Unit Price Adjustment Calculator (±20% Art. 86 SIA 118) & Change Order Template
Measure the effect of a ±20% change in quantity on the unit price and prepare the change order.
Interactive tool
If left empty, the tool proposes the variable cost of the initial price (fixed costs are already amortised). The final price is set by mutual agreement on the same basis as the tender (Art. 62 para. 2).
Thresholds of Article 86 SIA 118
- Lower threshold (80% of Q₀)
- Upper threshold (120% of Q₀)
- Unit fixed costs (PU₀ × fixed share)
- Unit variable cost
Account in accordance with SIA 118
Change order template to print
The template reuses your figures and provides for the parties' signatures. Have it reviewed before signing.
Embed this calculator on a website page
Paste this code into the page, or write [outil code="3.3"] in the content of a page on the site.
📄 Files and templates linked to this tool (free)
- PDFDOCX ⚖️ Pure Law Cost Overrun on a Quote Pack (lump sum, estimate, SIA 118) Complete 5-page guide (PDF) and Word template. Lump-sum price, approximate quote or unit prices: who pays for the overrun, how to report it in time, notice, request for adjustment, the client's reply and a change-order form. See the file, its mini-tool and the pack →
- XLSXPDF Tracking of Daywork Reports & Change Orders The daily daywork sheet to print and the monthly table of pending or signed daywork, with a deadline alert. See the file, its mini-tool and the pack →
Move from calculation to full management
Keep your references at hand, then automate them in your quotes, bids and final statements.
Technical reference guide
How does the ±20% rule of Article 86 SIA 118 work on unit-price contracts?
The Article 86 SIA 118 quantity variation 20% governs what happens to the unit price when the quantity executed departs from that of the bill of quantities following an order modification. It belongs to the series of Art. 84 to 91 of the standard: it is the reference rule when searching for “site order modification SIA 118 Art. 84 87”. It assumes that SIA 118 is part of the contract; the contract may provide for a tolerance other than 20% (Art. 86 para. 3).
1. Between 80% and 120% of the quantity in the estimate: the initial unit price remains strictly unchanged
When quantities change by no more than 20%, the agreed unit price remains valid for the whole quantity executed (Art. 86 para. 1). For a bill of quantities of 100 m², any final measurement between 80 m² and 120 m² is paid at the contract price, without a change order.
2. Below 80% (under-quantity > −20%): why the contractor has the right to raise the unit price to recover unamortised fixed costs
When the final quantity does not reach 80% of the planned quantity, either party may demand a supplementary price for the quantity that falls short of 80% (Art. 86 para. 2). The tool models this right with the calculation new unit price amortisation fixed costs: the unit fixed costs (installations, overheads and profit, by default 25% of the price) that were to be amortised up to the 80% threshold are compensated, i.e. (80% of Q₀ − Q₁) × unit fixed costs, added to the price of the quantities executed.
3. Above 120% (over-quantity > +20%): the new unit price applies only to the quantity exceeding 120%!
For an over-quantity, the initial price holds up to 120% of the planned quantity; only the quantity beyond 120% is subject to a new price, set on the same basis as the tender (Art. 86 para. 2 and 62 para. 2) and recorded in a change order. The statement comes in two lines: 120% of Q₀ at the initial price, then the excess at the supplementary price. As the fixed start-up costs are already amortised, this price is often lower, unless extra equipment is needed.
| Quantity executed | Rule applied | Amount of the item excl. TVA (HT) |
|---|---|---|
| Q₁ = 110 m² (between 80% and 120%) | Initial price unchanged: 110 m² × 120.00 CHF | 13'200.00 CHF |
| Q₁ = 55 m² (under-quantity) | 55 m² × 120.00 CHF + 750.00 CHF of unamortised fixed costs (compensated price: 133.64 CHF/m²) | 7'350.00 CHF |
| Q₁ = 160 m² (over-quantity) | 120 m² × 120.00 CHF + 40 m² × 90.00 CHF (proposed variable cost) | 18'000.00 CHF |
The rule does not apply when quantities cannot be fixed at tender stage for construction-technical reasons, nor to items designated as such in the documents (Art. 86 para. 4). The price of the excess is agreed between the parties: the tool's calculation is a basis for discussion.
New services not provided for in the contract (Art. 87 SIA 118): how to secure a written change order before carrying out the work
For extra works change order estimate Swiss building, the golden rule is to agree the price before starting. When an order modification requires a service whose unit price is not in the bill of quantities, the parties agree as far as possible before the start of the work to define it and set the supplementary price, which is the subject of a change order to the bill of quantities (Art. 87 para. 1). A change order cannot be imposed on the other party, but it can be proposed in writing, priced, before carrying out the work.
- How to set the price: starting from the price of the closest contractual service, taking the difference into account, otherwise by mutual agreement on the same calculation basis as the tender (Art. 87 para. 2 and 3).
- If the parties cannot agree: the site management may have the work carried out on a daywork basis or entrust it to a third party while fully compensating the contractor; minor works are always done on a daywork basis (Art. 87 para. 4; see the daywork report generator).
- Key point: an oral order with no written trace is hard to prove; confirm it by email and have the change order signed. The price escalation calculator completes the set-up for price increases.
Frequently Asked Questions on Order Modifications and Art. 86 SIA 118 (FAQ)
1. What does Article 86 SIA 118 say about quantity variations?
If the quantities of the unit-price bill of quantities vary by no more than 20%, the agreed unit price remains valid (Art. 86 para. 1). If the final quantity exceeds 120% or does not reach 80% of the planned quantity, either party may demand a new price, set on the same basis as the tender, for the quantity above 120% or for the quantity short of 80%: this is the supplementary price, which is the subject of a change order (Art. 86 para. 2).
The contract may provide for a tolerance other than 20% (para. 3), and the rule does not apply to quantities that cannot be fixed for technical reasons (para. 4).
2. What to do if the quantity executed is below 80% of that of the estimate?
The contractor may ask for compensation of the fixed costs that could not be amortised. Example: 100 m² planned at 120 CHF, 55 m² executed, 25% fixed costs (30 CHF per m²). The quantity short of 80% is 25 m², i.e. a surcharge of 750.00 CHF and a compensated price of 133.64 CHF per m² on the 55 m² executed.
The tool applies this calculation model; the final amount results from the change order agreed between the parties.
3. How to price the quantity exceeding 120%?
The initial price holds up to 120% of the planned quantity; only the excess may be subject to a supplementary price. Example: 160 m² for 100 m² planned at 120 CHF. Line 1: 120 m² at 120 CHF = 14'400.00 CHF. Line 2: 40 m² at the agreed supplementary price (for example 90 CHF if the fixed costs are already amortised) = 3'600.00 CHF, i.e. 18'000.00 CHF in total.
The price of the excess is set by mutual agreement on the same calculation basis as the tender (Art. 62 para. 2): the tool's calculation is a starting proposal.
4. What to do before carrying out a service not provided for in the contract?
Agree the price in writing before starting: when an order modification requires a service whose unit price is not in the bill of quantities, the parties agree as far as possible before the start of the work and sign a change order (Art. 87 para. 1). The price is derived from the closest contractual service (para. 2), otherwise set by mutual agreement on the calculation basis of the tender (para. 3).
Failing agreement, the site management may have this work carried out on a daywork basis or entrust it to a third party, fully compensating the contractor; works of minor importance are always carried out on a daywork basis (Art. 87 para. 4).
Indicative information drawn up from the text of the SIA 118 standard (2013 edition). The final amount of a change order results from the agreement of the parties.