DGP vs DLT vs Site Manager: Division of Civil and Criminal Liabilities (RPH SIA 2026)

Understand the division of civil and criminal liability between DGP, DLT, and site managers under SIA 112 and the Swiss Code of Obligations.

Table of contents
The 3 Major Site Risks
  1. Financial / Margin: Confusion between General Project Management (DGP) and Local Site Supervision (DLT) leading to fee overruns (around 10 to 15 %). In the event of defects, the client may demand remediation or a price reduction under the Code of Obligations (CO), eating into margins if supervision is poorly defined.
  2. Legal / Joint / SUVA: Criminal liability of the site manager or site supervisor arising after an accident. Under art. 229 CP, anyone who intentionally breaches recognized building rules and knowingly endangers life or physical integrity faces a custodial sentence of up to five years or a monetary penalty.
  3. Administrative / Acceptance: Delays in joint inspection and acceptance of the work due to a lack of coordination. Such gridlock postpones the start of limitation periods for the client's defect warranty claims (five years for immovable works against the contractor or architect under art. 371 CO) and freezes the release of retainage guarantees.

Running a construction project in Switzerland requires surgical precision when defining roles. The SIA 112 service model and the regulations on services and fees (RPH SIA 102/103/108:2026) structure these duties. General Project Management (DGP) handles strategic project steering toward the client. In parallel, Local Site Supervision (DLT) provides day-to-day operational management and quality control on site. Facing them, the site manager represents the contractor: planning resources and directing site crews. Any blurred boundary between these entities sparks jurisdictional disputes, especially when construction defects arise.

Understanding how civil liability and criminal liability are divided is an absolute necessity. The Code of Obligations (CO) strictly governs contracts for work and services as well as agency mandates, holding every stakeholder liable for their own acts or a failure of supervision. Regarding safety, the employer must appoint a qualified person on every construction site responsible for occupational health and safety (art. 5 OTConst). If an accident occurs, criminal courts will determine who breached their duty of instruction. This guide details the scope of action for each role to secure your project management processes, right through to clearing defects during acceptance of the work.

Division of roles and contractual obligations under SIA 112

Managing a construction project in Switzerland rests on a strict separation of powers. The SIA 112 service model establishes a clear hierarchy. General Project Management (DGP) acts as the direct representative of the client for overarching strategic and financial decisions.

Local Site Supervision (DLT) oversees operational direction on site. It coordinates the trades, checks that execution complies with specifications, and approves quantity measurements. However, the DLT has no right to interfere with the contractor's internal organization.

The site manager acts on behalf of the appointed contractor. Their role is to schedule resources, lead their crews, and guarantee completion of the works under the contract for work and services defined by art. 363 CO. They safeguard the profitability of their construction site and implement occupational health and safety measures for their workforce.

Comparison table: DGP, DLT, and Site Manager

The table below summarizes the key differences between these three pivotal roles on a Swiss construction site.

Role Contractual relationship Civil liability (CO) Criminal liability (CP) Core responsibilities
General Project Management (DGP) Agency contract (art. 398 CO) with the client Diligent and faithful performance of the mandate, adherence to overall budget Limited, unless gross negligence occurs when selecting stakeholders Strategic steering, client representation, budget and credit approvals.
Local Site Supervision (DLT) Agency contract (art. 398 CO) with the client or the DGP Failure of supervision, incorrect approval of advance payments Triggered if imminent life-threatening hazards are tolerated (art. 229 CP) Spatial coordination, quality control, checking quantities, leading site meetings.
Site manager Employment contract with the contractor (art. 363 CO for the firm) Defective execution, delay (art. 366 CO), material defects Directly incurred in accidents caused by breaching the rules of the art (art. 229 CP) Crew allocation, procurement, meeting completion deadlines, site profitability.
Site foreman (contractor) Employment contract with the contractor Internal to the firm (subordinate to the site manager) Incurred on the ground in cases of conscious endangerment Day-to-day leadership of workers, receiving materials, enforcing site safety.
Safety specialist (MSST) Service mandate or employment contract Flawed advisory work or failure to identify hazards Incurred in case of gross failure to observe protective duties Safety audits, drafting health and safety plans, training workers.

Civil and criminal liability: boundaries and overlaps

Distinguishing between civil liability (remedying financial loss) and criminal liability (penalizing unlawful conduct) is essential. Both the DGP and the DLT are bound to the client under an agency mandate. Under art. 398 CO, an agent's liability is subject to the same rules as that of an employee; the agent is liable to the principal for the diligent and faithful performance of the mandate. If the DLT approves non-compliant works due to a lack of supervision, it incurs civil liability for the resulting loss suffered by the client.

For the contractor, art. 364 CO states that the contractor must perform the work in person or supervise it personally and procure the necessary tools, equipment, and machinery at their own expense. Furthermore, art. 365 CO provides that the contractor is liable for the quality of materials supplied; if materials supplied by the client or the ground designated by the client are defective, the contractor must inform the client immediately or bear the consequences.

Regarding safety, art. 3 OTConst requires work to be planned so that the risk of occupational accidents, occupational illnesses, or adverse health impacts is kept as low as possible. Under art. 4 OTConst, the employer must ensure, before starting operations, that a plan is in place setting out the measures required for the work carried out on the construction site. Art. 5 OTConst obliges the employer to appoint a qualified person on every construction site responsible for occupational health and safety, empowered to issue instructions to workers.

Criminal liability, however, is strictly personal. Art. 229 CP penalizes breaches of the rules of the art of construction: anyone who, when directing or executing construction or demolition work, intentionally breaches recognized building rules and knowingly endangers life or physical integrity faces a custodial sentence of up to five years or a monetary penalty; in cases of negligence, up to three years or a monetary penalty. This provision can apply equally to a site manager ordering a hazardous method and to a DLT supervisor who witnesses an imminent lethal danger without intervening to halt the work.

Common boundary errors and financial consequences

Interference by the DLT in the contractor's execution methods is a common pitfall. If the DLT dictates a specific working method to the site manager, it risks shifting liability for execution from the builder to the project supervisor. Should damage occur, the contractor can cite art. 369 CO, which excludes client warranty rights where defective execution is personally attributable to the client (such as orders issued contrary to express warnings by the contractor). Such interference can trigger unrecoverable additional costs of around 40 000 CHF to remediate a foundation slab.

Under art. 367 CO, upon delivery, the client must examine the condition of the work as soon as feasible and notify the contractor of any defects; for immovable works, the client has 60 days to give notice, and any shorter contractual deadline is void (in force since 1 January 2026). If the DLT fails to formalize these defect notices in time, the client forfeits their warranty rights, triggering the DLT's civil liability.

Finally, negligence in inspecting materials supplied by third parties is another classic trap. The site manager must verify substrates and building supplies without fail. Neglecting the duty to notify under art. 365 CO regarding poor subsoil means the contractor must bear the financial fallout from settlement or structural deterioration, which can easily reach losses of around 25 000 CHF depending on the remedial work required.

Illustrative practical cases (typical scenarios on Swiss construction sites)

The figures and scenarios outlined below are illustrative examples constructed to demonstrate how standards apply, and do not represent actual construction sites.

Scenario 1: Safety dispute on a residential building (Canton of Vaud)

Context: During the structural work phase of an apartment building, the DLT notes a lack of edge protection along a floor slab.

Problem: The site manager claims that fitting fall protection is the responsibility of the scaffolding contractor.

Standard analysis: Art. 17 OTConst provides that measures must be taken at workstations and transit routes so that workers are not endangered. Furthermore, art. 22 OTConst defines peripheral guardrail requirements: a top rail with its upper edge at least 100 cm above the working surface, at least one intermediate rail, a toeboard of at least 15 cm, and a maximum gap of 47 cm between components. These provisions set technical standards without establishing criminal penalties directly.

Resolution and liabilities: The DLT must order an immediate stoppage of work in the unprotected zone. Tolerating this hazard could trigger criminal liability should a fatal fall occur, under art. 229 CP (negligent breach of the rules of the art of construction). The site manager, acting on behalf of the employer, must apply art. 5 OTConst and instruct their workers to vacate the hazard area. The cost of the shutdown (estimated at 3 500 CHF per day) will be borne by the defaulting contractor pursuant to the contract terms.

Scenario 2: Material defect and duty to notify during renovation (Canton of Geneva)

Context: During a renovation project, the client insists on using a batch of floor tiles imported directly by themselves.

Problem: While laying the tiles, the site manager notices substantial variations in thickness that prevent an even, level finish.

Standard analysis: Under art. 365 CO, if materials supplied by the client prove defective, or if any other circumstance jeopardizes regular execution of the work, the contractor must notify the client immediately, under pain of bearing the consequences.

Resolution and liabilities: The site manager must immediately halt tiling work and issue written notice (by registered mail or a formal, countersigned entry in the daily site report) to the DLT and the client. If tiling continues without warning, the firm loses the right to bill for remedial work and must assume civil liability for the aesthetic defect (price reduction or remediation at its own expense, estimated at roughly 12 000 CHF). By serving formal notice, the contractor shifts the risk back to the client. If the DLT still orders the work to proceed, art. 369 CO applies, barring the client from asserting defect rights caused by an order given contrary to the contractor's formal advice.

00:00 - 00:15 AI Avatar: A serious accident or a 100 000 CHF budget overrun on your construction site? Confusing DGP and DLT is extremely costly in Switzerland.

00:15 - 01:10 Screen and Diagrams: Demonstration of the responsibility matrix. Overview of SIA 112 standard phases. Focus on art. 229 CP for criminal liability and art. 367 CO for defect management. Clear division of supervision duties.

01:10 - 01:30 AI Avatar: Master your legal obligations. Use our interactive tool below to generate your role allocation matrix and secure your construction contracts.

Contracts and SIA 118: free tools

Advance payments and retentions, surety bonds, price escalations, daywork reports, subcontractor monitoring.

View the contracts and SIA 118 tools

Frequently asked questions

Does the site manager incur criminal liability in the event of a serious accident?

Yes. Under art. 229 CP, anyone who directs construction work and breaches recognised professional rules, knowingly endangering human life, is liable to prosecution. Through direct on-site supervision, the site manager is particularly exposed to this criminal provision in the event of negligence.

How does SIA standard 112 divide duties between DGP and DLT?

SIA standard 112 sets out a precise scope of services. The General Project Management (DGP) leads the project, handling overall finances and appointed consultants. The Local Site Management (DLT) focuses on technical execution, quality control and day-to-day coordination of contractors directly on the construction site.

Is the site management liable if a quote is exceeded?

Yes, an inaccurate estimate engages the consultant's civil liability under the Code of Obligations (CO). If the overrun stems from negligence in financial monitoring, the client can claim damages. An unjustified discrepancy, such as 50 000 CHF, represents a major financial risk.

Can the client delegate occupational health and safety to the DLT?

Art. 3 OTConst requires work to be planned to minimise risks. The DLT coordinates shared measures, but each employer remains responsible for their own workers. Each employer must designate a competent person on the construction site, pursuant to art. 5 OTConst, to ensure daily safety.

What is the deadline for notifying a defect under the revised law?

Since 1 January 2026, art. 367 CO gives the client a 60-day period to notify defects in an immovable work. SIA standard 118 provides for a warranty period during which defects may be reported at any time, simplifying the procedure.

Must the DLT check the working conditions of hired subcontractors?

Absolutely. The Posted Workers Act (LDét) imposes a duty of due diligence. The main contractor is jointly and severally liable for non-compliance with minimum wages (art. 5 LDét). The DLT controls site access and verifies certificates to avoid financial penalties or costly work stoppages on the construction site.

Summary of responsibilities

Distinguishing between General Project Management, Local Site Management and the site manager is critical for project compliance in Switzerland. The requirements of SIA standard 112 and the Code of Obligations (CO) demand absolute rigor. Unclear allocation exposes managers to civil liability and criminal risks. Structure your mandates using our interactive matrix.