The 3 Major Site Risks
- Financial / Margin: Confusion between yellow (demolition) and red (new) resulting in unplanned work. Indicative extra costs of around 15 % on structural work and disputes arising under the contract for work (Code of Obligations (CO)).
- Legal / Joint / SUVA: Demolition of existing elements (grey) containing unidentified asbestos, in breach of art. 32 OTConst. Immediate site stoppage.
- Administrative / Acceptance: Planning application rejected by the municipality due to non-compliance with standard SIA 400, stalling the building permit (Federal Act on Spatial Planning).
In Switzerland, drawings for alteration and renovation projects follow strict chromatic coding under standard SIA 400. This standard ensures clear, unambiguous communication between the architectural office, the engineers, and the contractors. The principle relies on three colours: grey for existing elements to be retained, red for new construction, and yellow for demolition.
Applying these conventions rigorously prevents costly mistakes during execution. A poorly coded plan can lead to the accidental removal of a load-bearing wall, triggering the draughtsperson's liability. In addition, these colour plans are required by municipal authorities for the public planning inquiry. This guide details the requirements of standard SIA 400 to help you structure your renovation project files.
Application of standard SIA 400
For any refurbishment project, clear graphic documentation is critical for site management. Standard SIA 400 requires strict chromatic coding in Switzerland: grey for existing, red for new, and yellow for demolition. This standardisation extends all the way to execution drawings. It provides a visual representation of the contract for work governed by the Code of Obligations (CO), defining the exact scope of works due by the contractor with utmost precision.
Superimposing colours requires great care. Grey elements, representing the fabric to be preserved, are drawn with fine lines to keep the drawing legible. Red and yellow must stand out clearly. When planning demolition works (yellow), the employer takes hazardous materials into account. If asbestos is suspected, the employer takes the necessary protective measures under art. 32 OTConst before any work begins.
Managing overlaps and structural openings
Creating openings in existing walls requires combining colours: the original wall remains grey, the section to be taken down is hatched in yellow, and new lintels are drawn in red. This precision ensures site safety. Erecting temporary shoring, whose load-bearing capacity must meet the requirements of art. 77 OTConst, relies on masons understanding the yellow zones accurately.
Comparison table: Chromatic coding and hatching (SIA 400)
The table below sets out the drafting conventions and the risks associated with misinterpreting the drawings.
| Project element | Colour code (SIA 400) | Standard graphic representation | Technical point to watch | Illustrative financial risk |
|---|---|---|---|---|
| Existing wall to be retained | Grey (or fine black) | Fine line, light grey solid fill or existing-structure hatching | Do not obscure new dimensions with an overly dark grey | Delays reading drawings (approx. 500 CHF) |
| Wall or slab to be demolished | Yellow | Dashed lines or solid yellow fill | Check for hazardous pollutants before demolition starts | Site shutdown (from 5'000 CHF) |
| New masonry | Red | Thick line, red solid fill or specific hatching | Differentiate reinforced concrete from clay brick using hatching | Ordering error (2'000 to 10'000 CHF) |
| Opening cut into existing fabric | Yellow (opening) / Red (lintel) | Yellow zone overlapping red contours | Install props before taking down the yellow zone | Structural damage (over 20'000 CHF) |
| Added external thermal insulation | Red (or dedicated colours) | Wavy or cross-hatching depending on the material | Detail the junction with the existing grey façade properly | Waterproofing defects (3'000 to 8'000 CHF) |
Common mistakes and financial consequences
Printing renovation drawings in black and white for the construction site is a major mistake. Red and yellow turn into indistinguishable shades of grey, leading to the accidental demolition of newly built elements. The resulting rework costs and schedule delays often range between 5'000 and 15'000 CHF on a standard refurbishment. Furthermore, misrepresenting demolition works can cause falls from height if floor openings are not anticipated and protected with edge protection or robust coverings, as required by art. 25 OTConst.
Illustrative practical cases (typical scenarios on Swiss construction sites)
These figures and scenarios are illustrative examples and do not represent actual construction sites.
Scenario 1: Farmhouse renovation (Canton of Fribourg)
On a heavy alteration project involving 12 workers, the design creates wide openings in rubble-stone load-bearing walls. Standard SIA 400 was applied to the execution drawing: the main wall is grey, the openings are yellow, and the new reinforced concrete frames are shown in red. This allowed the masonry contractor to plan saw-cutting and propping accurately. Clear plans prevented a partial collapse of the structure, avoiding any breach of the recognised rules of construction (art. 229 CP).
Scenario 2: Building vertical extension (Canton of Vaud)
This project involved taking down the existing roof to build a timber-frame penthouse. The drawings indicated the existing roof structure in yellow and the new structure in red. Site management noted that the sarking membrane (yellow zone) contained asbestos. Works that release substantial amounts of hazardous asbestos fibres into the air may only be carried out by asbestos abatement firms recognised by CNA (art. 82 OTConst). The colour drawing isolated the volume requiring remediation, avoiding a site shutdown.
Surfaces, standards and permits: free tools
SIA 416 floor areas and volumes, cantonal zoning ratios, U-values and dew points, acoustics, planning enquiry requirements.
Frequently asked questions
How should a wall to be demolished be marked under standard SIA 400?
Standard SIA 400 requires yellow for all demolition. Yellow hatching marks the zone to be removed, preventing any confusion during works on the construction site.
Does the colour code apply to Plumbing & Sanitary Installations drawings?
Yes, this standard SIA 400 requirement applies to Swiss execution drawings. Existing pipes remain grey, new ones are red, and decommissioned lines are shown in yellow.
What colour should be used for an existing element to be kept but remediated?
The retained element is drawn in grey under standard SIA 400. Specific remediation work is clarified with a text note or distinct hatching defined in the drawing legend.
What should you do if the municipality requires black-and-white drawings?
Although standard SIA 400 recommends these colours, some authorities accept specific hatching patterns. Red becomes dense hatching, while yellow is rendered with dashed lines.
How can demolition and construction costs be estimated?
Costs are calculated per m³ or m² according to the CFC. For unit prices ranges in CHF, consult the Indice ACIP tables.
Who is liable if a colour coding mistake leads to accidental demolition?
The author of the drawings bears liability. However, the contractor must also report any discrepancies before executing the works, in accordance with the duty of care under the Swiss Code of Obligations (CO).
Applying the grey, red, and yellow colour code from standard SIA 400 ensures clear, unambiguous renovation drawings. To explore Swiss drafting standards in greater detail, see:
- Standard SIA 400: Complete Guide to Architectural and Execution Drawings in Switzerland
- Scales 1:100 vs 1:50 Under Standard SIA 400: Graphic Level of Detail Expected in Switzerland
- Cumulative Dimensions and Levels (±0.00 and m a.s.l. Pierre du Niton): SIA 400 Dimensioning Rules
- Standardised Material Hatching (SIA 400): Reinforced Concrete, Masonry, Insulation, Timber and Natural Ground