Representation of the Client by Site Management: Financial and Legal Limits (SIA 118)

What are the representation powers of site management under SIA 118 and the CO? An analysis of financial and legal limits.

Table of contents
The 3 Major Site Risks
  1. Financial / Margin: Approving addenda or daywork without written power of attorney from the client risks cost overruns of around 5 % to 12 % that will not be covered. In case of an abuse of authority, art. 32 CO and art. 398 CO hold the site management liable for compensating the resulting financial loss under art. 97 CO.
  2. Legal / Joint / SUVA: Unlawful interference with the contractor's execution methods or dangerous site instructions. If a breach of the recognised rules of construction intentionally or negligently endangers the life or physical integrity of individuals, art. 229 CP provides for a custodial sentence or a monetary penalty.
  3. Administrative / Acceptance: Unlawful signing of inspection records or acknowledging cost increases without explicit delegation. Under standard SIA 118, this leads to the client refusing ratification, thereby stalling the closing of the final account and compliance procedures with the local municipality.

On a Swiss construction site governed by standard SIA 118, site management coordinates the execution of the works and monitors compliance with the plans. However, ambiguity remains regarding its powers of legal representation toward contractors. While site management conveys technical instructions for the project, it does not automatically possess the authority to alter agreed prices or contractual terms. Under art. 32 CO, acts executed on behalf of the client bind the client only if site management holds the required authority, which restricts any unagreed financial initiative.

For site management teams, construction managers and clients in French-speaking Switzerland, distinguishing technical direction from legal representation is vital to prevent disputes over fees and addenda. Under the mandate contract (art. 398 CO), the agent is liable for the proper and faithful execution of their assignment. This article examines the boundaries of site management interventions under standard SIA 118, power of attorney mechanisms, and the traceability rules essential for safeguarding site financial administration.

Scope and limits of site management powers under Swiss law

The contractual relationship between the client and the site management is governed by the mandate under art. 398 CO. The agent is bound to act with fidelity and diligence in the principal's best interest. Conversely, the scope of their external representation authority with contractors is ruled by art. 32 CO. On a construction site governed by standard SIA 118, site management provides technical direction and quality control of the works. It issues execution instructions, coordinates trade packages, and checks quantities, without this conferring general financial authority.

This operational competence does not allow altering the contractual framework of the project. Entering into a contract for work and services under art. 363 CO or waiving legal rights remains the exclusive prerogative of the client. Pursuant to art. 32 CO, acts carried out by the site management bind the client only if the client granted the corresponding authority. Should the site management make financial commitments exceeding its brief, the client can refuse to ratify them. The agent may then be held liable under art. 97 CO for the damage caused by a breach of its duty of diligence.

Technical Scope of Action versus Financial Commitments

Swiss practice requires a clear distinction between technical supervision and economic decisions. Site management is empowered to monitor compliance with execution drawings, record the progress of construction phases, and record facts in site minutes. It possesses the authority needed to reject non-compliant supplies or demand the rectification of defective work in accordance with the recognised rules of construction.

On the other hand, any decision that alters the financial balance of the contract requires a written power of attorney from the client. This covers change orders for modified works, the use of daywork, or agreeing on additional unit prices. Although art. 1 CO and art. 6 CO allow for the tacit formation of contracts under certain conditions, the contractor cannot presume the financial authority of the site management without an explicit clause. Standard SIA 118 establishes a framework for managing site orders, but never exempts the parties from complying with the statutory limits of mandate law.

Competency table: authorised actions and actions requiring written power of attorney

To prevent financial disputes, site authorities are allocated according to the following matrix:

Nature of the act on the construction site Role of the site management Client written approval required Legal or standard basis
Issuing drawings and execution instructions Direct execution authority Not required if aligned with original design art. 398 CO and standard SIA 118
Joint inspections and quantity measurements Establishing technical facts Not required for technical measurement art. 398 CO and standard SIA 118
Change orders and cost increases Investigation and preliminary technical assessment Mandatory prior to ordering art. 32 CO and art. 363 CO
Signing daywork sheets and new prices Verification of hours and materials Required for financial commitment art. 32 CO and art. 374 CO
Formal notice for delay or anticipated defect Notification and setting a deadline Recommended depending on financial impact art. 366 CO and standard SIA 118
Joint inspection and acceptance of the work Leading the joint inspection Required for the acceptance report art. 367 CO and art. 370 CO

Common governance mistakes and financial impacts on construction sites

A classic mistake is equating the signing of a daywork sheet with approval for payment. The site foreman submits daily reports to the site management, which initials them without reservation. The contractor interprets this as financial approval, whereas the client challenges the necessity of the works. On a structural work or building services package, a dispute over unapproved daywork typically generates claims in the range of 30 000 CHF to 75 000 CHF.

A second pitfall involves lump-sum price contracts governed by art. 373 CO. When site management accepts minor changes on site without a formal addendum, the contractor subsequently claims a cost increase. Under art. 373 CO, the lump sum is binding on the contractor, except in extraordinary circumstances. If the site management creates an expectation of compensation without its principal's consent, the client can refuse payment under art. 32 CO. The contractor will then turn against the site management, or the client will invoke its liability for breach of mandate under art. 398 CO and art. 97 CO.

Lastly, mishandling the duty to notify set out in art. 365 CO para. 3 creates major risks. If the contractor verbally alerts site management to a ground or design issue, but site management fails to convey this formal notice to the client, the client's legal position is compromised. In the event of subsequent damage, site management can be held liable for lack of diligence.

Illustrative practical cases (typical scenarios on Swiss construction sites)

The following situations are illustrative examples designed to analyse contractual and financial mechanisms on Swiss construction sites and do not correspond to any actual site.

Typical Scenario 1: In the canton of Vaud, during the construction of a multi-family housing development involving 18 workers for the structural work, unforeseen water ingress requires pumping and trench shoring not included in the original quote. Site management gives a verbal order to carry out the work for an amount of around 60 000 CHF. When the monthly payment application is presented, the client refuses to pay the bill, citing the absence of financial authority under art. 32 CO. The contractor proves the measures were essential under art. 365 CO. Final dispute resolution leads the client to pay for the work required for the structural stability of the building, but the site management's fees are subjected to a deduction under art. 97 CO and art. 398 CO for failure to provide prior notice.

Typical Scenario 2: In the canton of Geneva, during the refurbishment of an administrative building with 12 workers handling finishing work, schedule delays threaten the delivery deadline. To mitigate these overruns, site management considers ordering overtime work from the plastering and painting contractor. The contractor notes that the contract was executed at a lump-sum price within the meaning of art. 373 CO and values the cost impact at around 35 000 CHF. Instead of signing independently, site management draws up a reasoned report based on art. 366 CO and submits a draft addendum to the client. The client approves the commitment in writing before any work begins. This procedure protects all parties and ensures complete legal compliance throughout the process.

Contracts and SIA 118: free tools

Advance payments and retentions, surety bonds, price escalations, daywork reports, subcontractor monitoring.

View the contracts and SIA 118 tools

Frequently asked questions

Can site management sign a financial addendum without written power of attorney?

No. Under art. 32 CO and standard SIA 118, the financial representation powers of site management are strictly limited to the agreed mandate. Without a special written power of attorney from the client, ordering an additional service amounting to around 15 000 CHF does not validly bind the client.

What liability does site management incur if it exceeds its powers?

Site management is liable for improper performance under art. 398 CO, which governs mandates. If it approves change orders without authority, resulting in an unexpected cost overrun of around 25 000 CHF, it triggers its professional civil liability and can be required to make good the damage.

Can the contractor rely on verbal change orders given on the construction site?

No, the contractor faces the risk of non-payment. In accordance with standard SIA 118, any change order must be agreed in writing beforehand. Executing work that has not been approved by the client, for an amount of around 10 000 CHF, shifts the financial risk entirely to the contractor.

Which technical acts can site management perform as of right?

Subject to contractual clauses, site management performs technical supervision, checks material compliance, keeps site minutes, and carries out joint measurements. It may also order urgent safety measures to avoid immediate property damage of around a few thousand CHF.

What criminal liability can site management face in the event of a site accident?

If site management intentionally or negligently breaches fundamental construction standards and knowingly endangers the life or physical integrity of others, it falls under art. 229 CP, which penalises breaches of the recognised rules of construction.

How can the client ratify a change order that exceeded authority?

Under art. 32 CO and art. 1 CO, the client may expressly or tacitly ratify an act performed beyond the powers granted. Without formal ratification, the financial commitment, such as an unexpected daywork slip of around 8 000 CHF, cannot be enforced against the client and remains the liability of site management.

Defining representation powers clearly by contract protects every party on a Swiss construction project against financial and operational disputes. To delve deeper into construction site governance, explore our specialised guides: