Lump-Sum Variations Without an Agreed Price: Courts Apply Market Rates (ATF 143 III 545)
· 8 min read
Financial stakes Variations under a structural works lump-sum contract: seven items remitted to the Commercial Court (nos. 5, 8, 9, 11, 15, 16, and 22). The amounts are not specified in the published extract.
Legal basis ATF 143 III 545 (2017); Art. 373(1) and (2) and Art. 374 CO (Swiss Code of Obligations); Art. 84, Art. 58(2), Art. 62, and Art. 89 of standard SIA (Swiss Society of Engineers and Architects) 118, as cited by the Federal Supreme Court.
Fatal error Executing additional works without an agreed price or a daywork order, then claiming payment without the factual elements required to establish a market price.
Immediate countermeasure Agree on the price before execution; failing that, set out in writing the prevailing price applied and document the variation order.
1. The facts: a lump sum, variations, no price agreement
A consortium of two contractors executed the structural works of a building for a client company. The contract was based on a lump-sum price and incorporated standard SIA 118. Once works were completed, the contractors claimed additional amounts: partly for variation orders instructed by the client, and partly for special conditions attributable to the client. Prior to execution, neither party had determined the price for these variations, and the client had not instructed them as daywork.
The Commercial Court of the Canton of Zurich dismissed the claims not acknowledged by the opposing party. In its view, standard SIA 118 contained a gap on this point: by analogy with Art. 374 CO, the price had to be calculated on the actual effort expended. However, the contractors had not provided sufficient details regarding this effort: relevant pleadings were missing.
The contractors appealed. The Federal Supreme Court partially allowed the appeal, set aside the judgment regarding seven variation items (nos. 5, 8, 9, 11, 15, 16, and 22), and remitted the case.
2. What Swiss law states
The CO: firm lump sum, except under extraordinary circumstances
Where the price is fixed in advance, the contractor must complete the work for that exact amount (Art. 373(1) CO). The court may only grant a price increase, or termination, if extraordinary, unforeseen circumstances prevent completion or make it excessively difficult (Art. 373(2) CO). Where the price is not fixed in advance or is fixed only approximately, it is determined according to the value of the work and the contractor's expenses (Art. 374 CO).
Standard SIA 118: a supplementary price to be agreed
The standard gives the client a unilateral right to order variations (Art. 84) and provides, for an overall or lump-sum price, a supplementary price to be agreed, based on the cost base prevailing at the time of the variation (Art. 89). It does not expressly state what happens if the parties fail to agree.
The ruling of the Federal Supreme Court
The court refused to find a contractual gap. If the supplementary price were only governed by mutual agreement, the contractor could block the variation by stalling negotiations, or would be forced to execute works without knowing how they would be paid. The judge therefore sets the price by applying Art. 89 by analogy.
- The lump sum remains in place; a supplementary price is added (or deducted).
- Calculation basis: prevailing market prices at the time of the variation (unless agreed otherwise), because the "cost base" under the standard is objective, independent of the individual contractor's cost structure. It is not an automatic continuation of tender unit rates.
- Tender documents serve as evidence: the client selected this contractor, which suggests competitive pricing, especially following a competitive tender. Discounts granted during negotiations must be deducted, for instance as a percentage.
- No retrospective daywork accounting: daywork requires a prior order so that the contractor records its hours. Without an order, it is too late to document this.
- No single "correct" price: the court exercises discretion, with "restraint", and weighs all pricing factors submitted by the parties.
3. The real cost of this mistake
| Item | What the ruling states |
|---|---|
| Positions in dispute | Seven variations remitted (nos. 5, 8, 9, 11, 15, 16, 22); amounts not published in the extract |
| Ground for cantonal dismissal | Insufficient pleadings regarding actual effort; the claim was rejected for lack of detail |
| Basis set by the Federal Supreme Court | Prevailing market prices at the date of the variation order |
| Competitive tender discounts | To be deducted from tender prices when used as evidentiary guidance |
| Next steps in the case | Remittal to the Commercial Court: determine whether remunerable variations actually exist, then establish prices |
Illustration, outside the ruling: if a tender item is listed at CHF 100 after a 5% negotiated discount, the market indicator to apply is CHF 95, not the original list price.
For an SME, the cost is twofold: the time required to submit new pleadings, and the risk of seeing part of the variations dismissed if it fails to prove either the variation itself or the prevailing price.
4. Site protocol: four immediate actions
- Price before executing. Conclude a written variation agreement, signed before starting the additional works, with a supplementary price based on current market rates. If urgent, require a written daywork order: without it, daywork will not serve as a calculation basis retroactively.
- Do not rely on protracted negotiations. The Federal Supreme Court rejected an interpretation that would allow the contractor to neutralise the client's right to order variations by dragging out price discussions: failing agreement, the court sets the price. Focus instead on preparing evidence of prevailing market rates.
- Retain all pricing documentation: detailed tender, cost breakdowns, granted discounts, price lists, and comparative third-party quotations as of the variation date.
- Plead each variation individually, specifying its description, the date of instruction, and its prevailing price. The Federal Supreme Court requires pleadings that allow the judge to determine the price; a lump-sum final invoice does not satisfy this requirement.
A price benchmark and a variation template. The Indice ACIP provides a rate schedule by trade (CFC) and by French-speaking canton, with daywork hourly rates and regional coefficients: an independent benchmark to substantiate a price. The calculateur d'avenant generates a variation agreement template for quantity changes, and the guide direction financière : métrés, régie, avenants sets out site management practice in detail.
5. Frequently asked practical questions about this case
What happens if the client orders additional works without discussing price?
The ruling concerns a lump sum governed by standard SIA 118: in the absence of an agreement, the judge determines the supplementary price by applying Art. 89 of the standard by analogy, based on prevailing market rates at the time of the variation. The best practice remains agreeing on the price in writing prior to execution.
Can the variation be billed retrospectively as daywork?
Not as the basis for calculation. The Federal Supreme Court noted that daywork requires a prior order so the contractor can record and substantiate hours. Without such an order, it is too late: billing based on actual effort does not serve as a reference; prevailing market prices are what matters.
Does my tender offer prove the market price?
It can serve as evidence: the client selected this contractor, suggesting competitive pricing, especially following a competitive tender. Discounts granted during negotiations must be deducted, for example as a percentage. It is only indicative evidence, not a mandatory rule for identical pricing.
Official sources
- ATF 143 III 545 (judgment of the First Civil Law Court) — Federal Supreme Court
- Code of Obligations, Arts. 373 and 374 (status as of 1 October 2026) — Fedlex
Compliance notice. This article is a technical and educational analysis based on Swiss law in force and published decisions; the parties are anonymised as in the judgments. It does not replace the advice of a specialist lawyer for an ongoing dispute. Art Construction is independent of the SIA and CRB: their standards are not reproduced. Legal texts and judgments reviewed on 18 November 2026. This version is an automatic translation of the French article, which remains the authoritative text in the event of any discrepancy.