Digital Submission on eConstruction in Valais (Commune vs CCC): Required PDF/A Formats and Signatures

Guide to submitting building permits on eConstruction in Valais: PDF/A requirements, qualified electronic signatures, and division between commune and CCC.

Table of contents
The 3 Major Site Risks
  1. Financial / Margin: Adaptation costs and iterative engineering overheads of the order of 3'500 CHF to 9'000 CHF following the rejection of a non-compliant vector file, engaging diligence under art. 364 CO.
  2. Legal / Joint Body / SUVA: Suspension of the public inquiry following non-compliance with the inter-departmental coordination requirements set out in art. 25a LAT between the commune and the Cantonal Building Commission.
  3. Administrative / Acceptance: Formal inadmissibility of the application due to non-compliance with the PDF/A format or lack of a qualified electronic signature, blocking authorisation under art. 22 LAT.

The paperless processing of building permit applications in the canton of Valais requires heightened technical rigor on the eConstruction platform. Designed for architects, draftspersons, and civil engineers, this digital protocol formally distinguishes municipal decision-making powers from those of the Cantonal Building Commission (CCC), particularly for projects outside the building zone reviewed under art. 24 LAT. Every official site plan, elevation cross-section, and technical drawing must satisfy long-term archiving requirements prior to transmission.

The formal admissibility of the application hinges on the strict use of the PDF/A format as well as the application of a qualified electronic signature recognized under Swiss law. A graphic scale error, improper layer settings, or a missing validation by the consultants immediately halts the upload and triggers a request for additional documents. Full compliance of CAD files ensures adherence to the schedule and a public inquiry process free from technical objections.

Division of review authority: Commune and Cantonal Building Commission

The processing of building permit applications in Valais via the eConstruction platform relies on a clear separation of administrative authority. Projects located within the building zone fall under the decision-making authority of the commune, which rules in accordance with art. 22 LAT and municipal building regulations. As soon as a project involves a zoning variance or is located outside the building zone, art. 24 LAT grants exclusive substantive jurisdiction to the Cantonal Building Commission (CCC). This duality requires the lead consultant to anticipate the cantonal notice procedure. Under the coordination principle set out in art. 25a LAT, the competent authority ensures consistency across sectoral decisions (natural hazards, water protection, heritage conservation), preventing any substantive contradictions when the permit is issued.

Technical requirements on eConstruction: PDF/A formats and qualified signatures

CAD file admissibility on eConstruction requires strict compliance with long-term archiving standards. Standard office formats or hybrid PDF exports generated by 2D/3D modelling software face automatic rejection during upload. Architectural drawings, cross-sections, and elevations must strictly be converted to ISO PDF/A standards (notably PDF/A-1a or PDF/A-2u). This conversion ensures the full embedding of vector fonts, neutral color profiles, and the removal of dynamic scripts or unflattened transparencies.

Regarding the identification of parties, a scanned handwritten signature inserted as a simple image onto the drawing is legally void. The canton of Valais requires a qualified electronic signature (QES) issued by a recognized trust service provider in Switzerland. The author of the plans, specialized civil engineers, and the client must each apply an active individual digital certificate guaranteeing the absolute integrity of the submitted documents.

Comparative table of transmission requirements on eConstruction

Drawing or technical documentRequired file formatType of validationDecision-making authorityGrounds for inadmissibility
Official surveyor's site planCertified vector PDF/AQualified electronic signatureCommune and CCCLack of elevation data tied to federal coordinates
Floor plans, cross-sections, and elevations (1:100)PDF/A-1a or PDF/A-2uQualified electronic signatureCommune (building zone)Unmerged CAD layers or unembedded fonts
Application outside the building zone (art. 24 LAT)Structured multi-page PDF/AQualified signature from lead consultant and clientCantonal Commission (CCC)Lack of justification for the mandatory site location
Safety and fire protection conceptsSearchable text PDF/AValidation by a certified specialistCantonal department / CCCHandwritten reports without searchable text indexing
Waste disposal notice (art. 16 OLED)Validated PDF/A formApplicant's signatureCompetent cantonal departmentOmission of sorting channels above the regulatory threshold

Recurring modelling errors and financial impacts

The most frequent errors on eConstruction stem from poor preparation of digital deliverables. Inserting unoptimized raster images, retaining hidden layers, or failing to flatten vector hatching produces oversized files that fail the platform's integrity checks. Furthermore, discrepancies between graphic dimensions on architectural plans and the geometric data from the official survey trigger an immediate halt during municipal formal verification.

Contractually, reworking a rejected application leads to engineering and architectural overheads in the range of 3'000 CHF to 8'500 CHF for model corrections and certificate re-issuance. When these delays push back the public inquiry by several months, the consultant's liability may be invoked under professional diligence rules set out in art. 364 CO.

Illustrative practical cases (typical scenarios on Swiss construction sites)

The amounts and parameters presented below are illustrative examples constructed for technical analysis and do not represent actual situations.

As part of a project converting a former barn into housing located in the canton of Valais, outside the building zone, joint intervention by the commune and the Cantonal Building Commission was required. The appointed architectural firm, with a team of five employees, had to submit the entire application on eConstruction in accordance with the requirements of art. 24 LAT.

Given the presence of protected heritage elements and the geotechnical constraints of the plot, the chosen technical approach standardized all plans to the PDF/A-2u format with full flattening of 3D modelling layers. The lead consultant coordinated the application of qualified electronic signatures between the property owner, the civil engineer, and the architect using certified certificates. Concurrently, a detailed management note for excavated materials was integrated to meet the requirements of art. 16 OLED and art. 19 OLED.

This rigorous preparation ensured technical admissibility on the cantonal portal on the first submission, thereby preventing an estimated twelve-week procedural delay and rework fee overheads of around 5'200 CHF.

Surfaces, standards and permits: free tools

SIA 416 floor areas and volumes, cantonal zoning ratios, U-values and dew points, acoustics, planning enquiry requirements.

View engineering tools

Frequently asked questions

Which PDF/A profile is required on eConstruction Valais?

Plans require the flattened PDF/A format without dynamic layers. A technical error on a representative 450000 CHF project halts review under art. 22 LAT by the municipal administration.

Is a qualified electronic signature required for all consultants?

Authors of drawings must apply a qualified signature recognized in Switzerland. A benchmark application representing 85000 CHF in fees is rejected by the CCC if a signature is missing from the digital submission.

How is authority divided between the commune and the CCC?

The commune verifies local zoning, then refers the case to the CCC for cantonal coordination, thereby ensuring harmonization under art. 25a LAT on an illustrative 620000 CHF project.

Which waste management evidence must be attached to the application?

The waste disposal form is required from 200 m³ onwards under art. 16 OLED. On a construction site valued at 350000 CHF, the absence of this document suspends review by cantonal departments.

Does a rooftop solar installation require a building permit?

In a building zone, compliant solar panels are exempt from building permits under art. 18a LAT. A simple notification suffices for such installations, representing around 32000 CHF in roofing work.

How should safety regulations be integrated into public inquiry plans?

Earthwork plans indicate the required clearances under art. 71 OTConst. For a typical 580000 CHF project, these graphical details prevent any blockage during review by the commune.