the initial written record of this formal notice.
Comparison table: logging practices and evidentiary value
The difference between a vague entry and a record compliant with the requirements of site management and the construction contract determines the outcome of subsequent financial claims.
| Site log section | Defective or disputable phrasing | Phrasing compliant with Swiss standards | Legal weight and financial impact |
|---|---|---|---|
| Weather conditions | "Continuous rain, work stopped in the afternoon." | "Continuous rain from 10:00 to 17:00 (28 mm recorded). Slab concreting level 2 stopped following delivery refusal from the batching plant." | Evidence of technical impediment justifying an extension of the contractual deadline under standard SIA 118 without penalties. |
| Workforce and subcontracting | "6 workers on site for masonry." | "General contractor: 1 foreman, 3 qualified masons. Steel subcontractor: 2 declared steel fixers. Badge checks carried out." | Compliance with the duty of diligence regarding subcontractors and substantiation of output rates set out in the master schedule. |
| Ground conditions and excavations | "Excavation base too soft, waiting for engineer." | "Resurgent water ingress at base of excavation along grid lines C-D. Unstable ground. Notice sent to civil engineer to inspect shoring and slope battering." | Formal notice within the meaning of art. 365 CO and compliance with excavation requirements under OTConst, avoiding the transfer of ground remediation costs. |
| Work stoppage for safety reasons | "Guardrail issue on north facade." | "Perimeter edge protection missing on floor edge higher than 2 m. Formwork halted until compliant guardrails installed per art. 23 OTConst." | Prevention of liability for breach of recognised construction rules under art. 229 CP and verifiable tracking of safety measures. |
| Unforeseen work and daywork | "A few extra hours to clear the embankment." | "Scaling unstable rock blocks on north embankment: 2 workers for 3h00, 1 15-t excavator for 3h00. Daywork sheet countersigned." | Validation of the right to payment for daywork under standard SIA 118, preventing rejection during the final account. |
Recurring logging errors and financial impact on final accounts
The most frequent failure seen on construction sites is drafting the log retrospectively or weekly. Reconstructing headcounts, temperatures, or subcontractor operations from memory several days later deprives the document of its evidentiary value before Swiss courts. In disputes over delays under art. 366 CO, the client may claim the contractor is in default without the contractor being able to cite specific weather events or third-party disruptions. Financial losses resulting from contractual penalties under art. 160 CO frequently reach amounts of 35'000 CHF to over 120'000 CHF for just a few weeks of unsubstantiated delay.
The second classic mistake is the lack of joint sign-off. A site log kept unilaterally by the foreman in the site hut without regular signature by site management constitutes mere party assertion. Conversely, site management remarks not countersigned by the contractor create damaging uncertainty. When variation orders occur without immediate logging of the plant and labour deployed, the contractor risks having their daywork hours rejected. On its side, a site management team failing to record visible defects as soon as they appear risks jeopardising defect notification under art. 367 CO, where the statutory timeframe for immovable works is 60 days following delivery.
Illustrative practical cases (typical scenarios on Swiss construction sites)
The following figures and situations are illustrative case studies designed for technical and legal analysis.
Standard Scenario 1: Managing winter weather in an Alpine region (Canton of Valais)
On a construction site for a three-storey residential building in Valais, the structural work contractor employs an average workforce of twelve workers. In January, a severe cold snap pushes morning temperatures down to between minus eight and minus twelve degrees. The foreman logs the temperature readings in the digital site log daily at 07:00 and 13:00, accompanied by timestamped photographs showing frozen aggregates and the impossibility of pouring reinforced concrete without major structural risks. Local site management validates these entries daily via electronic signature.
Thanks to this rigorous record-keeping, the contractor serves a formal notice of work suspension to safeguard the quality of the works and comply with worker safety in severe cold under art. 37 OTConst. During final account settlement, the client claims a contractual penalty of 60'000 CHF for a three-week delivery delay. The jointly signed site log, corroborated by official meteorological data, proves the absence of fault on the contractor's part under art. 97 CO, securing the corresponding extension of time without financial penalties.
Standard Scenario 2: Uncovering an unstable ground pocket during excavation (Canton of Vaud)
During earthworks for an office building in the canton of Vaud, the excavation contractor operating a 22-tonne excavator strikes an unexpected water resurgence that triggers local collapses of the trench wall. The foreman halts operations immediately in the affected area and logs the incident in the site log: precise location, volume of collapsed soil, and perimeter safety measures deployed. Indeed, the OTConst mandates that excavation slopes must be suited to ground stability and that appropriate precautions must be taken whenever ground stability is compromised.
Site management, notified via the site log entry and written notice, summons the geotechnical engineer to assess overall stability and specify supplementary shoring. The immediate, detailed log entry provided the material proof of immediate notice required by art. 365 para. 3 CO regarding defective ground. As a result, the contractor was able to justify daywork costs of 24'500 CHF for emergency pumping and stabilisation, which were approved without reservation by the client in the monthly progress payment.
Contracts and SIA 118: free tools
Advance payments and retentions, surety bonds, price escalations, daywork reports, subcontractor monitoring.
Frequently asked questions
Who must sign the daily site log between site management and the contractor?
The foreman records factual conditions on site and site management countersigns the document. Under standard SIA 118, this joint signature validates recorded headcounts, weather, and deliveries, avoiding disputes over unexpected work stoppages averaging roughly 4 500 CHF per bad-weather day.
What is the evidentiary value of photographs included in daily reports?
A timestamped, geolocated photo proves the actual condition of works before they are covered up. Under the Code of Obligations (CO), it documents adherence to technical standards during construction and acts as critical evidence should remedial works estimated at 12 000 CHF later be demanded by the client.
How do you record a work stoppage ordered for safety reasons?
The competent person designated under art. 5 OTConst records the work stoppage order and the exact reason in the logbook. If a situation violates the recognized rules of construction under art. 229 CP, site management formalises the event without delay to prevent any personal injury on the construction site.
In the event of an unstable excavation, what technical details should be entered in the daily report?
The logbook records the excavation depth and the condition of the trench shoring pursuant to art. 68 OTConst. If the trench walls pose a risk of collapse during heavy rainfall, the appropriate shoring measures are logged immediately to prevent an emergency response extra cost of around 8 000 CHF caused by bad weather.
How do you track the disposal of bituminous materials or demolition rubble?
The report specifies the type of mineral waste streams and the transport notes pursuant to art. 20 OLED. Systematic sorting recycles demolition concrete, avoiding cantonal environmental penalties and uncontrolled disposal fees that can reach 6 000 CHF per contaminated skip.
What impact does the site logbook have on the warranty periods of the works?
The logbook establishes the exact completion date of parts of the works prior to acceptance inspections. For an immovable work, the client's warranty rights expire after five years under art. 371 CO, a period calculated precisely thanks to the daily entries recorded without interruption by local site management.
Rigorous maintenance of the daily logbook by local site management and the foreman guarantees unassailable technical traceability in the face of construction uncertainties. To secure all your administrative and contractual project supervision on Swiss construction sites, explore our specialised methodological protocols:
- Weekly Meetings, Daily Log and Evidentiary Value of Site Minutes in Switzerland
- How to Draft Legally Watertight Site Meeting Minutes in Switzerland
- Deadline for Contesting Site Minutes: Legal Effect of Silence and Contractual Clauses
- MEP / Structural Work Spatial Coordination and Technical Integration: Clash Prevention Protocol Before Pouring