Running Dimensions and Elevations (±0.00 and m s.m. Pierre du Niton): SIA 400 Dimensioning Rules

Master running dimensions and elevation rules (Pierre du Niton, m s.m.) on Swiss architectural plans according to the SIA 400 standard.

Table of contents
The 3 Major Site Risks
  1. Financial / Margin: An absolute altimetric reference error leads to excavation cost overruns. This offset results in an illustrative 15 % overrun on earthworks, impacting the budget under the SIA 118 standard.
  2. Legal / Joint Body / SUVA: Exceeding legal height templates set by the commune due to an erroneous dimension causes a construction site shutdown under the Federal Act on Spatial Planning (LAT).
  3. Administrative / Acceptance: The refusal of an occupancy permit tied to ambiguity between absolute altitude and relative level blocks acceptance and triggers liability under the Code of Obligations (CO).

The accuracy of running dimensions and elevations structures every construction project in Switzerland. According to the SIA 400 standard, the reference level, set at ±0.00 for the ground floor, is tied to the national altimetric system of the Pierre du Niton (m s.m.). Mastering this dual reading—relative for execution and absolute for the land—ensures the conformity of the structure.

Faulty representation of levels distorts setting out by the surveyor and the pouring of slabs. The SIA 400 standard dictates the exact symbology for altimetric benchmarks and structural or finished levels. Applying these guidelines prevents interpretation errors on the construction site and validates compliance with regulatory building envelopes.

Dual Altimetric Dimensioning Principle according to the SIA 400 Standard

On Swiss plans, the SIA 400 standard requires a strict distinction between dimensions relative to the building and absolute dimensions tied to the land. The reference level, generally the finished floor of the ground floor, is defined by the relative dimension ±0.00. This benchmark value allows contractors to orient themselves easily during the erection of the structure.

This zero point must imperatively be tied to the Swiss national altimetric system, whose fundamental datum is the Pierre du Niton (elevation of 373,60 m s.m.). On the site plan, absolute elevation is expressed in metres above sea level (m s.m.). Site management and the surveyor rely on this dual reading to ensure that the layout complies with the building profiles approved by the commune, in accordance with the Federal Act on Spatial Planning (LAT).

Graphic representation follows strict rules. A solid triangle indicates a finished level, including the screed. An open triangle indicates a structural level, such as the concrete slab. This distinction is critical to coordinate structural work and finishing work, and to avoid disputes governed by the Code of Obligations (CO) regarding defects in the work.

Comparative Table: Representation of Levels and Elevations (SIA 400)

The table below details the symbology of altimetric benchmarks on Swiss plans.

Benchmark type SIA 400 symbology Unit and format Main application Target trade
Finished level (floor) Solid triangle pointing down Relative dimension (e.g. +2.80) Final height including floor finishes Finishing work, joiners
Structural level (slab) Open triangle pointing down Relative dimension (e.g. +2.65) Top of concrete slab Masons, structural builders
Absolute elevation Cross with topographic benchmark m s.m. (e.g. 412.50) General building setting out Surveyor, earthwork contractor
Excavation bottom Open triangle with hatching Relative or absolute dimension Maximum excavation depth Earthwork contractor
Legal building envelope Specific dimension line m s.m. and relative height Compliance with municipal regulations Site management

Frequent Dimensioning Errors and Financial Consequences

Misinterpreting structural and finished levels is a costly failure. When a mason pours a slab by mistakenly relying on the finished level dimension instead of the structural level, the clearance needed for acoustic insulation and the screed disappears. This mistake often forces mechanical milling of the slab or door height adjustments. Illustrative extra costs to rectify a slab of 100 square metres easily reach around 15 000 CHF, not to mention delays.

Another major error involves confusing reference systems. If the surveyor sets out the building with an offset relative to the Pierre du Niton m s.m. datum, the structure risks exceeding the maximum height allowed by the commune. Non-compliance with building envelopes can also lead to an immediate construction site shutdown by the competent authorities. In that case, demolition of the surplus section can be mandated. Remedial costs for an incorrectly elevated roof structure frequently exceed 40 000 CHF.

Illustrative practical cases (typical scenarios on Swiss construction sites)

The figures presented below are illustrative examples demonstrating the application of dimensioning rules.

Scenario 1: Residential building (Canton of Vaud)

Context: A project requires deep excavation. The workforce numbers 12 workers. The plan shows a reference elevation of 450.20 m s.m., but the excavation execution plan lists only relative dimensions (-3.50).

Resolution: The earthwork contractor risks digging too deep if the ±0.00 benchmark is not marked on site. Site management requires dual dimensioning at every level. The surveyor places batter boards with the absolute elevation. This precision prevents over-excavation, backfilling for which would have cost approximately 8 500 CHF.

Scenario 2: Office renovation (Canton of Geneva)

Context: Refurbishment of an open floor plan with 8 installers. The original drawings lack clarity regarding the nature of the triangle markers.

Resolution: The joiner orders doors based on a dimension assumed to be the finished level. The architect redraws the sections applying the SIA 400 standard: a solid triangle for the finished floor (+0.00) and an open triangle for the structural slab (-0.15). This clarification saves an order with an estimated value of 22 000 CHF.

Surfaces, standards and permits: free tools

SIA 416 floor areas and volumes, cantonal zoning ratios, U-values and dew points, acoustics, planning enquiry requirements.

View engineering tools

Frequently asked questions

How do you define the ±0.00 level on a Swiss plan?

According to the SIA 400 standard, the ±0.00 level corresponds to the finished ground floor. It is tied to the absolute elevation in metres above sea level (m s.m.) to prevent any setting-out errors.

What is the difference between structural and finished dimensions?

The structural dimension indicates the level of the load-bearing slab, while the finished dimension includes the screed. The SIA 400 standard requires them to be clearly distinguished on drawings.

Why use the Pierre du Niton reference datum?

The Pierre du Niton datum guarantees a unified altimetric reference in Switzerland. It secures the surveyor's layout and prevents height disputes during building permit applications.

How do you dimension an access ramp or inclined plane?

The SIA 400 standard requires stating the starting and ending elevations, along with the gradient as a percentage. A directional arrow systematically points towards the lowest level.

What should you do if the natural ground differs from the drawings?

The contractor must inform site management immediately, in accordance with the Code of Obligations (CO). Running dimensions must be verified by a surveyor before proceeding with excavation or earthworks.

How are dimensions represented on a vertical section?

Dimensions are indicated by a solid triangle for finished levels and an open triangle for structural levels, aligned vertically with their respective values under the SIA 400 standard.

Mastering altimetric dimensions secures execution on Swiss construction sites. Explore our other technical guides: