Scaffolding, Edge Protection from 2.00 m, and Shored Excavations from 1.50 m: OTConst & SUVA Rules

OTConst and SUVA rules in Switzerland: edge protection from 2 m, trench shoring from 1.50 m, and scaffolding safety compliant with SIA 222.

Table of contents
The 3 Major Site Risks
  1. Financial / Margin: A work stoppage ordered during a safety inspection leads to equipment retention costs, contractual delay penalties, and emergency response surcharges that can represent an illustrative order of magnitude of 15 000 CHF to 50 000 CHF per week of shutdown under art. 97 CO.
  2. Legal / Joint body / SUVA: Non-compliance with fall protection or shoring rules exposes contractors to a shutdown of works by competent inspectors and engages liability in the event of bodily endangerment under art. 229 CP, which provides for a custodial sentence or a monetary penalty for breaching the recognized rules of construction.
  3. Administrative / Acceptance: Non-compliant guardrails or a lack of traceability for scaffolding inspections delays formal inspection procedures, compromises access for finishing trades, and halts the verification of the works governed by standard SIA 118.

Site management, site supervisors, and project managers must coordinate physical fall protection measures right from the site setup phase. Art. 23 OTConst mandates the use of perimeter edge protection at unprotected locations whenever the fall height exceeds 2 m, as well as along slopes higher than 2 m with an incline steeper than 45 degrees. Under art. 22 OTConst, this system comprises a top rail with its upper edge at least 100 cm above the trafficable surface, at least one intermediate rail, a toeboard of at least 15 cm, and a maximum clearance of 47 cm between these elements. For building facades, art. 26 OTConst requires scaffolding as soon as the fall height exceeds 3 m, with a top rail extending 80 cm above the highest exposed area.

In earthworks, securing excavations is a constant operational priority. Pursuant to art. 68 OTConst, earthworks, shafts, and excavations must be arranged so that falling or caving ground does not endanger any worker; when deeper than 1 m 50 without shoring or trench shielding, they must be sloped back or secured by other appropriate measures. Shoring and shielding must withstand anticipated loads and meet the recognized rules of technology under art. 77 OTConst. Overall coordination rests on the employer's statutory duty to take the necessary preventive measures under art. 82 LAA and art. 3 OPA, guaranteeing safe circulation routes before masonry or civil engineering crews commence work.

OTConst technical requirements for fall protection

Implementing safety measures on Swiss construction sites follows strict building rules, governed by the Construction Works Ordinance (OTConst) and SUVA recommendations. As soon as workstations or circulation routes present a risk of falling into space, contractors must implement compliant collective protection solutions.

Perimeter edge protection and slab openings

Temporary guardrails installed along floor edges or slab openings must meet the precise dimensional requirements specified in art. 22 OTConst. This complete assembly includes a top rail at least 100 cm above the walkable working surface, at least one intermediate rail, and an edge toeboard at least 15 cm high, with a clear gap not exceeding 47 cm between these horizontal elements. This arrangement prevents both personnel from falling from height and tools or building materials from rolling onto lower levels, in accordance with the preventive duties under art. 17 OTConst.

For utility shafts, elevator cores, or access openings left in concrete slabs, art. 25 OTConst mandates either the installation of such full perimeter edge protection or the placement of a flush-fitting, break-proof cover securely anchored to prevent any accidental displacement during material handling or personnel movements.

Facade scaffolding and roofing work

During structural work and facade operations, scaffolding serves as the primary temporary structure for collective protection. Under art. 26 OTConst, the top guardrail of facade scaffolding must project at least 80 cm above the upper edge of the working area presenting a fall hazard. If the horizontal gap between the outer face of the building and the guardrail exceeds 60 cm, this protective upstand must be increased to at least 100 cm to account for a potential fall trajectory.

For sheet-metal work, roofing, or timber construction, art. 41 OTConst specifies edge and eaves arrangements. Where roof pitch exceeds 60 degrees, personnel may only work from a mobile elevating platform or specially configured standing scaffolding, as standard perimeter edge barriers no longer provide sufficient kinematic retention.

Earthwork safety and trench shoring rules

Trench earthworks, excavation pits, and foundation shafts expose civil engineering crews to severe risks of engulfment. The stability of an unsupported cut depends on the internal shear strength of the soils, which can be heavily degraded by adverse weather or vibrations generated by traffic.

Shoring conditions and compliant excavation slopes

When the depth of an excavation exceeds the statutory threshold and the sidewalls cannot be sloped according to the mechanical strength of the soil, art. 77 OTConst requires installing trench boxes or shoring systems engineered to retain earth pressure as well as dynamic surcharges caused by plant machinery or material stockpiles. According to art. 75 OTConst, if the unsupported sloping option is selected, the embankment slope angle must match the soil type and be corrected immediately if water ingress or frost damages its stability.

The layout around excavation perimeters is likewise regulated: art. 71 OTConst provides that an unobstructed berm at least 50 cm wide must be maintained along the crest when a trench is shored. This horizontal clearance zone is increased to at least 1 m when sidewalls are sloped back, preventing spoil from sliding under the weight of pedestrian circulation.

If excavation depth exceeds 4 m or if geotechnical conditions prove unfavourable due to roadway surcharges or water seepage, art. 76 OTConst requires technical proof of stability prepared by a qualified civil engineer or geotechnical specialist prior to any work at the bottom of the excavation.

Comparative summary of dimensional and technical requirements

The following table summarises the thresholds, geometric criteria, and applicable legal provisions for each type of collective fall protection equipment on site:

Equipment categoryAction thresholdGeometric specificationsLegal requirementOrganizational measures
Perimeter guardrailFall greater than 2,00 mTop rail at 100 cm, 15 cm toeboard, clear gap < 47 cmArt. 22 and art. 23 OTConstDaily visual check and rigid fastening with no play
Facade scaffoldingFall height from 3,00 mRail upstand of 80 cm (or 100 cm if gap > 60 cm)Art. 26 OTConst, standard SIA 222Written sign-off before use, anchorages per structural calculation
Floor opening coversProven fall hazardBreak-proof, non-displaceable fasteningArt. 25 OTConstVisible marking, removal prohibited without barricading
Trench / excavation shoringDepth from 1,50 mStructural design accounting for machine loads, 50 cm bermArt. 71 and art. 77 OTConstVerification of trench struts and jacks after each rainfall event
Natural excavation batteringSlope height from 1,50 mSlope tailored to ground conditions, 1,00 m clear benchArt. 71 and art. 75 OTConstEngineer calculation report if height > 4 m (art. 76 OTConst)

Recurring site mistakes and their financial impacts

An analysis of site inspection reports across French-speaking Switzerland highlights several recurring breaches that disrupt site operations:

  • Omission of the toeboard on temporary guardrails: The absence of the 15 cm toeboard exposes personnel on lower levels to falling tools or debris. Remedying these items incurs compliance costs in the range of 450 to 1'200 CHF per level, not including delays to finishing trades.
  • Lack of scaffolding extension when pouring parapets: Failing to plan for the statutory top rail upstand when casting the top-floor edge parapet requires an emergency scaffolding lift. Unplanned work by a specialist scaffolding contractor typically generates an unforeseen surcharge of 2'500 to 6'000 CHF.
  • Stockpiling materials at the trench crest: Placing skips, excavated soil, or rebar within the 50 cm or 1 m safety strip increases lateral earth pressure, significantly raising collapse hazards and necessitating costly, unbudgeted heavy shoring.
  • Unilateral substitution with personal protective gear: Attempting to replace collective protection with safety harnesses without proving technical impossibility under art. 29 OTConst constitutes a formal infraction, liable to halt work during a SUVA inspection.

Illustrative practical cases (typical scenarios on Swiss construction sites)

The financial figures and cost estimates below are provided as illustrative examples formulated for the technical analysis of typical projects.

Typical scenario 1: Construction of a residential building in the Canton of Vaud

On a structural work site in Lausanne involving an average workforce of fourteen workers, site management coordinates the casting of an upper floor slab situated 6,50 m above ground level. The initial quote planned for temporary edge protection clamps installed along the freshly stripped slab edge. During the preparatory review required by art. 3 OTConst, the contractor and site management noted that subsequent facade works and window installations would require uninterrupted perimeter access anyway.

The team decided to erect standing scaffolding in advance in compliance with standard SIA 222 and art. 26 OTConst, equipped with top rails extending 100 cm above the future parapet level. This decision eliminated dangerous edge-protection clamp operations along exposed edges and avoided recurring assembly-disassembly costs for slab edge barriers, valued at the equivalent of 4'800 CHF in labour. Furthermore, the continuous facade netting protected ground-floor pedestrian traffic below.

Typical scenario 2: Stormwater collector trench in an urban area in Geneva

A civil engineering contractor digs a trench 2,80 m deep and 1,20 m wide along a busy roadway to install precast pipes. The team comprises five operatives and an 18-tonne tracked excavator operating close to the trench edge.

Tight municipal boundaries made sloped battering impossible. In accordance with art. 77 OTConst, the contractor installed slide-rail trench boxes designed to resist active earth pressure increased by heavy transit bus traffic. A 50 cm setback strip was strictly barricaded with rigid fencing along the trench edge under art. 71 OTConst to prevent the dumping of demolition debris. This rigorous organization prevented road settlement and ensured safe pipe laying with zero pavement damage.

00:00 - 00:15 AI Avatar: Welcome to Art Construction. On Swiss construction sites, falls from height and trench collapses pose critical risks for site management. Let's analyze the thresholds set out in the OTConst.

00:15 - 01:10 Screen and Diagrams: Visual breakdown of regulatory clearances. Starting at a 2,00 m fall height, art. 23 OTConst mandates edge protection with a top rail at 100 cm and a 15 cm toeboard in accordance with art. 22 OTConst. From 3,00 m, art. 26 OTConst requires facade scaffolding extending 80 cm above the work area. For earthworks, art. 68 OTConst governs excavations from 1,50 m deep: beyond this, sloped banks complying with art. 75 OTConst or trench shoring dimensioned under art. 77 OTConst are mandatory. Art. 71 OTConst ensures a clear berm of 50 cm or 1 m. For slopes over 4 m, verification under art. 76 OTConst by a specialist engineer becomes mandatory to avoid any endangerment under art. 229 CP.

01:10 - 01:30 AI Avatar: Legal compliance protects your teams and shields your liability. Use our verification templates to secure your construction site logs in line with Swiss requirements.

Contracts and SIA 118: free tools

Advance payments and retentions, surety bonds, price escalations, daywork reports, subcontractor monitoring.

View the contracts and SIA 118 tools

Frequently asked questions

From what exact height does edge protection become mandatory under the OTConst?

Art. 23 OTConst mandates edge protection in unprotected areas as soon as the fall height exceeds 2 m. Art. 22 OTConst sets a top rail of at least 100 cm, an intermediate rail, a 15 cm toeboard, and a maximum gap of 47 cm between elements. A typical setup costs around 45 CHF per linear metre.

When is full facade scaffolding required for building works?

Under art. 26 OTConst, facade scaffolding is required as soon as the fall height exceeds 3 m. The top rail must extend at least 80 cm above the highest fall hazard area, or 100 cm if the horizontal gap is under 60 cm. Typical rental represents an indicative budget of 18 CHF per m².

What are the requirements for an unpropped excavation over 1,50 m deep?

Art. 68 OTConst stipulates that excavations over 1 m 50 deep without shoring or trench sheeting must be sloped in accordance with art. 75 OTConst or secured by other suitable measures. For banks exceeding 4 m, art. 76 OTConst requires safety verification by a specialist engineer, typically costing around 1850 CHF in professional fees.

What clear pathway width must be maintained along the top edge of an excavation?

Art. 71 OTConst provides that the top edge must remain horizontally clear by at least 50 cm if the excavation is shored, and by at least 1 m if the wall is sloped. This prevents falling materials as governed by art. 17 OTConst. Construction site warning signs cost approximately 320 CHF per set as an illustrative example.

What criminal liability applies to site management in the event of a safety breach?

Art. 229 CP punishes anyone who intentionally breaches the recognised rules of the building trade and thereby knowingly endangers the life or physical integrity of others with a custodial sentence of up to five years or a monetary penalty. In cases of negligence, the penalty is up to three years or a monetary penalty.

What rules apply to work performed on pitched roofs?

Art. 41 OTConst mandates appropriate measures from a 2 m fall height, including roof-catch scaffolds or edge protection depending on the pitch. On roofs with a slope exceeding 60°, work is permitted only from scaffolding or a mobile elevating work platform. The daily cost of a roof-catch scaffold module runs around 65 CHF.

Rigorous control of edge protection and earthworks ensures operational safety and full compliance with SUVA and OTConst requirements. To structure all operational and environmental protocols across your construction site, explore our dedicated technical guides: