Abnormally low tender: the lowest price always receives the highest score (ATF 143 II 553)
· 9 min read
Financial stakes An engineering contract worth CHF 6'799'426 (excl. VAT) in Zurich, lost by the lowest tenderer: CHF 5'938'839 versus CHF 7'408'504 for the second lowest.
Legal basis ATF 143 II 553; Art. XIII para. 4 let. b of the WTO Agreement on Government Procurement, Art. 13 let. f of the AIMP (Intercantonal Agreement on Public Procurement, 2001 version), Art. 3 and 5 of the Internal Market Act (LMI), Art. 50 para. 1 Cst. (Federal Constitution of the Swiss Confederation, municipal autonomy).
Fatal error Relying on a very low price without being able to substantiate the hours supporting it — or, from the contracting authority's perspective, lowering the price score simply because it appears too low.
Immediate countermeasure Document the hours, the difficulty level, and the underlying assumptions for every low bid, and carefully review the sub-criteria of the "price" criterion prior to submission.
1. The facts: three bids, a discrepancy of 17,000 hours
The City of Zurich wished to renovate the Seewasserwerk Moos, a lake water treatment plant with a capacity of 100'000 m³ per day. The works had to be executed during active operations while preserving protected heritage buildings. On 17 July 2015, it launched an open procedure for engineering services (planning and design).
Announced award criteria: quality of the tender 30%, fees 30%, references 20%, qualification 20%. The "fees" criterion was broken down into three sub-criteria: the tender sum (70%), the hourly rates for additional services (10%), and the plausibility of the offer (20%). The tender documents expressly warned that deductions would be applied for implausible assumptions or calculations.
Three tenders were submitted: CHF 5'938'839, CHF 7'408'504, and CHF 11'833'039.44. The City selected the second tender (89.6 points versus 85.8 points for the cheapest) and awarded the contract on 9 December 2015 at the price of CHF 6'799'426 excl. VAT. What dragged down the score of the lowest bidder: difficulty factors considered incomprehensibly low, an overall total of hours lower by 17'000 hours — roughly ten person-years, including 16'000 hours in process engineering, the core of the project — and the proposal to transfer part of the engineering services to suppliers earlier than required.
The Zurich Administrative Court struck out the "plausibility" sub-criterion, reallocated its weighting across the other two, and inverted the ranking: 90.6 points versus 88.9. It ordered that the contract be awarded to the lowest bidder (judgment of 27 September 2016). The City and the successful tenderer appealed to the Federal Supreme Court.
2. What Swiss law says
A low price is not unlawful
Tenderers are free to calculate their prices. A bid priced below cost is not impermissible in itself, provided the tenderer meets the eligibility criteria and the award conditions. If a bid appears unusually low, the contracting authority may request clarifications. If it proves deficient, the authority may exclude it or score it lower on account of those qualitative deficiencies — not because of its price.
Under the price criterion: the lowest always wins
Under the "price" criterion, the lowest tender must always receive the highest score relative to the other bids, although not necessarily the maximum score possible. A deduction applied directly to the price score on the grounds that the price is "implausible" or "does not cover costs" is inadmissible. For complex projects, price must carry a weight of at least 20%, and the evaluation method must not dilute it further.
However, the plausibility of the services may be evaluated
The Federal Supreme Court allows a plausibility criterion that assesses, based on objective elements, the scope of services covered by the price: number of hours, assumed level of difficulty, and consistency with the requested project concept. In a complex contract, this applies even to a fixed lump-sum price: it takes into account the well-known risk of subsequent disputes concerning additional claims. This constitutes an assessment of quality and represents a milder measure than outright exclusion, allowing the bid to remain in contention.
Transparency and the true weighting of price
Plausibility was set out in the tender documents, along with the notice of potential deductions: the principle of transparency was fully respected. The effective weight of price fell from 30% to 24% (21% for the basic price alone): the Federal Supreme Court considered this to be the lowest acceptable limit for a procurement of such complexity. It upheld the appeals of both the City and the successful tenderer.
Note: the judgment applies the law in force prior to the revision of the AIMP; the conceptual framework of the decision (price evaluated strictly for what it is, services assessed as a matter of quality) remains a benchmark, but every tender must be read according to its own terms.
3. What this error actually costs
| Item | Amounts and figures from the judgment |
|---|---|
| Tenders submitted | CHF 5'938'839; CHF 7'408'504; CHF 11'833'039.44 |
| Award | CHF 6'799'426 excl. VAT (decision of 9 December 2015) |
| City's scores | 89.6 versus 85.8 points (a gap of 3.8 points out of 100) |
| Scores after Cantonal Court | 88.9 versus 90.6 points: the ranking is inverted |
| Discrepancy in hours between both tenders | 17'000 hours, equivalent to roughly ten person-years |
| Actual weight of base price | 21% of the total score, against a jurisprudential minimum of 20% |
For the tenderer, the cost of an indefensible bid is not merely a lost discount: it is a contract worth nearly seven million francs forfeited over a few quality points. For the contracting authority, it means an award contested all the way to the Federal Supreme Court.
4. Site protocol: four immediate actions
- Explain every deviation. Hours per project phase, difficulty factor, assumptions: if your tender is the lowest, draft the page that answers "why this specific number of hours?" before being asked.
- Do not base your price on a delivery model not envisaged by the tender documents. In this case, offloading engineering tasks to suppliers earlier than planned negatively affected the score.
- Review the sub-criteria under the "price" criterion. If plausibility is listed along with announced point deductions, it will be strictly applied. If a criterion appears unlawful to you, challenge it upon publication: in this case, the terms had not been challenged at the outset, and the judgment leaves open the question of whether the cantonal court was even entitled to review them after the fact.
- Benchmark your pricing against an independent market reference prior to submitting: compare quantities, labour time, and prices against local cantonal standards.
A pricing benchmark before submitting your tender. The ACIP Index provides price benchmarks by trade code (CFC) and by French-speaking canton, including daywork rates; the guide on using the ACIP index as a tender price benchmark explains how to apply it. For detailed rules, consult the guide on abnormally low tenders and wage dumping and, to monitor upcoming tenders, check the Simap public procurement radar.
5. Frequently asked practical questions about this case
Is a bid priced below cost prohibited?
No. The Federal Supreme Court reiterates that tenderers are free to calculate their prices: an offer priced below cost is not unlawful per se, provided the tenderer meets the suitability criteria and the tender conditions. Where doubt exists, the contracting authority may request further information.
Can the price score of a tender be reduced because it is deemed too low?
No. Under the price criterion, the lowest tender must always receive the highest score relative to the other bids, although not necessarily the maximum score possible. A deduction based on an "implausible" or "cost-insufficient" price is impermissible. Any defects identified may, however, lead to the tender being excluded or scored lower elsewhere.
Where can the contracting authority assess the quoted hours?
Within a plausibility criterion that assesses the scope of services covered by the price, based on objective criteria set out in the tender documents. In Zurich, the City had announced that deductions would be made for implausible assumptions or calculations; the Federal Supreme Court treated this as a qualitative assessment, not an assessment of price.
Official sources
Compliance notice. This article is a technical and educational analysis based on Swiss law in force and published decisions; the parties are anonymised as in the judgments. It does not replace the advice of a specialist lawyer for an ongoing dispute. Art Construction is independent of the SIA and CRB: their standards are not reproduced. Legal texts and judgments reviewed on 18 November 2026. This version is an automatic translation of the French article, which remains the authoritative text in the event of any discrepancy.