Dimensioning the Site Layout Plan (PIC): Cranes, LTr Accommodation and ESTI Connections

Dimensioning the site layout plan in Switzerland: tower crane location, site accommodation under OLT 3 and temporary ESTI electrical connections.

Table of contents
The 3 Major Site Risks
  1. Financial / Profit margin: Underestimating connected electrical power or choosing an unsuitable crane foundation leads to unplanned adaptation costs, ranging from 15 000 CHF to more than 45 000 CHF for adding a generator or underpinning the foundation slab, with no possibility of passing these costs on to the client pursuant to art. 364 CO.
  2. Legal / Joint body / SUVA: Non-compliance with OLT 3 hygiene requirements for mess rooms or failing to notify an electrical installation to the Federal Inspectorate for Heavy Current Installations (ESTI) can prompt a work stoppage by the cantonal labour inspectorate or SUVA, triggering liability for endangerment under art. 229 CP.
  3. Administrative / Handover: Failure to formalise the health and safety plan required by art. 4 OTConst or unauthorised crane slewing over adjacent land halts the granting of municipal permits for public land use, delaying the actual start of work.

The rigorous dimensioning of the site layout plan (PIC) is the cornerstone of technical, safety, and logistical management for any construction project in Switzerland. Intended for site management, project managers and civil engineers, this document maps out work zones, plant traffic routes, tower crane locations, and the layout of welfare facilities. Pursuant to art. 3 OTConst, planning construction work requires anticipating all installations so that the risk of occupational accidents, occupational illnesses, or damage to health is kept as low as possible, taking into account topography, neighbouring properties, and access to local utility networks.

Setting up welfare facilities for staff requires strict compliance with art. 6 LTr and the provisions of OLT 3, which set out requirements for changing rooms, heated mess rooms, and sanitary facilities based on the peak number of workers present simultaneously. At the same time, temporary power supply demands strict adherence to ESTI directives to prevent electric arcing and equipment overloads, while crane positioning remains subject to the Crane Ordinance as well as the geotechnical calculations required to guarantee the stability of crane tracks or outrigger pads.

Tower crane positioning and dimensioning: kinematics and geotechnics

Selecting the location of a tower crane on a site layout plan involves balancing technical trade-offs between oversailing constraints, ground bearing capacity, and access to storage areas. The Crane Ordinance lays down strict rules regarding the erection, maintenance, and operation of this lifting equipment. When drawing up the layout plan, site management must verify clearances between the jib radii and nearby obstacles, particularly overhead power lines and adjacent plots. Under art. 364 CO, the contractor procures the necessary resources, plant, and tools at its own expense, which includes anti-collision systems when multiple cranes operate simultaneously.

From a geotechnical standpoint, crane foundations require rigorous verification of support stability. When a crane is set up near an excavation, art. 77 OTConst requires trench shoring and sheeting to withstand all foreseeable loads and forces, taking into account supplementary surcharges such as construction machinery and stored materials. If the excavation involves unsupported battered slopes, the ground stability provisions must prevent any ground collapse that could destabilise the crane foundations.

Footing stability and slewing zones

The maximum ground pressure exerted under in-service and out-of-service conditions determines whether to use a reinforced concrete raft foundation, isolated footings tied with ground beams, or a ballasted chassis on a compacted gravel bed. The civil engineer responsible for the temporary works must calculate permissible differential settlements. At work stations and on traffic paths under the jib, art. 17 OTConst requires taking measures to ensure workers are not endangered by falling objects or materials. In addition, art. 6 OTConst mandates the wearing of safety helmets near cranes, supplemented by the high-visibility warning clothing specified in art. 7 OTConst.

Site accommodation and welfare facilities under the Labour Act and OLT 3

Setting up the site compound is not a mere logistical convenience, but a mandatory health protection requirement under art. 6 LTr. Employers must take all necessary measures to protect the personal integrity of their workers. OLT 3 details the hygiene and health requirements applicable to rest areas, changing rooms, mess rooms, and construction site sanitary installations. Art. 18 OLT 3 addresses air pollution, stressing the need for adequate air renewal inside modular cabins, while art. 22 OLT 3 covers noise and vibration, which must be avoided or mitigated using appropriate measures.

Modular cabins must be dimensioned in proportion to the foreseeable peak workforce on the construction site. Mess rooms must provide seating with washable tables, drinking water, refrigerators, and food-heating equipment, allowing breaks to be taken in accordance with the durations set out in art. 15 LTr. Changing rooms must be ventilated, heated in winter, and fitted with individual lockable lockers to separate street clothes from soiled workwear. Regarding sanitary facilities, the ratio standard in Switzerland requires at least one toilet and one urinal per fifteen workers, alongside washbasins with soap and single-use towels.

Temporary electrical connections and safety under ESTI rules

Powering a construction site requires early coordination with the local distribution network operator and a licensed electrical contractor. Prescriptions issued by the ESTI (Federal Inspectorate for Heavy Current Installations) govern temporary site distribution boards, power cable selection, and personal protection against direct or indirect contact. Art. 3 OPA stipulates that employers must take all safety arrangements and protective measures complying with recognised technical safety rules.

The main site distribution board must feature clearly identifiable, easily accessible emergency stop controls. Each outgoing circuit feeding socket-outlets must be protected by high-sensitivity residual current devices (RCDs). Supply cables running across vehicle tracks must be routed through heavy-duty cable trenches or drive-over cable protector ramps to prevent mechanical crushing or severing by delivery lorries and earthmoving machinery.

Comparative table of technical PIC parameters

PIC componentApplicable Swiss standard / ruleDimensioning criteriaOperating requirementMain risk to manage
Static tower craneCrane Ordinance, art. 77 OTConstPermissible ground bearing capacity, max reach, oversailing clearanceGeotechnical verification of subgrade, out-of-service weathervaningPlant overturning, jib collision, overloading
Mess room and rest areaLTr art. 6 and art. 15, OLT 3Peak workforce count, minimum seated surface areaDaily cleaning, heating, compliant ventilationUnsanitary conditions, joint-body non-compliance, disputes
Changing rooms and toiletsOLT 3, art. 18 OLT 3Sanitary ratios, clean/dirty separation, ventilationIndividual lockers, hot water, disinfectionDisease transmission, stagnant humidity
Electrical distribution boardESTI prescriptions, art. 3 OPATotal active power, differential selectivityPeriodic inspection, fire brigade and maintenance accessElectric shock, fire outbreak, nuisance tripping
Access routes and waste sortingArt. 7 OTConst, OLED art. 17Lorry turning circles, labeled skips footprintSeparation of pedestrian and vehicle traffic, levelled groundPedestrian-plant collision, mixing of mineral waste

Recurring planning errors and financial impacts

The first common mistake lies in under-sizing the connected electrical capacity. When a contractor sets up a high-powered crane combined with pan mixers or screed pumps without properly coordinating peak demand, nuisance tripping of the main breaker paralyses activity. Bringing in an unplanned backup generator costs roughly 6 000 CHF to 14 000 CHF per month in hire fees and fuel, an expense that remains entirely with the contractor pursuant to art. 364 CO.

The second pitfall involves welfare facilities that fall short of cantonal labour inspectorate requirements. Providing fewer cabins than the actual workforce demands or lacking proper ventilation can lead to an order to deliver additional modular units under complex access conditions, triggering crane rental costs of 4 000 CHF to 9 000 CHF. Finally, neglecting site run-off management and omitting a settlement basin or grit separator at site exits exposes the site to discharge bans issued by the water police, triggering contractual penalties for execution delays.

Illustrative practical cases (typical scenarios on Swiss construction sites)

The scenarios described below are illustrative examples created for educational purposes to guide practitioners, and do not relate to actual construction sites.

Standard Scenario 1: Residential building in the Canton of Vaud

On a 24-unit new-build residential project in Nyon, the initial site layout plan called for a tower crane with a 45-metre jib positioned right next to a 4.20-metre deep excavation. In accordance with art. 76 OTConst, site management requested structural wall calculations prepared by a geotechnical engineer, as the depth exceeded 4 metres. Given the risks of ground failure beneath the crane footing, the solution involved moving the crane back by 3 metres and constructing a soldier pile wall tied back with temporary ground anchors dimensioned under art. 77 OTConst. The site compound accommodated 28 workers during peak structural work: three linked cabins for the mess room and two for toilets and showers were erected, ensuring compliance with art. 15 LTr for breaks and the requirements of OLT 3.

Standard Scenario 2: Refurbishment in dense urban fabric in the Canton of Geneva

In Carouge, adding storeys to an office building while keeping parts of it operational severely restricted available ground footprint. As the tower crane could not encroach on public highway land, it was anchored directly onto a reinforced concrete foundation integrated into the building's future foundations. Coordinating the 80 kVA power supply with the Geneva municipal utilities allowed the contractor to install a main site distribution board compliant with ESTI requirements right from site start. Changing rooms and rest areas were stacked on the first floor above the waste sorting area organised pursuant to art. 17 OLED, while rigid hoardings ensured strict separation between pedestrians and machinery in compliance with art. 17 OTConst.

Contracts and SIA 118: free tools

Advance payments and retentions, surety bonds, price escalations, daywork reports, subcontractor monitoring.

View the contracts and SIA 118 tools

Frequently asked questions

Who bears the financial cost of temporary connections under standard SIA 118?

Unless agreed otherwise, the contractor provides its working resources under art. 364 CO. The works contract defines how costs for the ESTI site power board are split. Energy consumed is tracked by a sub-meter, typically amounting to roughly 4 500 CHF for standard structural work.

Which document governs placing a crane along an adjacent plot boundary?

Oversailing a neighbouring plot requires a building lease agreement or written consent from the neighbouring owner. Under the Crane Ordinance and SUVA directives, the site management must record slewing restriction zones in the installation plan, preventing any endangerment within the meaning of art. 229 CP.

What minimum comfort requirements apply to site welfare facilities?

Under art. 6 LTr and the provisions of OLT 3, the employer must provide heated, ventilated rooms equipped with drinking water. The mess room must offer seating space and facilities to heat meals. Fit-out for ten workers represents an indicative monthly investment of around 1 200 CHF.

How should the installation plan be coordinated with occupational health and safety requirements?

Work planning must reduce risks to the lowest possible level in accordance with art. 3 OTConst. Before operations start, the employer draws up the written plan required by art. 4 OTConst, detailing traffic routes, the location of emergency facilities and material storage areas.

What electrical checks does ESTI require before commissioning the site distribution board?

The licensed electrical installer draws up an official safety report certifying the compliance of residual current devices and equipotential bonding. This inspection prevents electrical accidents. The initial inspection cost by an accredited body is typically around an illustrative 450 CHF.

What action should be taken if the crane bearing ground shows instability?

The contractor informs the client pursuant to art. 365 CO if ground conditions jeopardise the proper performance of the work. A geotechnical calculation note certifies the bearing capacity of the concrete crane base. Rebuilding the platform incurs an illustrative technical additional cost estimated at 8 500 CHF.

Mastering the site installation plan ensures operational profitability and health protection on Swiss construction sites. To explore site preparation protocols, risk management and the applicable legal framework in more depth, see our technical guides: