Average Execution Rates by CFC Trade in Switzerland: Realistic Benchmark for Site Managers

Average execution rates by CFC trade in Switzerland. Realistic benchmarks for site managers under standard SIA 118 and the Swiss Code of Obligations.

Table of contents
The 3 Major Site Risks
  1. Financial / Margin: Underestimating actual unit production rates leads to unexpected acceleration costs. For a masonry or finishing work package, exceeding allocated hours can reduce gross margin by 15% to 25%, with the contractor remaining bound by the agreed sum under art. 373 CO subject to statutory exceptions.
  2. Legal / Joint Body / SUVA: Imposing unrealistic outputs often leads to non-compliance with working hours under the LTr or safety lapses. Under art. 3 OTConst, works must be planned to keep risks as low as possible.
  3. Administrative / Acceptance: A discrepancy between theoretical rates and actual progress jeopardises the master schedule's critical path. The client may invoke rules on default or initiate the delay procedure under art. 366 CO and standard SIA 118, delaying joint inspection.

Construction site scheduling in Switzerland requires rigorous mastery of execution rates by construction cost code (CFC). Aimed at site managers, construction project managers, site supervisors and clients, this guide presents realistic output benchmarks observed across Western Switzerland. From CFC 211 earthworks to CFC 211-212 reinforced concrete structures and CFC 271 to CFC 285 finishing work trades, team sizing directly determines adherence to agreed deadlines. Art. 364 CO stipulates that the contractor is liable for the proper and faithful execution of the work, which implies deploying the personnel and equipment required for contractual progress.

Incorporating realistic production rates into the execution schedule prevents cascading disruptions along the critical path. Overly optimistic daily output estimates create severe bottlenecks, particularly during service shaft runs or screed laying, whose incompressible curing times dictate subsequent trades. Site supervision professionals will find field-tested progress ratios below, along with key criteria for adjusting resources to architectural complexity and cantonal constraints.

Calculation method for execution rates by CFC group

Determining production rates on a Swiss construction site relies on the standard unit time (TU), expressed in operative-hours per unit of work (h/m², h/m³ or h/m). For site management and site operations, converting these figures into daily or weekly progress requires accounting for the average staffing of a standard crew, effective working hours under the labour act, and spatial congestion constraints.

Linear or surface progress on a critical task stems from a basic equation: daily output corresponds to the active workforce multiplied by productive daily hours, divided by the average standard unit time for the relevant CFC. Under a works contract governed by standard SIA 118, the contractor remains responsible for supplying the manpower and plant needed to meet agreed milestone dates. Should exceptional circumstances jeopardise the schedule, art. 365 CO reminds contractors of their duty to notify the client.

Safety and spatial coordination constraints

Construction site organisation requires building safety requirements into daily output. Under art. 3 OTConst, building works must be planned to minimise risks as far as possible. In CFC 211 earthworks and excavations, excavator output depends on the duty to slope trenches deeper than 1.50 m that lack shoring, in accordance with art. 68 OTConst. Similarly, collective edge protection on bare CFC 211 slabs—satisfying art. 22 OTConst requirements with guardrails at least 100 cm high—absorbs labour hours that yield no poured concrete but are mandatory before subsequent trades may access the area.

Finishing work trade interfaces demand thorough critical-path analysis. Doubling electricians (CFC 232) and dryliners (CFC 271) on the same level without dedicated work zones reduces overall output by 20% to 35% through physical clutter, without shortening execution time for the sector.

Comparison table of average execution rates by CFC chapter

The table below summarises average standard unit times recorded on Swiss residential and commercial building sites, alongside theoretical daily outputs for a standard crew under normal operating conditions.

CFC chapter Scope of works Standard crew Average unit time (TU) Daily output per crew
CFC 211 Bulk excavation and trenching (loose ground) 1 plant operator + 1 operative 0.06 to 0.12 h/m³ 130 to 250 m³/day
CFC 211 Formwork, rebar placing and slab concreting (reinforced concrete) 1 foreman + 4 masons 1.10 to 1.60 h/m² 25 to 36 m²/day
CFC 214 Erection of precast concrete units (columns, beams) 1 crane operator + 3 erectors 1.80 to 2.50 h/unit 12 to 18 units/day
CFC 221 Wood-metal windows (installation with perimeter sealing) 2 skilled fitters 2.00 to 3.20 h/frame 5 to 8 windows/day
CFC 228 Two-layer bituminous waterproofing on flat roof 1 skilled waterproofer + 1 operative 0.35 to 0.55 h/m² 30 to 45 m²/day
CFC 232 Commercial electrical cable pulling and cable trays 2 electricians 0.08 to 0.14 h/m 110 to 190 m/day
CFC 241 Underfloor heating distribution (pipe laying over insulation) 2 installers 0.20 to 0.32 h/m² 50 to 80 m²/day
CFC 271 Drywall partitions (studwork with double board linings) 2 dryliners/plasterers 0.65 to 0.95 h/m² 16 to 24 m²/day
CFC 272 Liquid screed or bonded/unbonded cement screed 3 screeders 0.09 to 0.15 h/m² 160 to 260 m²/day
CFC 281 Medium-format porcelain stoneware tiling (floors) 1 tiler + 1 operative 0.90 to 1.40 h/m² 11 to 17 m²/day
CFC 285 Interior matt painting on walls and ceilings (2 coats) 2 painters 0.25 to 0.40 h/m² 40 to 64 m²/day

Common cadence assessment errors and financial impacts

Misjudging production tempos causes severe operational imbalances. A frequent error involves conflating material application speed with technical drying periods. For a cement screed (CFC 272), a crew can lay 200 m² per day, but the material requires an irreducible drying time before moisture-sensitive floor finishes (CFC 281 or parquet) can be installed. Scheduling the tiler too early stalls the site or requires artificial drying costing around 6 000 CHF to 15 000 CHF per storey for dehumidifier hire and power.

Another common pitfall is overestimating formwork outputs (CFC 211) during winter. Because a crew casts 35 m² of slab daily in May, site management assumes the same tempo in January. Yet lower temperatures slow concrete curing and require heating measures. Striking formwork prematurely breaches recognised engineering standards, tying up formwork gear and necessitating an additional formwork fleet costing 18 000 CHF to 30 000 CHF per month in unplanned immobilisation.

Lastly, underestimating the time needed to erect safety installations for work at height skews planning. Art. 26 OTConst mandates façade scaffolding once fall heights exceed 3 m, with the top guardrail extending at least 80 cm above the highest fall hazard. Modifying and adjusting these systems slows down lightweight curtain walling or window installation (CFC 221), shifting milestones and risking contractual penalties of roughly 500 CHF to 2 000 CHF per day of delay where agreed under art. 160 CO.

Illustrative practical cases (typical scenarios on Swiss construction sites)

The figures and scenarios below are illustrative examples developed to examine how site production rates are managed in practice.

Scenario 1: Structural work schedule catch-up in an urban setting (Vaud)

On a 24-unit rental housing project in the canton of Vaud, earthworks and Special Foundations (CFC 211) suffered a two-week delay following water ingress. The superstructure comprises three storeys over ground floor with a gross slab area of 480 m² per floor.

Site management reviewed execution tempos: a standard crew of 5 masons (1 foreman, 4 operatives) casts an average of 30 m² of reinforced slab per working day (average TU of 1.33 h/m² for an 8-hour shift). Pouring an entire rough floor required 16 working days. To absorb the delay without resorting to overtime capped by art. 12 LTr, the contractor split each pour into two 240 m² sectors and deployed a second tower crane alongside a second crew of 4 masons. Combined progress reached 55 m² per day, cutting the floor cycle to 9 working days. Additional plant and logistical expenses totalled around 22 000 CHF, offset by avoiding delay penalties on weather-tight milestones.

Scenario 2: Finishing work trade coordination in an office building (Geneva)

In a commercial building in Geneva, the schedule planned simultaneous work by building services trades and drywallers (CFC 271) across a 900 m² floorplate. The drywall contractor had planned a crew of 4 operatives installing 40 m² of partitions per working day (TU of 0.80 h/m²). However, ventilation ducts (CFC 242) and primary cable trays (CFC 232) blocked corridors, slashing actual drywall output to 22 m² per day.

Noting an imminent risk of missing the completion date under art. 366 CO, local site management rearranged operations into strictly demarcated 300 m² zones. Mechanical and electrical trades were granted sole access for 6 working days per zone, immediately followed by drywallers operating at full speed. This zoning restored drywall production to 42 m² per day, eliminating spatial clashes and safeguarding the handover date without contractual disputes.

Contracts and SIA 118: free tools

Advance payments and retentions, surety bonds, price escalations, daywork reports, subcontractor monitoring.

View the contracts and SIA 118 tools

Frequently asked questions

How can structural work cadences be verified during a CFC 211 tender?

Site management evaluates the contractor's planned staffing against hours-per-cubic-metre ratios. For masonry work valued at around 450 000 CHF, the successful bidder proves the crew's technical feasibility without relying on undeclared work, under cantonal enforcement of art. 6 LTN.

Does insufficient progress in finishing work justify hiring a third party?

Yes, if site progress proves the contractor cannot finish the works by the agreed deadline. Under art. 366 CO, the client may grant a reasonable grace period, warning that remedial work or continuation will be assigned to a third party at the contractor's expense, representing an illustrative extra cost of 35 000 CHF.

How does CFC 251 screed drying affect the critical path?

Laying floor coverings requires strict compliance with curing times before any traffic or loading. Arbitrarily shortening these periods to make up lost time risks property defects. Such defects fall under the five-year statutory warranty prescribed by art. 371 CO.

How can façade assembly rates be balanced with safety requirements?

Accelerating production rates must never compromise occupational health and safety rules. Once the fall height exceeds 3 m, art. 26 OTConst mandates façade scaffolding with an upper guardrail extending at least 80 cm above the hazardous top edge.

Can the client change the contractual progress rates without adjusting the price?

If the client imposes a tighter schedule that alters the initial agreement entered into under art. 1 CO, the contractor is entitled to compensation for additional costs. For a lump-sum contract, unforeseeable disruptions pave the way for the adjustment rules provided for in art. 373 CO.

How do you document a slowdown caused by exceptional adverse weather?

The site manager records weather-related stoppages in the daily log and notifies site management pursuant to standard SIA 118. Art. 365 CO requires the contractor to report any circumstance jeopardising proper performance, preventing it from bearing the burden of a delay attributable to natural elements.

Mastering execution rates by CFC chapter ensures contractual deadlines are met, guarantees overall profitability and prevents technical disputes on a Swiss construction site. To delve deeper into schedule management and the applicable regulatory framework, consult the specialised guides: