Table of contents
The 3 Major Site Risks
- Financial / Margin: Occurrence of tacit acceptance depriving the client of retention money and discharging the contractor from its initial obligations, with residual remediation costs that can represent an illustrative benchmark of 5 to 15% of the contract sum according to standard SIA 118.
- Legal / Joint Body / SUVA: Forfeiture of statutory rights regarding apparent defects not notified in time under art. 370 CO, as well as the risk of criminal proceedings under art. 229 CP in the event of deliberate disregard of recognised building standards endangering life or limb when handing over an unsafe structure.
- Administrative / Acceptance: Blocking of bank security releases and postponement of the occupancy permit issued by the municipality in the absence of a formal joint inspection record drawn up within the one-month period prescribed by standard SIA 118.
On Swiss construction sites governed by recognised building standards, the contractual close-out of works is a pivotal stage for site management and the client. The contractor's submission of the notice of completion formally triggers a procedural countdown governed by standard SIA 118. Upon receipt of this written notice, the parties have a period of one month to carry out a joint inspection of the completed works. This joint inspection record aims to document site conditions in detail, classify any non-conformities, and formalise express acceptance of the delivered services. Neglecting this schedule exposes the project to automatic acceptance of the works without prior verification.
Inaction by site management during this allotted period entails major legal consequences governed by standard SIA 118 and the Code of Obligations (CO). When no joint inspection is undertaken within the month following notification, the works are deemed tacitly accepted, thereby immediately transferring risks to the client. This detrimental outcome deprives the client of contractual leverage and discharges the contractor from warranty obligations for discernible defects, in accordance with the principle set out in art. 370 CO. This guide outlines the operational steps, deadline calculations, and traceability protocols required to secure acceptance and preserve the client's rights.
Mechanism of the notice of completion and counting the one-month period
In Swiss contracting practice governed by standard SIA 118, the notice of completion is the unilateral act by which the contractor formally notifies site management that its works are ready for joint inspection. Under art. 367 CO, the client inspects the state of the works after delivery. Upon notification of this notice, a one-month deadline begins to run. During this period, site management and the contractor must organise and conduct the joint inspection. The timing is critical: if the client or its representative allows this month to elapse without inspecting the premises or stating a reasoned refusal, the legal fiction of tacit acceptance takes effect.
From a contractual standpoint, this period is not merely a scheduling recommendation. It is an agreed deadline designed to secure mutual commitments. Failing to respond within this timeframe exposes the client to de facto acceptance of the completed works, reversing the burden of proof and triggering the start of the five-year limitation period under art. 371 CO applicable to immovable construction works. Consequently, keeping an acceptance log and scheduling a joint inspection date within ten days of the notice represents an elementary requirement of good practice for site management.
Tacit acceptance: application criteria and legal consequences
Tacit acceptance occurs primarily in two distinct forms provided for by standard SIA 118: inaction by the client following the notice of completion upon expiry of the one-month period, or actual taking of possession of the premises without reservations. When occupants move in or commercial spaces are operated prior to any joint inspection record, this use constitutes acceptance of the delivered works, subject to contrary stipulations agreed in writing beforehand.
Acceptance, whether express or tacit, leads to major consequences set out in art. 370 CO: the contractor is released from liability for all defects that could have been identified during a standard inspection. Only hidden defects, impossible to uncover during a diligent examination, remain covered by the defect notification period. Regarding payment, art. 372 CO stipulates that the contract price becomes payable upon delivery of the works, giving the contractor the right to claim settlement of its balance, minus the agreed retention. Furthermore, the occurrence of tacit acceptance eliminates the possibility of claiming a contractual penalty for delay under art. 160 CO if this right was not formally reserved at the time of taking possession.
Comparative table of acceptance procedures
The following table compares the different situations encountered during the completion of a works contract governed by standard SIA 118 and the Code of Obligations (CO):
| Close-out procedure | Formal trigger | Status of apparent defects | Due date of balance (art. 372 CO) | Limitation period start (art. 371 CO) |
|---|---|---|---|---|
| Express acceptance without reservations | Signed joint inspection record without list of defects | Full discharge of the contractor under art. 370 CO | Payable subject to deduction of retention money | Date of signing the record |
| Express acceptance with reservations | Joint inspection record listing minor rectifications | Warranty maintained for points specified in the record | Payable with targeted retention on items to complete | Date of the initial joint inspection |
| Tacit acceptance by expiry of the period | Client silence for one month following completion notice | Presumption of acceptance of the works as is | Payable at the end of the one-month period | Expiry of the month following the completion notice |
| Tacit acceptance by putting into use | Occupants move in or use of the premises begins | Acceptance deemed granted for elements in use | Payable upon taking possession of the premises | Date of actual taking of possession |
| Reasoned refusal of acceptance | Letter from site management notifying a major defect | No discharge; works remain under contractor custody | Not payable; remains in work-in-progress status | Deferred until the new formal inspection |
Recurring supervision errors and financial impacts
On Swiss construction sites, the most widespread mistake is treating the partial completion of a trade as tacit authorisation for occupancy without drawing up an interim inspection record. For example, allowing a flooring installer to work on a screed without formally checking levelness and residual moisture content transfers the risk of future debonding onto the client, resulting in a dispute where remediation costs may range from 25 000 CHF to 50 000 CHF for an average-sized area.
A second critical error lies in failing to respond in writing upon receiving a notice of completion sent by a contractor when the works display visible non-conformities. If site management fails to formally notify its refusal to proceed within the one-month period, the trap of tacit acceptance closes. The client then loses the benefit of the provisions of art. 368 CO regarding apparent defects not notified on time. Regarding safety coordination under art. 3 OTConst, planning the completion of operations also requires ensuring that access routes remain secure until workers have vacated completely; negligence regarding temporary guardrails during this handover phase engages the liability of site management.
Illustrative practical cases (typical scenarios on Swiss construction sites)
The figures and situations presented below are illustrative examples designed to analyse the decision-making mechanisms of standard SIA 118 and Swiss law.
Scenario 1: Refurbishment of an office building in the canton of Vaud
In a commercial office complex in the canton of Vaud, a finishing work contract for demountable partitions and suspended ceilings was concluded for 380 000 CHF excluding VAT (8,1% rate). The general contractor subcontracted execution to a specialist firm fielding an average workforce of six installers. On 15 September, the company sent its notice of completion by registered mail.
Preoccupied with technical building services testing, site management neglected to arrange an on-site visit. On 20 October, beyond the one-month deadline, it sent a letter listing misalignments and irregular recessed joints, demanding remediation. The contractor invoked tacit acceptance. Legally, silence kept for more than thirty days following valid notification operated tacit acceptance of the works. As the defects in question were aesthetic and fully apparent, the client was barred from demanding cost-free rectification under art. 370 CO. The dispute ended in a negotiated settlement where the client had to absorb around 18 000 CHF for third-party remedial works, an expense that could not be deducted from the initial contractor's final account.
Scenario 2: Multi-family housing construction in the canton of Valais
On a construction site of fourteen residential units in Valais, the external joinery firm (contract value 220 000 CHF) submitted its notice of completion on 2 May. The local site management convened the tradesperson for a joint inspection on 14 May, scrupulously adhering to the statutory timeframe.
During the joint walkthrough, two apartment entrance doors showed deficient acoustic seals and several window frames exhibited noticeable air infiltration around the perimeter. Site management drew up a detailed record classifying these issues as substantial non-conformities. It expressly refused overall acceptance of the trade package, while setting a reasonable deadline of twenty working days to rectify adjustments and weatherstripping in accordance with art. 366 para. 2 CO. Thanks to this formal step taken within the one-month period, tacit acceptance was successfully averted. The contractor assigned two technicians for three days to rectify the defects at no extra cost to the client, thereby safeguarding the quality of the thermal envelope prior to final key handover to buyers.
Contracts and SIA 118: free tools
Advance payments and retentions, surety bonds, price escalations, daywork reports, subcontractor monitoring.
Frequently asked questions
What risk does site management face by remaining silent after the notice of completion?
Standard SIA 118 requires an inspection within one month of the contractor's notice. Without formal action within this period, the works are deemed tacitly accepted. This acceptance releases the contractor from liability for apparent defects and triggers the limitation period under art. 371 CO, exposing the agent to liability.
Does a minor defect allow refusal of acceptance under standard SIA 118?
No, a minor defect does not prevent acceptance. The work is accepted with an obligation to rectify. For remediation estimated, for example, at 4 500 CHF, the client retains an equivalent amount while formalising acceptance, opening the exercise of the rights set out in art. 368 CO.
How does the notice of defects deadline under the Code of Obligations (CO) align with SIA 118?
For immovable works, art. 367 CO imposes a 60-day period to report defects after delivery. When SIA 118 is incorporated into the contract for work, its contractual warranty regime applies, subject to the mandatory provisions of art. 368 CO safeguarding the right to rectification.
Does taking possession of the premises by the client constitute tacit acceptance?
Early occupancy without clear reservations can be construed as acceptance under SIA 118 and art. 370 CO. Site management must draw up a written record stating that moving in does not constitute final acceptance, thereby preserving the client's rights against the trades.
What is the financial impact of acceptance on the price of the work?
Under art. 372 CO, the price of the work falls due upon delivery. Acceptance triggers the final account, the release of retention money subject to security bonds, and starts the clock on the statutory mortgage lien registration period under art. 839 CC for any unpaid balance.
What should be done if the contractor refuses to sign the joint inspection report?
A refusal to sign does not invalidate the findings. Site management serves the report by registered mail with acknowledgement of receipt. This mailing proves that the joint inspection took place and formally serves the list of defects, eliminating any risk of tacit acceptance under SIA 118.
Mastering the post-completion timeline provides an essential legal safeguard against the unintended acceptance of non-compliant work. To explore operational and contractual procedures on the Swiss construction site in greater detail, consult our dedicated guides:
- Acceptance of the Work, Defect Classification, and Commissioning (SIA Phases 52 & 53 / SIA 118)
- Minor vs Major Defects Preventing Handover (SIA 118): Criteria and Federal Supreme Court Case Law
- The Client's 3 Remedies for Defects (SIA 118 / CO 2026): Repair, Price Reduction or Termination
- SIA Phase 52 (Commissioning): Building Services Functional Testing, Hydronic Balancing and Handover
