The 3 Major Site Risks
- Financial / Margin: Risk of additional fee expenses around 4 000 CHF to 8 000 CHF during iterative redraws of plans that do not match cantonal templates. Waiting times prolong capital tie-up under SIA 118.
- Legal / Parity / SUVA: Risk of the application being declared inadmissible under art. 22 LAT, which stipulates that no building or installation may be constructed or altered without approval from the competent authority.
- Administrative / Handover: Risk of the public inquiry being blocked by the commune or cantonal department, suspending the coordination of decisions required under art. 25a LAT and delaying the opening of the construction site.
The digitisation of public inquiry procedures via the FRIAC platform in the canton of Fribourg and the eBau portal in the canton of Bern fundamentally changes how building permit files are reviewed. For architects and draftspersons, initial acceptance now depends strictly on whether digital files comply with cantonal building authority requirements. The lack of proper georeferencing or improper handling of vector layers triggers an immediate return before any official publication.
This technical guide details how to prepare the 2D and 3D deliverables required on FRIAC and eBau, from file naming conventions to the standardized PDF/A profile. By applying the coordination principles of art. 25a LAT and the reference scales recognised by the Fribourg and Bern authorities, designers avoid missing-document notices and safeguard municipal public inquiry schedules.
Graphical and digital requirements on FRIAC and eBau
Submitting without a request for supplementary documentation on FRIAC in the canton of Fribourg or on eBau in the canton of Bern relies on strict compliance with Swiss drafting standards and precise calibration of digital files. Under art. 22 LAT, a building permit may only be granted if the project conforms to the zoning plan and is adequately serviced. These elements must appear immediately on site plans based on the official cadastral surveyor's drawing.
Technically, each uploaded drawing must be generated as native vector PDF/A, un-scanned, with embedded fonts and at a consistent scale. The graphic reference bar scale at the bottom of the sheet remains mandatory to offset any display distortion during verification by the commune or cantonal services. Standardised colours for work on existing fabric must be strictly respected: grey for preserved existing structures, yellow for demolished portions, and red for proposed new works.
Coordinating drawings is another critical point. When a file requires coordination within the meaning of art. 25a LAT, the cantonal authority simultaneously checks the consistency between the site plan, terrain cross-sections, and height profiling tied into the official Swiss coordinate system. If the project involves partial or full deconstruction of a structure, art. 16 OLED requires recording the type, quality, and volume of waste in the annexes if its volume is likely to exceed 200 m³ or if it contains pollutants, meaning these demolition volumes must be indicated directly on the site plans.
Comparative requirements matrix: FRIAC (Fribourg) vs eBau (Bern)
| Technical or administrative criterion | FRIAC platform (Canton of Fribourg) | eBau platform (Canton of Bern) |
|---|---|---|
| Authentication system | Secure State of Fribourg account with qualified electronic signature or signed paper submission | Cantonal BE-Login portal with electronic validation and submission of the signed summary form |
| Management of property owners' signatures | Qualified digital signature permitted or scanned signature sheet appended to the initial dossier | Signature via BE-Login or submission of the physically signed summary sheet to the commune |
| Surveyor site plans | Official digital extract from the surveyor stating public inquiry submission and boundary profile levels | Official site plan extracted from the Bern cadastre, integrating alignment and finished ground levels |
| PDF layer requirements | Single-layer PDF/A files without locked layers hiding graphical elements | Flattened PDF/A files, vectorised text, minimum resolution ensuring legibility of dimensioning |
| Plan language management | Application in French or German depending on the official linguistic status of the relevant commune | Bilingual dossier or drafted in the language of the commune (mostly German, French in the Bernese Jura) |
| Demolition and waste management | Sorting schedule according to art. 17 OLED linked to the yellow hatched surfaces on the plans | Cantonal construction waste annex attached to detailed deconstruction plans |
Recurring modelling errors and financial impacts
Omitting natural and modified ground levels is the primary cause of dossier suspensions. A 15 cm discrepancy between section AA and the South elevation halts the height profile assessment, triggering weeks of delay. Administrative re-examination fees and financing costs on an immobilised plot frequently result in additional costs around 4'000 to 12'000 CHF for the client.
A second frequent mistake is confusing art. 18a LAT with the regular procedure for solar panels. If the installation projects beyond the roof pitch by more than 20 cm under art. 32a OAT, it is no longer exempt from permit requirements and demands a formal public inquiry with complete elevations. Submitting a simple notification form instead of a complete application stalls municipal processing.
Illustrative practical cases (typical scenarios on Swiss construction sites)
The figures and scenarios below are illustrative examples compiled for methodological training.
Standard Scenario 1: Mixed renovation and vertical extension in the canton of Fribourg
In a Fribourg commune, a project involves a two-storey vertical extension on a three-storey building, mobilising a team of 14 people during structural work. The architecture firm prepares the dossier on FRIAC. The main challenge lies in accurately showing the existing structure in grey, roof cut-outs in yellow, and the projected timber frame in red. The chosen demonstration relies on a continuous longitudinal section linking the street, the ground floor, and boundary lines. Incorporating the waste management report in accordance with art. 16 OLED prevented any rejection by the cantonal department, as screed and roof structure demolitions exceeded 240 m³.
Standard Scenario 2: Siting a commercial workshop in the Bernese Jura
In the canton of Bern, a business plans to construct an operational building with offices for 8 employees. The tender on eBau required complex grading of the sloping site. To prevent any formal requests for additions from the prefecture, the draftsperson modelled terrain cross-sections at 5-metre intervals, linking excavation profiles with external works. Prior coordination mandated under art. 25a LAT between the civil engineering authority and the water and waste management office was documented on a dedicated composite coordination drawing, ensuring the dossier was accepted upon first municipal review.
Surfaces, standards and permits: free tools
SIA 416 floor areas and volumes, cantonal zoning ratios, U-values and dew points, acoustics, planning enquiry requirements.
Frequently asked questions
Which certified digital format is required on FRIAC for plans?
FRIAC requires unlocked PDF/A format with official georeferencing. A non-compliance rejection incurs municipal administrative fees around 150 CHF under art. 22 LAT.
How should the waste management concept be submitted on eBau Bern?
The waste management concept is uploaded directly via eBau. A preventive pollutant diagnostic around 800 CHF prevents any hold-ups under art. 16 OLED.
What electronic signature is required on FRIAC and eBau?
A Swiss qualified electronic signature is required to validate the application. Manual regularisation with the commune incurs out-of-pocket expenses around 50 CHF under art. 25a LAT.
Must safety measures be included in the digital application?
The municipal authority checks site access and planned installations on the site plan. Early document drafting prevents an adaptation surcharge around 600 CHF under art. 4 OTConst.
How do you submit a rooftop solar project on the cantonal portal?
Compliant installations require a formal notification with dimensioned plans. Any subsequent regularisation incurs additional municipal fees around 120 CHF under art. 18a LAT.
What is the effect of a request for additions on the public inquiry?
A technical non-compliance suspends review by cantonal and municipal departments. This interruption incurs administrative extension fees around 350 CHF under art. 22 LAT.
Strict compliance of vector plans guarantees validation without requests for additions on cantonal portals. Explore our practical guides:
- Compiling a Public Inquiry and Building Permit File in Switzerland (CAMAC, APA, FRIAC, eConstruction)
- Submitting a Successful CAMAC File in the Canton of Vaud (ATC / LATC): Required Plans and Specific Questionnaires
- Building Permits in Geneva (Accelerated APA vs Standard DD): Preparing Drawings for OAC e-Démarches
- Digital Submission on eConstruction in Valais (Commune vs CCC): Required PDF/A Formats and Signatures