The 3 Major Site Risks
- Financial / Margin: Immediate debit of contractual delay penalties, often amounting to several thousand CHF per working day as agreed by the parties (art. 160 CO), due to failing to notify the site management immediately of unforeseeable weather disruptions pursuant to norm SIA 118 and art. 365 CO.
- Legal / Joint Body / SUVA: Wrongful continuation of work under freezing conditions, driving rain or extreme heatwaves without taking the necessary measures to protect workers (art. 37 OTConst) or the safety criteria of the National Framework Agreement for the Swiss Main Building Trade, exposing the site to an administrative shutdown by the labour inspectorate or SUVA.
- Administrative / Acceptance: Forfeiture of the contractual right to an extension of time following a failure to submit a formal, substantiated notice, paving the way for threatened default substitution or contract termination under art. 366 CO with subsequent blocking of final statements and inspection of the work.
On Swiss construction sites, meteorological hazards such as exceptional precipitation, prolonged frost, summer heatwaves and high wind gusts preventing crane operations are the primary cause of critical path disruptions. For site management, site supervisors and project managers, distinguishing between standard weather risks, which must be incorporated into the contractor's initial planning in accordance with its duty of care under art. 364 CO, and extraordinary bad weather granting an entitlement to an extension of time under norm SIA 118 requires impeccable daily traceability.
This operational guide clarifies the criteria for unforeseeability and technical impact on work progress, the requirements for certified weather reports and the immediate notification procedure mandated by art. 365 para. 3 CO and norm SIA 118. It outlines the evidentiary approach needed to defeat liquidated damages claims under art. 160 CO and protect contractors' rights when updating construction schedules.
Classification of bad weather and extension rules under norm SIA 118
The impact of a weather event on the contract schedule does not arise from a mere pause in activity. Norm SIA 118 makes any extension of time contingent on meeting specific cumulative conditions. The disruption must lie outside the contractor's control, be extraordinary compared to local seasonal statistical data, and demonstrably affect a critical path task on the execution schedule.
Customary or foreseeable weather conditions for the project location do not constitute legitimate grounds for an extension. The contractor is deemed to have accounted for standard seasonal hazards typical of the Swiss climate in its initial tender, such as moderate snowfall at high altitudes or typical spring rain on the Central Plateau. When conditions exceed multi-year averages or make work technically impossible according to trade standards, a contractual extension can be claimed.
Site management reviews time adjustment requests by cross-referencing official weather records against specific construction contract requirements. For initial cost estimation questions and responding to calls for tenders, consult the dedicated tenders section. Likewise, detailed breakdowns of raw unit prices tables can be found in the ACIP index.
Notification duties and formal reporting procedure
Pursuant to art. 365 para. 3 CO, if any circumstance jeopardises the proper or timely execution of the work, the contractor must immediately notify the client, under penalty of bearing the consequences. This written communication is an indispensable prerequisite for any subsequent acceptance of a schedule delay. Under norm SIA 118, the disruption notice must state the exact nature of the impediment, its foreseeable impact on the completion date, and the protective measures taken to mitigate delay.
The site logbook and site meeting minutes serve as decisive evidentiary tools. Site management must log fixed-hour temperatures, wind speeds from crane anemometers, rainfall depths, subgrade ground conditions, and the number of idle or reassigned workers on sheltered secondary tasks daily. Without mutually agreed documentation, any subsequent claim for a schedule addendum is severely compromised.
The duty of care under art. 364 CO also requires the contractor to take reasonable internal reorganisation measures before claiming a deadline postponement. If indoor workstations or non-critical path tasks can be brought forward without disproportionate extra costs, site management is justified in refusing a full extension equal to the total hours of bad weather logged.
Occupational health and safety and weather constraints on site
Managing weather-related stoppages directly intersects with mandatory worker protection regulations. Art. 37 OTConst provides that when work is carried out in direct sunlight, severe heat or extreme cold, necessary measures must be taken to protect workers. When a heatwave or extreme frost prevents safe operations without risking physical health, suspending physical work becomes a legal employer obligation under art. 82 LAA and art. 3 OPA.
Wind gusts require heightened vigilance regarding lifting equipment and temporary structures. Under art. 17 OTConst, measures must be taken at workstations and access routes to prevent workers from being endangered by collapsing building components or falling objects and materials. Mandatory weather vaning of tower cranes in high winds halts vertical transport, bringing formwork assembly and concrete pours to a complete stop.
During heavy rainfall or rapid snowmelt, excavation stability is directly compromised. Art. 75 OTConst specifies that the slope of trench and excavation walls must be adapted to ground resistance and that appropriate measures must be taken if stability is compromised by heavy rain, thawing, structural loads or vibrations. Halting earthworks or special foundations work caused by soil saturation is therefore a strict public safety requirement.
Intentionally violating safety rules during hazardous weather engages criminal liability under art. 229 CP, which punishes anyone who breaches professional trade standards and knowingly endangers life or bodily integrity with a custodial sentence of up to five years or a monetary penalty. For matters involving relief crew recruitment or calculating bad-weather compensation on payslips, managers should consult the HR and employment modules.
Comparative summary of weather hazards and contractual criteria
| Weather hazard | Technical and safety requirements | Critical path impact | Right to extension (norm SIA 118) |
|---|---|---|---|
| Prolonged day and night frost | Concreting specifications and art. 37 OTConst for workforce health protection. | Halt on pouring external structural elements and exterior facade plastering. | Recognised if duration significantly exceeds regional statistical averages. |
| Continuous torrential rain | Art. 75 OTConst regarding slope stability and trench excavation pit walls. | Subgrade compaction impossible and risks of slope collapse. | Recognised for exceptional water volumes that prevent plant and machinery access. |
| High winds and gale gusts | Art. 17 OTConst on protection against falling objects; crane weather vaning. | Halt on heavy lifting, placement of precast components and structural timberwork. | Recognised provided crane shutdowns halt all concurrent critical path tasks. |
| Severe heatwave | Art. 37 OTConst and occupational health directives; rapid concrete desiccation. | Restricted concreting time windows and slowed rebar tying pace. | Partial extension if organisational measures cannot prevent schedule slippage. |
| Early snowfall | Duty to clear snow from site access routes, work platforms and scaffolding. | Material delivery routes blocked and trench shoring inaccessible. | Recognised only if snowfall dates are abnormal for the site's elevation. |
Recurring management errors and financial impacts
The primary pitfall observed is the failure to issue immediate formal notification. A contractor waiting until the monthly meeting to report ten cumulative days of site stoppage risks outright rejection of the claim. Under art. 365 para. 3 CO, silence forfeits claims and keeps original contractual deadlines running, triggering liquidated damages under art. 160 CO, which typically range between 1 000 and 3 000 CHF per day of unexcused delay.
The second mistake lies in conflating general bad weather with the actual impact on the critical path. If rain stops external works while indoor structural work continues unhindered, completion of the main structure is not compromised. Site management must reject blanket claims that fail to demonstrate the exact planned dependency chain.
The third failure involves not taking mitigation measures. A contractor that fails to adapt indoor work stations or refuses to reschedule non-critical tasks breaches the duty of care under art. 364 CO. Costs arising from unjustified, passive downtime remain entirely the responsibility of the executing contractor.
Illustrative practical cases (typical scenarios on Swiss construction sites)
The figures and scenarios described below are illustrative examples designed to clarify how contract rules apply on Swiss construction sites in practice.
Structural work scenario under high winds in suburban Vaud
On a residential development project of three apartment buildings in the canton of VD, the master schedule places third-floor concrete shear wall construction on the critical path. Over two consecutive autumn weeks, wind gusts compel site management to take the tower crane out of service for six full days to ensure safety pursuant to art. 17 OTConst. The crew of twelve masons can neither hoist formwork panels nor lift reinforcing steel.
The contractor formally notifies site management of each stoppage within twenty-four hours, provides certified anemometer data and offers to redeploy part of the workforce to non-critical basement masonry tasks. After reviewing actual site progress, site management approves an addendum granting a formal four-working-day extension for structural work completion, thereby avoiding liquidated damages under art. 160 CO calculated at 1 500 CHF per working day.
Excavation and retaining works scenario in unstable Valais terrain
On an office building construction site in VS, exceptional rainfall saturates the upper soil layers during deep excavation. Cut slopes display initial signs of sliding. Under art. 75 OTConst, site management and the geotechnical engineer order a complete halt to excavation works for eight consecutive days to clear unstable areas and pump out drainage water.
Because the contractor submitted written notice under art. 365 para. 3 CO at the very first sign of rising water levels, the eight-day extension was incorporated into the construction schedule with no financial penalties applied. Site management updated the foundation slab delivery milestone, avoiding contract disputes while maintaining full compliance with current safety standards governing temporary support and trench shoring.
Contracts and SIA 118: free tools
Advance payments and retentions, surety bonds, price escalations, daywork reports, subcontractor monitoring.
Frequently asked questions
Does wind preventing crane operations entitle you to a deadline extension under standard SIA 118?
Yes, if the shutdown exceeds normal statistical contingencies for the season and blocks the critical path. The notification must be recorded in the construction site minutes. On a key item costing around 12 000 CHF per day, the contractor thus protects their rights without incurring penalties.
How do you legally formalise a stoppage due to persistent frost under the Code of Obligations (CO)?
The contractor immediately notifies the client of the hindrance in writing in accordance with art. 365 CO. For a masonry package of around 85 000 CHF, this notification avoids bearing the consequences of a schedule delay or defects resulting from low temperatures during concrete curing.
What safety obligations apply during extreme heatwaves under the OTConst?
Art. 37 OTConst requires the employer to take the necessary measures to protect workers during work in extreme heat. If productivity slows despite adapted working hours, the impact on the schedule must be recorded immediately with the site management to offset any delay.
Does torrential rain justify an extension of time for earthworks?
Yes, because under art. 75 OTConst, the slope of the trench walls must be adapted if stability is compromised by heavy rainfall. For an excavation package of around 45 000 CHF, technical safety requirements warrant a legitimate suspension, entitling you to an extension under standard SIA 118.
Can the contractor claim financial compensation for extraordinary bad weather?
Standard SIA 118 generally grants an extension of time without direct financial compensation. However, art. 373 CO allows a court to grant an increase in the lump-sum price or terminate the contract in the event of extraordinary circumstances that were impossible to foresee or excluded from the parties' assumptions.
What does the CN Secteur principal provide for in the event of work stoppages due to bad weather?
The CN Secteur principal regulates bad-weather stoppages to protect workers' health and organise short-time work. The site manager logs these hours of interruption, preventing the contractor from facing unjustified contractual penalties on an overall contract of around 500 000 CHF.
Strict traceability of bad weather in the construction site minutes protects the contractor against penalties and ensures the fair application of standard SIA 118 when facing Swiss climatic contingencies.
Consult our reference guides to master your schedules and contractual procedures:
- Site Scheduling in Switzerland: Gantt Tracking, CFC Production Rates and Delay Management (SIA 118)
- From Master Schedule to Construction Schedule: Critical Path and Concrete / Screed Curing Times
- Average Production Rates per CFC Trade in Switzerland: Realistic Benchmarks for Site Supervisors
- Delays on the Construction Site (SIA 118 / CO): Formal Notice and Substitute Performance