Table of contents
The 3 Major Site Risks
- Financial / Margin: Unplanned transport, analysis, and landfill costs: the lack of a comprehensive survey or the reclassification of mixed rubble skips into hazardous waste increases disposal costs by about 40 % to 150 % per tonne removed. Pursuant to art. 17 OLED, hazardous waste must strictly be separated and disposed of through dedicated channels, failing which heavy penalties apply for deferred sorting at transfer stations.
- Legal / Joint Body / SUVA: Immediate work stoppage by SUVA or the cantonal labour inspectorate for endangering workers' health. In accordance with art. 32 OTConst, if a hazardous substance such as asbestos or PCBs is unexpectedly uncovered, work must stop and the client or their representative must be informed immediately. Under art. 82 OTConst, asbestos removal operations releasing hazardous airborne fibres are restricted to Suva-approved firms, with serious breaches exposing violators to prosecution under art. 229 CP in the event of bodily endangerment.
- Administrative / Acceptance: Withholding of the building permit or deferral of operating permits by the municipality and cantonal environmental protection authorities. Art. 16 OLED requires indicating the type, quality, quantity, and planned disposal routes upon applying for the building permit if the waste volume exceeds 200 m³ or involves hazardous pollutants, and later proving their compliant disposal. Without validated OMoD consignment notes, the final acceptance of the works is compromised.
Managing a conversion, heavy refurbishment, or demolition construction site in Switzerland requires flawless control over building pollutants and complete traceability across disposal routes. Aimed at site management teams, contract managers, site supervisors, and clients, this guide details preliminary surveys for asbestos, PCBs, and lead, while upholding the risk planning duty set out in art. 3 OTConst and norm SIA 118.
On the ground, methodical separation of materials at the source and rigorous tracking of electronic consignment notes prevent financial disputes during the final account. Close coordination between specialist consultants and executing contractors secures the overall schedule, protects workers' health, and ensures full compliance with federal and cantonal environmental ordinances.
Free website tool
Decision Tree for Asbestos (<1991), PCBs & Construction Waste Calculator (OLED 200 m3)
Methodology for investigating building pollutants: asbestos, PCB, and lead
Pollutant surveys dictate the technical setup of any renovation or deconstruction construction site. Pursuant to art. 3 OTConst para. 2, if the presence of asbestos or PCBs is suspected, the employer identifies and assesses hazards and plans the necessary measures. This duty requires an exhaustive survey prior to any destructive intervention.
For asbestos, sampling targets pipe lagging, tile adhesives, vinyl floor tiles, and fibre cement panels. Pursuant to art. 32 OTConst para. 2, if the presence of these substances is suspected, the employer takes the planned measures and informs the workers of the survey findings. If such a substance is discovered unexpectedly, art. 32 OTConst para. 3 provides that work must stop and the client or their representative must be notified. Under art. 82 OTConst, work that releases a significant quantity of hazardous airborne asbestos fibres may only be carried out by asbestos abatement firms recognised by Suva.
For PCBs, sampling focuses on joint sealants and anti-corrosion coatings. Lead is investigated in old paints and piping. Analysis in an accredited laboratory quantifies concentrations to size containment enclosures and maintain air quality.
Disposal concept and material recovery according to OLED and OMoD
Residual materials management is governed by OLED and OMoD. Under art. 16 OLED para. 2, the client must indicate in their building permit application the type, quality, and quantity of waste as well as the planned disposal routes if the volume is likely to exceed 200 m³ or if waste containing hazardous pollutants such as PCBs, PAHs, lead, or asbestos is expected; upon request, the client must provide proof of compliant disposal after completion of the work.
On the construction site, art. 17 OLED para. 2 requires hazardous waste to be separated from other waste and disposed of separately; remaining waste must be sorted on the construction site (soil materials, excavated materials, deconstruction materials, recyclable materials such as glass, metals, wood, and plastics, combustible waste, other waste); if on-site sorting is impossible, it must be performed in suitable installations.
Under art. 18 OLED, soil materials removed from topsoil and subsoil stripping must as far as possible be fully recovered if suitable and compliant with OSol guideline values. Art. 19 OLED requires the fullest possible recovery of unpolluted excavated materials. For mineral deconstruction waste, art. 20 OLED mandates the fullest possible recovery of demolition concrete and bituminous materials whose PAH content does not exceed 250 mg per kg, recovery being prohibited beyond this threshold. Movements of hazardous waste are tracked using OMoD consignment notes.
Comparative matrix of disposal routes and traceability
The table below sets out the regulatory status, packaging requirements, and authorised disposal routes for major construction waste in Switzerland:
| Waste category | Regulatory status | Logistics packaging | Authorised disposal route | Traceability document |
|---|---|---|---|---|
| Low-density (friable) asbestos | Hazardous waste (OMoD) | Sealed dedicated airtight bags | Landfill for stabilised residues | OMoD consignment note |
| High-density (bonded) asbestos | Controlled waste | Dismantling without breakage, sealed big bags | Type B landfill | Site waste tracking sheet |
| Sealants containing PCBs | Hazardous waste (OMoD) | Approved leakproof drums | High-temperature incineration | OMoD consignment note |
| Elements with lead-based paint | Controlled or hazardous waste | Airtight wrapping under plastic sheeting | Metal recovery or incineration | Cantonal disposal voucher |
| Asphalt with PAHs <= 250 mg/kg | Recovery (art. 20 OLED) | Selective milling and dedicated storage | Asphalt mixing plant | Weighbridge ticket and PAH analysis |
| Unpolluted excavated materials | Recovery (art. 19 OLED) | Separate earthmoving skips | Backfilling or licensed gravel pits | Weighbridge ticket and OLED certificate |
Recurring pollutant management errors and financial overruns
Failures in identification and sorting generate severe budget overruns. The most damaging mistake consists in skipping destructive sampling before works begin. An unexpected discovery of asbestos during the strip-out phase halts operations and triggers containment and reorganisation expenses ranging from 35 000 CHF to 85 000 CHF.
Contractually, art. 365 CO para. 3 provides that if the material supplied by the client or the plot designated by them proves defective, or if any other circumstance jeopardises the proper or timely execution of the work, the contractor must inform the client immediately, failing which the contractor bears the consequences. Any failure exposes the firm to resulting remediation costs.
Mixing ordinary waste with hazardous substances in skips represents another critical risk. Fibre cement debris tossed into a concrete skip results in the full downgrading of the batch, incurring sorting surcharges at specialised centres of around 10 000 CHF to 25 000 CHF per 20 m³ skip. Finally, missing OMoD documentation prevents the municipal authority from signing off on the final project records.
Illustrative practical cases (typical scenarios on Swiss construction sites)
The situations presented below are illustrative examples designed to clarify the operational and financial management of pollutants under Swiss law.
In a first scenario in the canton of Vaud, the refurbishment of a 1970s office building involves 16 workers. The preliminary survey reveals asbestos-containing vinyl tiles and PCB sealants. The employer applies art. 3 OTConst para. 2 to plan protective measures. Heavy asbestos removal is entrusted to a Suva-approved specialist under art. 82 OTConst. The disposal concept submitted under art. 16 OLED provides for the separation mandated by art. 17 OLED: 35 tonnes of hazardous waste are removed under an OMoD tracking document for dedicated incineration, while 110 tonnes of unpolluted concrete are recycled. The total remediation surcharge is held to approximately 125 000 CHF thanks to early planning.
In a second scenario in the canton of Geneva, the demolition of an industrial workshop engages 10 workers. Laboratory tests reveal lead-coated steel frameworks and asphalt containing polycyclic aromatic hydrocarbons at 190 mg per kg. In accordance with art. 20 OLED, this level below the 250 mg per kg threshold permits the full recycling of the 320 tonnes of asphalt at a processing plant. Lead-coated metal components are dismantled under controlled extraction. Strict enforcement of OLED and OMoD protocols enables the project to wrap up with environmental expenditure kept around 58 000 CHF.
Contracts and SIA 118: free tools
Advance payments and retentions, surety bonds, price escalations, daywork reports, subcontractor monitoring.
Frequently asked questions
When does a pollutant survey become legally mandatory before works begin?
Under art. 16 OLED, the client must document the nature, quality, and quantity of waste whenever the projected volume exceeds 200 m³ or if hazardous pollutants are suspected. Art. 3 OTConst requires assessing risks from the planning stage. Illustrative survey costs run around 3 500 CHF.
What must be done if asbestos-containing materials are discovered unexpectedly during strip-out?
Pursuant to art. 32 OTConst, if a hazardous substance is unexpectedly discovered, work must stop immediately and the client or their representative must be informed. The employer implements required measures. This scenario entails an illustrative remediation cost of around 8 000 CHF to be settled with site management.
Who is allowed to perform asbestos removal operations that release hazardous fibres on a site?
Under art. 82 OTConst, work releasing significant quantities of hazardous airborne asbestos fibres is restricted to asbestos abatement firms recognised by Suva. Bonded materials still call for technical precautions. Safe treatment costs an illustrative amount of around 4 200 CHF per containment zone.
What requirements govern on-site material sorting directly on the construction site?
Art. 17 OLED dictates that hazardous waste must be separated and disposed of distinctly, while recyclable materials must be sorted on site. If tight space prevents this, sorting is carried out at an appropriate facility. Rotating separate skips represents an illustrative outlay of around 1 200 CHF.
How must mineral deconstruction waste be recovered according to environmental standards?
Under art. 20 OLED, mineral waste from deconstruction, such as concrete and non-bituminous materials, must be recovered as far as possible. Bituminous mixtures containing up to 250 mg of PAHs per kg may be recycled. Local recycling costs an illustrative amount of around 45 CHF per tonne.
What proof of waste disposal can the municipality require after completion of the works?
Under art. 16 OLED, the client must provide proof upon request of the compliant disposal of construction waste after the works. OMoD tracking documents guarantee environmental traceability. Drawing up the final disposal balance sheet generates illustrative administrative costs in the region of 950 CHF.
The site management ensures legal and environmental compliance by tracking construction waste disposal. Find our operational resources here:
- Site Setup and Preparation in Switzerland: OTConst Safety, SUVA and OLED Waste
- Health and Safety Plan (PSST - OTConst): Mandatory Legal Content
- Scaffolding, Fall Protection from 2.00 m and Shored Trenches from 1.50 m: OTConst & SUVA Rules
- Managing Alkaline Construction Site Runoff, Soil Protection, and Noise (OPB) and Air (OPair) Directives
