Construction Site Delays (SIA 118 / CO): Formal Notice and Third-Party Performance

Managing Swiss site delays under SIA 118 and CO: formal notice procedures, grace period setting, and third-party substitute performance.

Table of contents
The 3 Major Site Risks
  1. Financial / Margin: An unnotified schedule slip exposes site management and the client to idle-time cost overruns of roughly 15 000 CHF to 50 000 CHF per week depending on the scale of the works, in addition to the enforcement of liquidated damages stipulated in the works contract under art. 160 CO, without prejudice to damages under art. 97 CO.
  2. Legal / Joint Body / SUVA: Hastily reorganising a slipping construction site without formally readjusting workflow compromises collective site safety, in breach of art. 3 OTConst on preventive workstation planning and art. 82 LAA on appropriate technical prevention measures.
  3. Administrative / Acceptance: Failing to comply with the formal notice requirements of art. 102 CO or omitting to grant a reasonable grace period under art. 107 CO and art. 366 CO deprives the client of the right to assign the works to a third party at the defaulting contractor's expense, postponing the final verification under SIA 118 indefinitely.

On Swiss construction sites governed by standard SIA 118 or operating under the fundamental statutory regime of the contract for work and services under art. 363 CO, adhering to the contractual schedule conditions the entire chain of trade packages. When a contractor lags behind in starting, delays progress, or is manifestly unable to deliver its works at the agreed time, site management must act with rigor. Art. 366 para. 1 CO entitles the client to terminate the contract without awaiting the agreed deadline when the delay unequivocally compromises timely completion. This prerogative nevertheless demands strict legal qualification of debtor default under art. 102 CO, preventing any unjustified unilateral termination.

Substituting a defaulting contractor through third-party performance is the ultimate measure of operational recovery. Under art. 366 para. 2 CO, the client may, by formal warning, set a reasonable grace period for the contractor to rectify defective work or recover an insufficient pace, failing which continuation of the works will be assigned to a third party at the original contractor's cost and risk. By incorporating the conciliation mechanisms of SIA 118 and the general principles of art. 107 CO, site managers and local project directors must issue every formal notice in writing to prevent the forfeiture of contractual penalties under art. 160 CO.

Managing a construction site delay in Switzerland requires drawing a strict distinction between mere operational sluggishness and legally qualified default. Under the Code of Obligations (CO), art. 102 CO provides that the debtor is placed in default by formal demand from the creditor, or by the mere expiration of the term where the performance date was agreed jointly. Within the framework of the contract for work and services under art. 363 CO, art. 366 CO grants the client broad powers right from the execution phase: under art. 366 para. 1 CO, if the contractor fails to start the work on time, delays execution, or falls so far behind that it can no longer complete the work by the agreed date, the client may withdraw from the contract without waiting for the final deadline.

Applying standard SIA 118 modulates this approach by imposing coordination duties on site management and notice obligations on the contractor. Where impediments not attributable to the contractor arise, such as delays in issuing execution drawings or unexpected ground conditions, art. 365 para. 3 CO requires the contractor to inform the client immediately if any circumstance threatens the proper or punctual completion of the work, on pain of bearing the consequences. For its part, site management must record progress in the site journal without delay and compare the actual critical path against agreed project milestones.

Operational Protocol for Formal Notice and Setting Grace Periods

To validly establish grounds for coercive action or substitution, site management acting on behalf of the client under the rules of representation set forth in art. 32 CO must adhere to strict evidentiary formality. Sending a formal demand by registered post constitutes an essential starting point. This letter must articulate three key components: a factual and joint inspection record of unperformed work against the execution schedule, a formal demand to increase manpower or reorganise phasing, and the setting of a reasonable comminatory grace period within the meaning of art. 107 CO.

The grace period granted must be realistic in light of the nature of the remaining works. A 48-hour deadline to complete a reinforced concrete foundation slab is legally null and void because it is manifestly impracticable. Under art. 108 CO, setting a grace period is not necessary where the debtor's conduct renders it manifestly useless or where performance has ceased to have any utility. When the overall schedule is not irremediably compromised but defective execution threatens downstream trades, art. 366 para. 2 CO makes it possible to formally warn the contractor that, once the deadline expires, continuation or rectification will be assigned to a third party at its expense and risk.

Contractor Substitution and Performance by a Third Party under Art. 366 Para. 2 CO

Resorting to third-party performance without entirely terminating the contract is an exceptional remedy to clear the critical path. Enforcing art. 366 para. 2 CO requires meeting cumulative conditions: faulty non-performance attributable to the contractor, prior formal notice with a reasonable grace period, formal warning of substitute performance, and the unsuccessful expiration of that grace period. The debtor's fault is assessed under art. 97 CO, with the debtor liable for damages unless it proves that no fault can be attributed to it.

Bringing in a third-party contractor requires a thorough joint inspection of the site. Before the new subcontractor enters the work area, site management must draw up a photographic record detailing the exact quantities completed by the defaulting contractor, material stocks on site, and any non-conformities. This step prevents cross-liability issues during subsequent acceptance of the works and secures downstream financial set-off against outstanding interim payment certificates.

Procedure Stage Swiss Legal Basis Action Required from Site Management Risk in Case of Non-Compliance
Noting production rate deficits Standard SIA 118 / Art. 364 CO Reconciling joint quantity measurements with master schedule Inability to enforce delay claims against the contractor
Formal demand Art. 102 CO Registered letter qualifying debtor default No default status and forfeiture of liquidated damages
Setting a grace period Art. 107 CO / Art. 366 para. 2 CO Issuing a realistic deadline with warning of third-party execution Third-party intervention rendered null and void
Joint inspection record of abandonment Art. 366 CO / Standard SIA 118 Survey record, quantity survey, and photographic documentation Inability to allocate liabilities between contractors
Award to third-party contractor Art. 366 para. 2 CO Order restricted to defaulted works at debtor's expense Disallowance of extra costs by the civil court
Final account and financial withholdings Art. 97 CO / Art. 160 CO Offsetting cost overruns and enforcing contractual penalties Claims for damages challenged and dismissed

Common Project Management Mistakes and Financial Impact

The most common mistake made by site management is retaining a substitute contractor without prior formal notice complying with art. 366 para. 2 CO or without granting a reasonable grace period. In such cases, the replacement is reclassified as an unjustified unilateral termination under art. 377 CO, requiring the client to indemnify the ousted contractor in full for incurred expenses and lost profit. On a finishing work trade package worth 350 000 CHF, this oversight can trigger outright losses of 40 000 CHF to 70 000 CHF, borne by the client or the professional civil liability insurance of the managing agent subject to art. 398 CO.

A second pitfall is the hasty application of a contractual penalty stipulated in the contract. Art. 160 CO provides that where the penalty was agreed for failure to perform at the agreed time, the creditor may demand both performance and the penalty, unless it expressly waived the right or accepted performance without reservation. If site management approves monthly payment statements or signs a handover certificate without an explicit written reservation regarding accrued delay penalties, the right to the penalty lapses. Furthermore, under art. 161 CO, the penalty is due even if the creditor suffered no damage, but if actual losses exceed that amount, claiming higher compensation requires proving fault on the debtor's part. Finally, art. 163 CO provides that the judge retains the power to reduce penalties deemed excessive.

The third pitfall involves failing to verify the obligations of subcontractors brought in as backup to make up for a delay. Under pressure from an emergency, bringing staff onto the construction site without complying with the duty of due diligence set out in art. 5 al. 3 LDét and art. 8c ODét exposes the general contractor and the client to administrative penalties under art. 9 LDét of up to 5000 francs, or even 30 000 francs in the event of a breach of the net minimum wages guaranteed by art. 2 LDét. Likewise, under art. 4 OTConst, no work may begin without a written plan detailing the safety and health protection measures.

Practical Case Studies (Typical Scenarios on Swiss Construction Sites)

The figures below are illustrative examples intended to guide professionals working on Swiss construction sites.

Scenario 1: Structural Work Standstill and Threat of Substitution (Canton of Vaud)

During the construction of a residential building in Lausanne, the masonry and reinforced concrete contractor (CFC 211), staffed with a team of 8 workers, runs 4 weeks behind schedule on pouring the ground-floor slab. This lag paralyzes subsequent facade works and Plumbing & Sanitary Installations. Site management formally records the lack of sufficient manpower against the agreed progress rates.

A formal notice is sent by registered post with acknowledgment of receipt, granting a grace period of 10 working days to triple equipment capacity and assign 6 additional workers, with an express warning of enforcement under art. 366 para. 2 CO. With no response from the defaulting contractor, site management conducts a joint inspection record of site conditions. The client then engages a third-party firm to pour the slab and complete the structural work. The 85 000 CHF intervention cost overrun is offset in full against the original contractor's advance payment certificates, in accordance with the rules of the contract for work and services.

Scenario 2: Finishing Work Delays and Penalty Enforcement (Canton of Geneva)

On an office building project in Carouge, a plastering and painting contractor with 4 employees fails to hand over partitions by the contractually agreed deadline of 15 September. The contract specifies liquidated damages of 1 000 CHF per working day of delay under art. 160 CO, capped at 10% of the 280 000 CHF contract value. The contractor delivers the works on 15 October, representing 22 working days of delay not attributable to bad weather or variation orders.

Site management enters a formal reservation during the inspection of the work and retains the sum of 22 000 CHF on the final account. When the contractor claims a supply shortage of plasterboard, site management proves that no prior notice was given under art. 365 para. 3 CO. The financial retention is upheld, safeguarding the project's financial margin without litigation.

00:00 to 00:15 AI Avatar: In the face of a critical delay, acting without legal rigor leaves the client vulnerable to costly disputes. Serving formal notice in strict compliance with the Code of Obligations (CO) and standard SIA 118 immediately safeguards your rights of intervention.

00:15 to 01:10 Screen and Diagrams: The site management identifies the pace discrepancy on the critical path. The formal warning sets a specific deadline pursuant to art. 366 al. 2 CO. In the event of inaction, art. 102 CO establishes the formal notice. Daily penalties are triggered in accordance with art. 160 CO and art. 161 CO. Recourse to a replacement third party is initiated at the defaulting party's expense, with direct offsetting against advance payments.

01:30 AI Avatar: Master the Swiss legal framework to recover your schedules without the risk of procedural bottlenecks.

Contracts and SIA 118: free tools

Advance payments and retentions, surety bonds, price escalations, daywork reports, subcontractor monitoring.

View the contracts and SIA 118 tools

Frequently asked questions

How do you formalise a formal notice when work progress is insufficient?

The site management issues a written notice calling on the contractor to restore scheduled progress within a reasonable period, for instance ten working days. Pursuant to art. 366 al. 2 CO, the client gives notice that continuation will be entrusted to a third party at the defaulting contractor's expense and risk if the delay persists.

At what exact point can third-party substitution work begin?

Substitution begins as soon as the final deadline set in the formal warning expires without result. The client appoints a third-party contractor to complete the works at the defaulting contractor's expense, pursuant to art. 366 al. 2 CO. Art. 108 CO specifies that setting a deadline is not required if the debtor's attitude makes it clear that it would have no effect.

Can contractual penalties be enforced without proving a financial loss?

Yes. Pursuant to art. 161 CO, the contractual penalty agreed in the contract is payable even if the creditor has suffered no loss. For a contractual delay penalty set at 500 CHF per calendar day, the amount applies automatically as soon as the deadline is missed, without any requirement to quantify a direct loss of rental income.

Which claims can be offset against the retention money?

The extra cost billed by the replacement third party, for example an illustrative 45 000 CHF, is deducted directly from frozen advance payments or retention money under standard SIA 118. Art. 366 al. 2 CO places these expenses on the defaulting contractor, preventing the client from having to pay out unbudgeted additional funds.

What preliminary steps are required before terminating for a critical delay?

Art. 366 al. 1 CO allows the client to withdraw from the contract before the completion date if the delay makes timely completion impossible. A joint inspection record documenting the site shutdown and prior compliance with art. 102 CO regarding formal notice through proper warning legally safeguard this immediate termination.

Where can you turn to recalculate unit prices or re-tender the contract?

To restructure a tender or re-tender after a default, visit /soumissions/. To check average takeover costs without exposing a raw schedule of rates, refer to /indice-acip/. Finally, to offset a shortage of site workers, your hiring requirements are handled on /jobs/.

Rigorous delay management relies on strict compliance with the stages of formal notice and the rules governing replacement performance. To explore schedule and contract management in greater depth across your Swiss construction sites, consult our dedicated resources: