Execution self-inspections by trade: documenting the acceptance of the substrate

When the next trade receives a substrate, a sheet validated before it starts is worth more than a conflicting recollection.

On a site, each trade works on what the previous one has left: the screeder on the structure, the tiler on the screed. If the substrate is not ready and nobody wrote it down, the dispute falls on whoever works last. This page shows how execution self-inspections by trade, with a hold point to be validated before the next task, help to document the state of a substrate. The criteria, the measurements and the responsibility remain those of your company.

Art Construction ProcessusSelf-inspection sheets and site follow-up
14-day trial
  • Self-inspection sheets with a hold point to validate
  • Problem or STOP reported from the field
  • Roles: everyone sees what concerns them
  • Team, commitments and dashboard
Start the 14-day trial See the demonstration

From CHF 99 per month, excl. VAT. Trial with no card required.

The substrate is received, the defect appears, and nobody had written it down

A site is a chain. The screeder delivers a surface, the tiler receives it, the painter receives another. At each handover, someone decides, often without saying so, that the substrate is ready enough to continue. If a defect appears later, the first question is factual: what state was the substrate in when the next trade started, and who noted it?

Three situations are often met: a doubtful substrate accepted for fear of losing one’s slot, a defect reported verbally with no record, a check omitted for lack of time. In each case, the dispute is then settled on recollections.

Examples of points to check, without figures

These examples are generic. The limit values and the measurement methods come from the applicable standards, the manufacturers’ technical data sheets and the site supervision, not from this page.

What Processus brings to self-inspections and substrate acceptance

Processus lets you write a self-inspection sheet for each type of work, have it used on site and follow what has been validated. The functions below exist in the software in service.

Sheet with a hold point

The sheet lists the points to check for a trade. The hold point must be validated before the next task.

Problem and STOP from the field

If the substrate is not ready, the person reports a problem or a STOP from the field, with their comment. The foreman, the site manager and the business owner are alerted.

Roles and overview

Roles set who sees what. To keep the overview, the site manager and the business owner rely on the team, the commitments and the dashboard.

Exportable data

The data stays exportable at any time: you can hand it to whoever needs it if a dispute arises.

A validated sheet does not prove that the substrate was perfect: it shows that a check was planned and validated before work began.

Three steps to receive a substrate while keeping a record

The method is the same for a screed, a waterproofing layer or tiling: only the sheet changes from one trade to another.

Step 1: write the trade’s sheet

List the points to check on the trade’s own work and on the substrate received, then set the hold point: the item to be validated before the next task. The criteria come from the standards and the site supervision.

Step 2: check before starting work

The trade finishing fills in its sheet; the trade arriving checks the substrate before starting. As long as the hold point is not validated, the next task waits.

Step 3: report, correct, follow

If the substrate is not ready, report it as a problem or STOP; the foreman, the site manager and the business owner are alerted. The company decides on the correction.

Paper sheet, spreadsheet or procedures software: the record left between two trades

A paper sheet or a spreadsheet is already better than no check at all. The difference lies between two trades: who is alerted, who sees what, and what stops the next task. The table compares categories of approach, without brands.

What record of a self-inspection each approach leaves
CriterionPaper sheetsSpreadsheetProcedures software (Processus)
Having the sheet on sitePrinting and filing to arrangeFile to send and open on siteSheet used from the field
Hold point before the next taskOrganisational rule to be enforcedOrganisational rule to be enforcedHold point to validate before the next task
Reporting a substrate that is not readyCall, message or note on the sheetComment in a cellProblem or STOP from the field; foreman, site manager and business owner alerted
Knowing who sees whatDepends on who holds the sheetDepends on the file’s permissionsRoles: who sees what
Finding and extracting the dataSearching through bindersReusable fileData exportable at any time

Categories of approach, non-exhaustive comparison. The content of the sheets, the limit values and the acceptance of a substrate are for the company, the applicable standards and the site supervision.

14-day trial: a real sheet, then the price and limits

During the 14-day trial, with no card required, take a real sheet: that of the trade that most often receives a doubtful substrate in your company. Write it, have it used on a site and see whether the hold point changes how things unfold. Nothing is charged at the end.

After that, the price follows the size of the company: CHF 99 per month for 1 to 5 people, CHF 179 for 6 to 20 and CHF 299 for 21 to 50, excl. VAT. The count covers the business owner, the site managers and the office; the rest of the team is included, with all functions.

Frequently asked questions

What is a hold point in a self-inspection sheet?

It is the point on the sheet that must be validated before the next task begins. For example, before laying a covering, the state of the substrate is checked and then validated. What you check there, and by which criteria, is for your company to decide together with the applicable standards.

Does the software supply limit values for moisture or flatness?

This page gives no figures, and the software does not substitute for reference sources. Acceptance criteria come from the applicable standards, the manufacturers’ technical data sheets and the site supervision. You carry them into your sheets; Processus helps to get them applied.

Does a self-inspection replace acceptance by the site supervision?

No. Self-inspection is the check that each company carries out on its own work and on the substrate it receives. Acceptance of the work, with its findings and reservations, follows what the contract and the SIA 118 standard provide. The two complement each other.

Who can see the sheets and the reports?

Roles set who sees what. Before starting, decide who fills in the sheets, who follows the reports and who consults the dashboard. This split is an organisational rule of your company: the software reflects it, it does not set it for you. To pass information to a third party, you can export the data.

Going further

Software pages, tools that need no registration, guides on self-inspection and neighbouring pages on MSST and temporary workers.

Sources and limits. Functions described according to Processus in service on 26 November 2026. Generic examples of trades, with no normative value: acceptance criteria, measurements and responsibilities are decided with the applicable standards and the site supervision. Prices in CHF, excl. VAT; the pricing page is authoritative.