Building Permits in Geneva (Accelerated APA vs Ordinary DD): Preparing Plans for OAC e-Démarches

Prepare your APA and DD permit plans on e-Démarches for the OAC in Geneva. CAD drawing rules, building profiles and coordination under art. 22 LAT.

Table of contents
The 3 Major Site Risks
  1. Financial / Margin: An application rejected on the cantonal e-Démarches platform results in drafting revision costs and a planning delay on the order of 10 000 CHF to 25 000 CHF depending on the scale of the structure, pursuant to the principles of art. 22 LAT.
  2. Legal / Joint Body / SUVA: A lack of inter-agency coordination or starting works early without a formal permit exposes the lead consultant to an administrative site shutdown ordered by the Office des autorisations de construire, pursuant to the Geneva cantonal building act.
  3. Administrative / Acceptance: A geometric mismatch between the official cadastral surveyor map and the electronically submitted sections halts the issuance of the final occupancy permit and compromises the verification process under standard SIA 118.

In Geneva, submitting a digital application to the Office des autorisations de construire requires a flawless grasp of the distinctions between the accelerated APA procedure and the ordinary definitive application (DD) via the e-Démarches portal. This technical guide is addressed to architects, civil engineers and draughtspeople tasked with preparing plans compliant with the Swiss coordinate system, statutory building profiles and the vector legibility requirements of cantonal departments.

The classification of the project determines the scope of drawings to generate, from 1:100 layout plans to elevation profiles linked to the official height datum. Rigorous planning pursuant to art. 22 LAT and art. 25a LAT ensures the substantive consistency of technical preliminary notices from the OAC, preventing recurrent requests for supplementary documents that stall the construction site opening schedule.

Technical selection criteria: accelerated APA procedure or ordinary DD application

In Geneva, the Office des autorisations de construire applies a strict distinction between the accelerated procedure (APA) and the ordinary definitive application (DD). This initial choice dictates the drawing scale, the level of geometric detail, and the precise set of plans to upload to e-Démarches.

The APA procedure is reserved for internal alterations that do not affect the load-bearing structure, changes of use with no impact on public utilities, and minor ancillary structures. For these applications, architectural drawings are prepared at 1:100, focusing on internal circulation, openings, and user safety.

Conversely, any creation of gross floor area, volumetric modification visible from the public domain, or substantial excavation falls under the ordinary DD procedure. Pursuant to art. 22 LAT, authorization requires compliance with the building zone designation and adequate land servicing. When the project requires simultaneous approval from multiple cantonal or municipal departments for utilities or sanitation, the coordination principles set out in art. 25a LAT apply to ensure simultaneous public inquiry and substantive consistency among decisions.

Vector Drawing Standards and Georeferencing on e-Démarches

The cantonal e-Démarches system requires vector PDF files exported directly from CAD software. Layers must be rigorously organised with zero pixelation. Swiss colour conventions apply strictly: black or grey for existing masonry and retained structures, yellow for elements to be demolished, and red for proposed new works.

Each drawing sheet must be georeferenced to the Swiss MN95 coordinate system and tied to the official LN02 vertical datum. Omitting finished elevation levels for natural and developed ground leads to immediate application rejection during formal vetting. Whenever demolition or excavation volume exceeds 200 m³, art. 16 OLED requires attaching a waste management plan detailing the nature, volume, and disposal channels of construction waste.

Comparative drawing requirements table: APA vs DD

Drawing parameterAccelerated procedure (APA)Ordinary definitive application (DD)
Official cadastral excerpt1:500 site plan showing the footprint of modificationsCertified official 1:500 site plan showing building profiles, easements and building lines
Floor and roof plans1:100 scale limited to modified storeysComprehensive 1:100 scale for all storeys, basements and roofs
Elevation sectionsPartial sections through internal intervention areasFull longitudinal and cross sections showing existing and proposed ground levels
Façade elevationsRequired only if the external envelope is modifiedAll four elevations complete with height benchmarks and envelope profiles
Earthworks and wasteSimplified note if no significant excavationEarthwork profiles and mandatory waste management plan if volume exceeds 200 m³ (art. 16 OLED)
Utility coordinationIdentification of existing connections being retainedComprehensive drainage plan, runoff disposal, and inter-agency coordination (art. 25a LAT)

Recurrent CAD errors and financial impacts

Geneva planning vetting penalises technical discrepancies on drawings. Common grounds for refusal or postponement include:

  • Failing to dimension statutory boundary setback distances on the cadastral site plan.
  • Geometric discrepancies between rough structural work dimensions and finished dimensions including thermal insulation.
  • Omitting the natural ground profile beneath the proposed finished ground line on sections.

A formal rejection notice suspends planning operations for several weeks. Updating and correcting drawing sets routinely generates unexpected technical fees between 3 500 CHF and 8 000 CHF for the lead consultant. For the client, the resulting delay causes holding and carrying costs estimated in the region of 15 000 CHF to 40 000 CHF.

Illustrative practical cases (typical scenarios on Swiss construction sites)

The figures and scenarios described below are illustrative examples developed to clarify the drawing submission methodology and in no case represent actual construction sites.

  • Scenario 1: Office conversion into a medical practice in Carouge (Canton of Geneva). For this commercial project of 220 m² mobilising a site team of 6 finishing work tradespeople, the architectural firm selects the APA procedure. With no changes to façades or load-bearing elements, 1:100 plans detail partition alterations in yellow and red, securing rapid approval without a public inquiry.
  • Scenario 2: Multi-family residential building in Vernier (Canton of Geneva). For this sixteen-unit residential development over an underground basement mobilising a structural work team of 16 operatives, the ordinary DD application is required. The file includes sections tied to LN02, statutory building envelope profiles, and 900 m³ of earthworks subject to art. 16 OLED, with inter-agency coordination under art. 25a LAT.

Surfaces, standards and permits: free tools

SIA 416 floor areas and volumes, cantonal zoning ratios, U-values and dew points, acoustics, planning enquiry requirements.

View engineering tools

Frequently asked questions

When should an APA procedure switch to a DD application in Geneva?

Switching to the ordinary procedure is mandatory as soon as the project alters the building's use, impacts major building profiles, or requires coordination under art. 25a LAT across multiple cantonal departments.

Which file format does the OAC require on e-Démarches?

The e-Démarches portal requires vector PDF/A files that are unencrypted and drawn strictly to scale. To organise quantity take-offs or field management, explore our dedicated solution on /portail/.

Which waste sorting plans must be submitted under the OLED in Geneva?

Starting from two hundred cubic metres of waste, art. 16 OLED requires a detailed waste disposal concept. To evaluate landfill and tipping fees, refer to regional data on /indice-acip/.

Does a solar installation require an APA procedure in Geneva?

Within a building zone, panels conforming to art. 32a OAT and art. 18a LAT only require prior notification, unless installed on a listed building, which demands an ordinary permit.

How should the site health and safety plan be uploaded to e-Démarches?

Under art. 4 OTConst, a written plan specifies preventative measures for the construction site. This document is submitted digitally, while fee accounting and project billing are handled on /erp/.

What are the administrative fees for an APA application?

Cantonal administrative charges generally range between 300 CHF and 1 500 CHF for an application that complies with art. 22 LAT standards in Geneva.

To learn more about administrative procedures and statutory permit application standards across other French-speaking cantons, explore our technical guides:

Art Construction is an independent company: it is not affiliated with the SIA, CRB, SUVA, or KBOB. Referenced norms and standards point to publications from these bodies; only official versions are legally binding.