Practical guide

Post-Award Debriefing: Access to the Tender Opening Record

Access to the tender opening record and award debriefing in Switzerland: LMP and AIMP rules, transparency, appeal deadlines and tenderer rights.

Table of contents
The 3 Major Site Risks
  1. Financial / Margin: Outright loss of estimating and pricing costs (typically 1,5 % to 4,0 % of the submitted tender amount, representing an illustrative loss of 15 000.00 CHF to 60 000.00 CHF on a 1 500 000.00 CHF tender) without understanding the competitive gap, restricting future tactical margin adjustments under art. 41 LMP.
  2. Legal / Joint Body / SUVA: Irrevocable forfeiture of the right of action by letting the deadline under art. 56 LMP expire without requesting access to case documents to uncover potential breaches of equal treatment or wage protection rules under art. 12 LMP.
  3. Administrative / Acceptance: Formal rejection of a request for reconsideration or an appeal due to lack of access to the opening record and award reasoning, depriving the unsuccessful firm of tangible evidence to challenge a pricing irregularity under art. 38 LMP.

The publication of an award decision marks a critical milestone for tenderers in Switzerland. For company leadership, cost estimators, and bid managers, the conclusion of an open or selective procedure must not end with the mere receipt of an adverse outcome. Exercising procedural oversight rights, particularly inspecting the tender opening record and holding a formal debriefing with the contracting authority, is governed by strict procedural requirements under the LMP and the AIMP. This review allows firms to analyze the rejected tender's commercial standing, assess the consistency of the scoring methodology used, and verify scrupulous compliance with equal treatment enshrined in art. 11 LMP.

Access to the procurement file remains strictly regulated to protect competitors' trade secrets and technical know-how. The tender opening record logs the identity of tenderers, the submission date, and the total gross or corrected sum read out during the session. Debriefing sessions offer insight into qualitative evaluations without breaching the confidentiality required by public procurement law. Acting with diligence and methodical rigor is the only way to identify potential assessment flaws before the statutory appeal deadline under art. 56 LMP expires.

The tender opening record is a foundational administrative document in public procurement procedures. Drawn up immediately upon the submission deadline, it records the physical state of the bids delivered, the tenderers' identities, the receipt dates, and the announced total amounts. Under the principles of transparency, objectivity, and equal treatment set out in art. 11 LMP, this log protects all parties against any subsequent price alterations or document substitutions.

In open procedures governed by art. 18 LMP and selective procedures under art. 19 LMP, opening takes place formally before at least two representatives of the contracting authority or a public official. By contrast, for invited procedures under art. 20 LMP or direct awards under art. 21 LMP, sharing the opening record with competitors follows more restrictive rules, often limited to a summary notification of the final outcome.

Estimators must distinguish between two concepts that are frequently confused: the price read out at opening and the decisive price determined after arithmetical verification. Under art. 38 LMP, the contracting authority verifies compliance with formal requirements and rectifies obvious calculation errors ex officio. The opening record reflects the gross figures from the original schedules, whereas the final evaluation matrix incorporates these arithmetical corrections, alongside any accepted variants or conditional discounts.

Debriefing request protocol and file consultation

As soon as the decision is published on the simap.ch platform or formally served, an unsuccessful tenderer holds a legitimate interest worthy of protection to request a debriefing from the contracting authority. This step seeks to clarify how their own tender ranked against the award criteria published under art. 29 LMP, including price, technical merit, or the plausibility of the bid.

The distinction between right of access and business secrets

Access to the procurement file is not an unlimited right of inspection. The contracting authority must balance the principle of transparency with the mandatory obligation to safeguard the confidentiality of tenderers' information under art. 11 LMP. An unsuccessful tenderer may claim the right to inspect the tender opening record, the anonymized scoring matrix, or their own detailed evaluation report.

Trade secrets, internal cost breakdowns, a competitor's proprietary logistics concepts, and nominative certificates from pension institutions are strictly excluded from public inspection. The authority systematically redacts these sections before permitting on-site review or providing copies.

Alignment with the statutory appeal deadline

Holding an oral debriefing session or receiving written grounds neither stays nor extends the statutory time limit for an appeal. Under art. 56 LMP, an appeal against an award decision must be lodged in writing within a strict deadline of 20 days following its notification. Firms must therefore submit their inspection request on the very first business day following notification of the result to secure the opening record before this peremptory deadline lapses.

Analytical comparison of tender opening record components

Item recorded in the opening recordVerifiable content for the tendererApplicable legal basis or referenceOperational check for the contractor
Identity of tenderersExact company name and legal structure of bidding entitiesart. 11 LMP and art. 31 LMPCheck for any conflict of interest or excluded entity under art. 44 LMP.
Tender arrival date and timePostal timestamp or electronic simap.ch receiptart. 38 LMPVerify absolute compliance with the submission deadline; late bids must be rejected.
Total amount of the tender as read outGross submitted price before any error correctionsart. 38 LMPCompare this figure with the published award result to spot any corrections.
Contractor variantsPresence of variant bids and corresponding total pricesart. 29 LMPCheck whether variants were expressly authorized in the specifications.
Reservations stated at submissionStatements of special conditions or derogationsart. 44 LMPIdentify any material formal defects warranting disqualification of the tender.

Common mistakes when reviewing the record and financial impact

A superficial review of the opening record exposes a firm to significant setbacks. The first mistake is equating the ranking based on prices read out at opening with the final ranking under art. 41 LMP. If a competing firm makes an obvious multiplication error in a bill of quantities, ex officio correction by the contracting authority under art. 38 LMP alters the total sum, turning an apparently more expensive bid into the most advantageous tender.

The second mistake is failing to act when confronted with an abnormally low price. When the record shows a competitor pricing 30 % below the general average, the contracting authority is legally bound under art. 38 LMP to demand detailed clarifications on compliance with participation conditions, specifically observance of minimum wages and worker protection governed by art. 12 LMP. Failing to verify whether the authority examined this issue may cost an aggrieved firm a contract worth 850 000,00 CHF, with a net loss of profit around 68 000,00 CHF.

Finally, waiting passively for a verbal debriefing scheduled late by the client is a frequent procedural trap. If the meeting takes place on the twenty-second day after notification, the right of appeal is definitively forfeited under art. 56 LMP, rendering the award unassailable.

Illustrative practical cases (typical scenarios on Swiss construction sites)

The amounts and scenarios described below are illustrative examples constructed for technical analysis, rounded to the nearest 0,05 CHF, including Swiss VAT of 8,1 %.

Standard Scenario 1: Masonry and reinforced concrete works in the Canton of Vaud

A structural work contractor employing 35 workers tenders for the construction of a municipal school complex in the Canton of Vaud. The total submitted amount is 2 450 120,45 CHF incl. VAT. Upon publication on simap.ch, the contract is awarded to a competitor for 2 180 500,80 CHF incl. VAT.

The very next day, the company requests access to the tender opening record. The document shows that at the opening session, the successful competitor's tender had been read out at 2 580 500,80 CHF incl. VAT. The 400 000,00 CHF variance stemmed from an arithmetical correction carried out by the contracting authority on a carry-over page in the standard item catalogue.

Reviewing the validity of this correction under art. 38 LMP, management observes that the change addressed an unquestionable clerical error (transposition of two figures in a subtotal). The authority's intervention was legally justified, sparing the company a ill-advised appeal before the administrative court and saving procedural and lawyer fees of roughly 15 000,00 CHF.

Standard Scenario 2: Refurbishment of ventilation systems in the Canton of Geneva

A building services SME with 12 employees takes part in an open call for tenders to replace an air-handling system in an administrative building in Geneva. The SME's tender stands at 485 230,60 CHF incl. VAT. The contract is awarded to a third-party firm for 310 150,20 CHF incl. VAT.

Prompt inspection of the opening record confirms that this particularly low amount was read out as early as the tender opening. The company then files a written debriefing request focusing specifically on price plausibility under art. 29 LMP and the obligation to clarify abnormally low bids under art. 38 LMP.

The contracting authority supplies a summary of its assessment: the successful tenderer justified its price by demonstrating the use of modular prefabricated components that fully satisfy the specifications, without breaching working conditions or prevailing wages under art. 12 LMP. Swift access to the opening record provided the firm with complete transparency on the legality of the procurement within 8 days, safeguarding management decisions without futile legal obstruction.

Calls for tenders: free tools

Direct public procurement tenders, AIMP thresholds by canton, converting SIA 451 to Excel, quantity takeoff from an IFC model.

View tendering tools

Frequently asked questions

Which document should you request immediately during a cantonal award debriefing?

Demand access to the tender opening record and the anonymized evaluation matrix. Under the LMP and the AIMP, the contracting authority must maintain transparency throughout proceedings. This document records the total amounts read out, such as 1 450 000,00 CHF incl. VAT, alongside any discounts stated at the opening session.

Can the client refuse access to the tender opening record?

No, the principles of transparency and equal treatment establish the right to inspect recorded prices. Only business secrets and proprietary technical methods belonging to competitors remain confidential. In public procurement, the initial gross amount must always be disclosed to unsuccessful tenderers.

How can you spot an abnormally low bid using the tender opening record?

Compare the winning price, for instance 890 000,00 CHF incl. VAT, with the average of the other submitted bids. Under art. 38 LMP, the contracting authority must verify abnormally low prices to ensure requirements are met. An extreme discrepancy lacking written clarification warrants targeted questions during the debriefing.

What is the deadline to appeal after an unsatisfactory debriefing?

You must act quickly because the appeal period is not suspended. Under art. 56 LMP, a reasoned appeal must be filed in writing within 20 days of official notification. Obtaining the opening minutes right at the start of this period is critical.

Is a discrepancy between the announced price and the corrected price legal?

Yes. Under art. 38 LMP, the contracting authority automatically rectifies obvious calculation errors after opening. A bid read out at 520 000,00 CHF incl. VAT may therefore be corrected to 515 250,35 CHF incl. VAT. The opening minutes make it possible to identify the existence and exact scale of these arithmetic adjustments.

Can a ground for exclusion be challenged upon reviewing the opening minutes?

Absolutely. Under art. 44 LMP, exclusion for formal defects requires material non-compliance. The opening minutes record the submission time, postal mark, and envelope integrity. If your tender was wrongly discarded for an alleged delay, these opening records serve as decisive evidence.

Strategic review of the debriefing and record consultation

Methodical review of tender opening minutes alongside technical debriefings helps contractors evaluate price variances objectively, fine-tune future quantity take-offs, and verify strict compliance with public procurement rules. To strengthen the compliance of your tender submissions and master every Swiss award procedure, explore our specialised guides: