The 3 Major Site Risks
- Financial / Margin: Uncontrolled budget drift on unconfirmed measured or daywork items, generating an overrun of around 10% to 25% of the cost of the structure, with disputes over the amount when closing accounts under the rules applicable where the price was not fixed in advance or was set approximately.
- Legal / Joint Body / SUVA: Reclassification of daywork hours during inspections by cantonal joint commissions, challenge to the validity of change orders issued by a representative lacking authority of representation, or contentious enforcement of a real security on the real estate parcel.
- Administrative / Acceptance: Blocking of final account verification, suspension of security releases, and forfeiture of measurement disputes due to the lack of regular joint site measurements during the progress of the works under standard SIA 118.
Financial management of a construction site in Switzerland is the nerve centre of operational management for building, civil engineering, and finishing work operations. For practitioners such as site managers, construction project managers, foremen, and client representatives, monitoring financial flows is far more than a basic bookkeeping task of tallying progress billings. It requires rigorous implementation of the contractual mechanisms governing the contract for work under art. 363 CO, coordinated with standard trade practices under standard SIA 118. Right from the start of operations, every technical decision, ground unforeseen circumstance, and drawing revision entails direct pecuniary consequences. When a construction contract subjects the parties' relations to standard SIA 118, the procedures for quantity take-offs, daywork ordering, unit price adjustments, and monthly progress billing follow strict contractual formalities; failing to observe them compromises the project's financial balance. On construction sites in French-speaking Switzerland, from the cantons of Geneva, Vaud, Fribourg, Valais, Neuchâtel, and Jura to the Bernese Jura, stakeholders must navigate accurately between the requirements of bills of quantities structured under the Standard Article Catalogue, KBOB directives on price fluctuations, and benchmark statistical data such as the Indice ACIP. Managing financial flows requires unassailable written documentation to prevent services executed in good faith from being disallowed during the final settlement of accounts.
This comprehensive guide details all protocols required to rigorously administer accounting on a construction site governed by Swiss law. We will examine in turn the establishment and sign-off of joint site measurements as opposed to purely theoretical measurements derived from execution drawings, the strict procedural framework governing the performance and approval of daywork reports, as well as the calculation methods applicable to change orders and quantity variations. The analysis will also cover auditing monthly advance payment statements, retention money, and price escalation adjustments based on KBOB methods, culminating in the preparation and unreserved sign-off of the final account. Steering a project requires drawing a clear line between the execution phase and initial cost estimation, the latter falling within the tendering phase accessible via the dedicated Soumissions platform. Similarly, professionals seeking detailed statistical price levels by cost group should consult the price catalogues of the Indice ACIP, while specific staffing and payroll matters are addressed in the section dedicated to human resources and jobs. Through a pragmatic approach informed by field feedback and operational tools, this resource enables every trade professional to safeguard their contractual rights and maintain flawless financial traceability.
The contractual pricing structure represents the first pillar of site financial management. Under Swiss private law, freedom of contract allows parties to agree on various forms of remuneration, primarily unit prices, lump sums, and lump-sum prices. Art. 373 CO sets the fundamental rule whereby a contractor undertaking works for a fixed lump sum must complete the structure for that agreed amount and cannot claim any increase, even if the works required more expenditure than anticipated, subject only to unforeseen extraordinary circumstances. In standard Swiss practice, contracts are overwhelmingly awarded on the basis of unit prices linked to standardised price books. Under this framework, the actual price depends directly on the quantities actually placed in the work. This mechanism places the responsibility of physical measurement onto site management and the site supervisor, who must record the physical reality of the works as they are completed. When the contract does not fix the price in advance, art. 374 CO provides that it is determined according to the value of the work and the contractor's actual expenses. This statutory provision ties in closely with the rules of standard SIA 118, which meticulously regulates the taking of on-site measurements for elements to be covered up subsequently, such as earthworks, trench shoring, buried conduits, or rebar in reinforced concrete. Omitting a prior joint record before pouring a concrete slab or backfilling leaves the contractor facing severe evidentiary hurdles.
The handling of daywork represents a second major source of financial friction. On Swiss construction sites, daywork must never become a default billing method for poorly scoped tasks; it is a contractual instrument strictly reserved for minor unforeseen work or tasks for which no unit price can reasonably apply. Standard SIA 118 requires that resorting to daywork be agreed upon prior to starting any performance. Foremen must prepare daily daywork slips specifying the exact qualifications of deployed labour, hours worked, motor tools and heavy equipment used, and materials consumed. These reports are then submitted to site management, which is bound by strict contractual time limits to sign them off or issue substantiated objections. Should local site management delay its formal response, tacit acceptance mechanisms may take effect, complicating subsequent challenges by the client. Furthermore, the cost of daywork labour incorporates markups for overheads, small tooling, and contractor profit, all of which must strictly match the rate schedules appended to the initial contract or align with recognized regional joint commission tariffs.
Change orders constitute the third critical component of a project's financial life cycle. Changes to the architectural design, unexpected geotechnical conditions, or specific client requests regularly alter originally agreed works. Under standard SIA 118, the contractor is required to carry out modifications ordered by the client provided they relate directly to the intended structure and do not fundamentally disrupt the economic balance of the contract. However, this obligation carries the corresponding right to an adjustment in remuneration and construction schedules. When volumes for specific bill items vary substantially, the distribution of fixed costs and unit margins is affected. The standard framework sets a standard variance threshold beyond which either party is entitled to demand a renegotiation of the unit price applied to surplus or shortfall quantities. Site management must review these requests systematically, breaking down hourly wages, equipment productivity, and material purchase costs to settle on an equitable unit price for both parties, thereby preventing uncontrolled cost overruns before issuing supplementary purchase orders.
Continuous cash flow management operates through the monthly advance payment cycle. The contractor prepares payment requests based on the actual progress of the works, supported by verifiable interim measurement statements. Site management carries out arithmetic and qualitative checks on these statements, deducts contractual penalties or retentions where applicable, and issues a payment certificate forwarded to the client. It is during this procedure that retention money is applied to cover potential defects until formal acceptance. Standard SIA 118 governs this security via a retention on advance payments, which can be substituted with a joint and several guarantee issued by a prime Swiss bank or an authorized insurance company. Simultaneously, the impact of material and labour price fluctuations on long-term construction sites is addressed using price adjustment calculation formulas recommended by KBOB, based either on the parametric method or the documentary evidence method. This computational rigor prevents late disputes regarding currency depreciation or raw material inflation on the Swiss market.
Finally, the closing of accounts culminates in the preparation of the final account. Upon completion of the works or after the joint inspection of the structure, the contractor has a contractual deadline of two months to submit the closing statement, consolidating all advance payments received, retentions applied, definitive measurements, and approved daywork reports. Site management then has one month to audit the file and communicate any corrections. Signing the final account by both parties generally operates as a full and final discharge for claims arising from physical execution, precluding further financial claims regarding the construction price, subject only to statutory rights regarding latent defects. In the event of late payment of acknowledged sums, the creditor may issue a formal notice under art. 102 CO, which activates entitlement to statutory default interest. If serious disputes remain unresolved, the contractor retains the option to enforce securities provided under the Civil Code. Art. 837 CC grants the contractor the right to demand registration of a statutory mortgage lien of craftsmen and contractors on the relevant real estate parcel to secure payment of claims for labour and materials. This statutory right must be exercised within the strict statutory time limits established under art. 839 CC, under penalty of absolute forfeiture of the real estate lien privilege.
Throughout this comprehensive overview, site financial management emerges as a demanding discipline requiring constant coordination between practical field operations and strict compliance with Swiss contract rules. Site managers and project leads will find in the following sections the detailed calculations, approval flowcharts, and document templates required to secure every franc spent, while fully protecting the project's interests and ensuring fairness between construction partners.
Normative and contractual framework of financial management under standard SIA 118
Financial management of a construction project in Switzerland is structured around the fundamental principles of the contract for work and services, supplemented by the professional rules of standard SIA 118. Contractual balance relies on a clear distinction between the different pricing methods and the continuous traceability of works carried out. When the parties incorporate standard SIA 118 into the agreement, its provisions prevail as agreed contractual rules, defining the powers of site management, the duties of the contractor, and the prerogatives of the client.
Pursuant to art. 364 CO, the contractor is liable for the execution of the work and the required diligence, which encompasses the duty to give notice of foreseeable variances and provide supporting documents for costs incurred. In the Swiss financial framework, cost breakdown is usually performed according to Swiss construction catalogues, in particular the Building Cost Code and the Standardised Description of Work Items drawn up by the Swiss Research Centre for Architecture, Civil and Building Engineering. This standardised classification ensures consistency across the order phase, the measurement of as-built quantities, interim billing through advance payments, and the preparation of the final account.
Contractual doctrine distinguishes three basic compensation models: unit prices applied to actually measured quantities, lump-sum or fixed prices agreed for a specific work, and works paid on actual expenses as daywork. Each of these arrangements entails a specific monitoring regime for local site management and governs how subsequent change orders are handled.
Pricing types and cost allocation under the Building Cost Code
The unit price contract is the most common arrangement for structural work and infrastructure projects. The order is placed on the basis of a detailed quote structured in chapters according to the Building Cost Code. Each item includes a technical description, a precise unit of measurement, and a firm unit price. This unit price covers the supply of materials, tooling, labour, social security contributions, corporate overheads, and the profit margin.
Under this model, quantities indicated in the initial tender are indicative figures based on the working drawings. Final compensation derives from actual measurements taken after the works are built. However, standard SIA 118 establishes a contractual protection mechanism in the event of a significant variance between estimated and actual quantities. If quantities carried out deviate substantially from the detailed quote, either party has the right to request an adjustment of the unit price to reflect changes in site installation, logistics, or procurement costs.
Conversely, where the parties agree on a global or lump-sum price, the total amount remains fixed for the agreed scope of work. The contractor bears the risk of extra work, provided that the nature, quality, and dimensions of the works undergo no change directed by site management or resulting from circumstances beyond the contractor's control. If change orders occur, they must be set down in separate addenda to maintain the accounting integrity of the initial lump sum.
Legal status of daywork and limits of subsidiarity
Daywork is an exceptional method of compensation, applicable only when works cannot be described accurately in a preliminary detailed quote or when they involve unforeseeable, ancillary, or urgent interventions. Standard SIA 118 sets out the principle of subsidiarity: works must primarily be carried out at unit prices or for a lump sum. Carrying out daywork requires an express, prior order from site management, except in cases of imminent danger where safeguarding the works or persons calls for immediate action without prior notice.
The costs of daywork are determined based on the value of labour, plant deployment, and materials used. The hourly rates applicable are settled in the initial contractual agreement, often aligned with the schedules of cantonal professional associations in the main construction trades or finishing work. These hourly rates include gross wages, mandatory employer social security contributions, small tools, technical supervision, administrative overheads, and the corporate margin.
From an operational perspective, the contractor is required to assign staff to these tasks in accordance with the Construction Work Ordinance, specifically regarding the presence of a competent safety officer under art. 5 OTConst. Strict daywork administration demands daily tracking of every resource deployed: worker qualifications, exact working hours, type of machinery used, consumables, and raw materials incorporated into the works.
Change orders and contractual mechanism of addenda
Any intervention requested by the client or ordered by site management that departs from the initial plans, tender specifications, or conditions of execution constitutes a change order. Standard SIA 118 grants the client the right to order modifications, provided they remain related to the subject matter of the contract and do not fundamentally alter the nature of the work.
This power to make modifications gives the contractor the right to obtain a corresponding adjustment to the price of the work and contractual deadlines. As soon as a variation is contemplated, the parties must draw up a written addendum. This document sets out the detailed technical description of the altered works, the financial consequences calculated using the pricing bases of the initial contract, and the impact on the overall schedule. If the variation eliminates certain tasks, a proportionate deduction is made, taking into account expenses already incurred in good faith by the contractor.
Executing an addendum is not a mere accounting formality: it formalises the agreement of the parties on the new scope of their reciprocal obligations. Without a prior addendum or without formal approval from site management acting within its representation powers, a contractor taking the initiative to alter the work risks having to bear the extra costs or shoulder the expense of bringing the work into conformity with the original contract documents.
Legal regime of defects, advance payment statements, and limitation periods
Financial control on site runs parallel to quality supervision of the works. In construction contracts, invoicing proceeds via monthly advance payments based on the progress of the works. Standard SIA 118 provides that these advance payments are audited by site management within a specified period after receiving the statement submitted by the firm. To secure sound performance and the remediation of any defects identified along the way, retention money is withheld from certified amounts, unless the contractor provides equivalent security in the form of a bank or insurance guarantee.
In the event of delay in paying amounts due and payable, the general rules of the Code of Obligations apply. Under art. 104 CO, default interest of 5 % per year is payable once the debtor receives formal notice for the payment of a sum of money, unless a higher rate has been validly stipulated in the contract. This mechanism affords the contractor financial redress against unjustified payment delays that undermine its operating cash flow.
Upon full completion of the works, the contractor submits its final account to site management. This document summarizes all advance payments received, final measurements, approved addenda, and authorised daywork. Acceptance of the work then triggers warranty and limitation periods. Under art. 371 CO, the client's rights in respect of defects in immovable property lapse after a limitation period of five years against the contractor, architect, or engineer, a period that cannot be shortened contractually to the client's detriment. Upon delivery, the client inspects the state of the work and, for immovable property, has 60 days to give notice of defects under art. 367 CO. Final financial closing can therefore only be formalised once the reservations entered in the acceptance report have been resolved.
Methodical protocol: from joint site measurement to account closing
Sound financial management of a Swiss construction site requires a strict operational protocol executed in several successive stages. This methodical approach avoids late disagreements, disputes over quantity surveys at project closeout, and contested daywork invoices. Each step defines the respective roles of local site management, the project manager, and technical site supervisors.
Step 1: Preliminary joint inspection records and site condition survey
Before deploying machinery or opening a trench, site management and the contractor carry out a joint inspection record of the premises and neighbouring properties. This initial measure serves to record the baseline condition of adjoining plots, municipal public roads, and existing underground utilities.
In earthworks and civil engineering, this stage includes setting elevation benchmarks and reference survey monuments. Joint pegging out establishes the initial profiles of the natural terrain. The surveyor plans produced from these measurements are signed jointly by both parties. They provide an indisputable calculation baseline for later determining the exact volumes of cut, fill, and topsoil stripping.
This initial record also captures specific environmental conditions and the state of access roads. For deep excavations exceeding 1 m 50, the parties ensure that planning adheres to slope stability requirements in compliance with the Construction Work Ordinance, thereby preventing disputes over unexpected shoring surcharges.
Step 2: Periodic joint measurement surveys on site
As works progress, structural components intended to be concealed or backfilled must be subject to joint measurement surveys on site before they are covered up. This applies in particular to excavation beds, gravel sub-base courses, drainage and wastewater pipes, reinforcing steel prior to concreting, and buried waterproofing systems.
The project manager prepares detailed measurement sheets recording actual dimensions surveyed on site, gridline references, and corresponding item numbers from the Standardised Description of Work Items. Local site management checks these surveys directly on site before works proceed. Once the measurements are validated, the measurement sheet is initialled and signed by both designated representatives.
If discrepancies arise between dimensions surveyed on site and those on working drawings supplied by design management, an additional survey is performed immediately. The absence of joint verification for concealed works deprives the parties of conclusive evidence when drawing up advance payment claims, creating prejudicial uncertainty at the final account stage.
Step 3: Daily issuing, logging, and sign-off of daywork sheets
Administering daywork demands daily administrative discipline. As soon as a daywork order is issued by site management for an ancillary or unforeseeable task, the site foreman opens a daywork log identified by a unique sequential number, tied to the relevant Building Cost Code chapter.
At the end of each working day, or at the latest within the deadline stipulated in the contract for work and services, the contractor records on the daywork report:
- The exact date and working hours for each operative;
- The name and professional grade of each operative, in line with the wage scales of the applicable collective labour agreement;
- A clear and concise description of the tasks performed and their location on the construction site;
- Plant and machinery used, distinguishing productive operating hours from standby or idle time resulting from site conditions;
- The quantities of materials and consumables supplied specifically for the task.
This report is sent immediately to the local site management. They carry out its formal verification, check that the hours stated match the actual presence observed on site, and sign it off. Any dispute regarding the number of hours or the qualification of the workers must be noted on the document immediately. Sign-off by the site management certifies the factual reality of the hours and resources deployed, without predetermining final financial eligibility should the work have originally fallen under the obligations of the unit price or lump-sum price.
Step 4: Handling change orders and processing addenda
As soon as a change to the work is requested or proves essential due to physical constraints encountered on the construction site, the contractor informs the site management of the resulting financial and schedule consequences. This notification takes place before the modified work begins.
The contractor prepares a detailed supplementary quote. This tender addendum relies on the price structure of the main building contract: using identical contractual unit prices for similar work, or calculating new unit prices derived from existing price breakdowns for unprecedented work. For technical equipment or materials not listed in the initial quote, costs are established based on actual purchasing outlays marked up by the contractual percentages for overheads and profit.
The site management reviews the addendum offer, compares the financial ratios with Swiss construction market benchmarks, and negotiates any adjustments. Once the document is approved, the addendum is signed by the client or their authorised representative and by the contractor's executive management. This addendum formally amends the total contract amount and, where applicable, extends the completion deadline set in the contractual schedule.
Step 5: Reviewing advance payment requests and applying retentions
At the end of each monthly period, the contractor submits an advance payment request. This financial statement summarises:
- Amounts relating to quantity surveying progress for unit-price items, backed by signed joint measurement sheets;
- The progress share of lump-sum items, established according to a verifiable completion percentage on the structure;
- The total of daywork vouchers duly signed off by the site management over the past period;
- Instalments of approved addenda that have reached execution maturity.
The site management has a contractual timeframe to verify calculations, correct misallocations, and issue the payment certificate. During this process, the retention money agreed in the building contract is deducted from the net amount excluding tax. In accordance with SIA 118 practice, this retention typically amounts to a percentage of around 10% on initial advance payments, which may be capped or reduced to 5% of the total cost of the work as progress continues, or replaced by a joint and several guarantee complying with Swiss law.
Value-added tax at the current Swiss rate of 8,1% is then applied to the amount resulting from these deductions. The approved payment order is then forwarded to the client for payment into the contractor's account within the agreed deadlines.
Step 6: Preparing the final account and settling mutual claims
The final step in financial steering occurs after full completion of the works and acceptance of the work. The contractor prepares the final account, which consolidates all financial dealings arising from the contract. This document includes all final measurements, the balance of daywork, addendum statements, any adjustments for material price fluctuations according to conventional methods, and a summary of all advance payments already received.
The site management examines the final account, checks each amount against the site meeting minutes and supporting vouchers, and compiles its financial settlement report. Once the parties agree, the full and final settlement document is formalised. The final receipt confirms payment of the balance of the contractor's claim and the release or return of the retention money, subject to the statutory or contractual warranties for any defects governed by art. 371 CO.
Comparative table of remuneration and financial management instruments
The table below summarises the contractual tools used in the financial management of a Swiss construction site subject to standard SIA 118, setting out regulatory requirements, practical implications for site supervisory staff, and operational checkpoints.
| Tool or procedure | Contractual and regulatory framework | Practical implications on the construction site | Key points of vigilance for site management |
|---|---|---|---|
| Unit-price contract | Standard SIA 118 and chapters of the Standard Elements Catalogue | Remuneration tied to volumes measured in situ; requires continuous monitoring of quantities placed. | Check consistency between drawing measurements and actual measurements; monitor volume drift on earthworks. |
| Lump-sum or fixed-price contract | Lump-sum regime under standard SIA 118 and the Swiss Code of Obligations | Fixed price for a defined technical scope; volume risks lie with the contractor. | Refuse extra charges for works included in the original project description. |
| Joint measurement of hidden works | Provisions of standard SIA 118 on the recording of works | Mandatory dimensions taken on site before burying utility networks, backfilling, or pouring concrete. | Require immediate signing of survey sheets; record cross-sections in the site logbook. |
| Daily daywork | Standard SIA 118 and collective labour agreement rates | Remuneration based on time spent and materials consumed; subsidiary method requiring a formal order. | Check staff qualifications, plant operating hours, and signed daily reports on a daily basis. |
| Addenda for change orders | Standard SIA 118 and bilateral agreement on supplementary pricing | Prior formalisation of any change in scope altering costs or completion deadlines. | Never authorise execution of additional work without prior approval of the addendum offer. |
| Retention money on advance payment requests | Contractual practice under standard SIA 118 and financial securities | Deduction of around 10% to 5% on monthly certified amounts to cover defects. | Verify the legal validity of the replacement bank guarantee before releasing any retained funds. |
| Default interest for late payment | Art. 104 CO (statutory rate of 5% per annum) or contractual stipulation | Financial charge borne by the client if verification and payment processing deadlines are exceeded. | Strictly observe review periods for advance payment requests to prevent formal notice of default. |
Decision criteria for financial steering and margin control
Site financial management allows no room for approximation. To adjudicate disputed situations effectively and safeguard the operation's financial balance, site management and project managers must apply a decision grid structured around objective criteria.
Adjudicating between unit price adjustment and additional work
When a major volume change occurs on a bill item, the site manager must determine whether the work involves a mere quantity adjustment or a genuine change order:
- Identical nature and unchanged execution method: If the additional work strictly matches the description in the Standard Elements Catalogue and is carried out using the same logistical resources, the contractual unit price applies. Any price adjustment occurs only if the scale of the variation fundamentally alters the contractor's economic terms anticipated when signing the contract.
- Change in physical conditions or technical specifications: If the work requires using different materials, a substantial change in method dictated by ground conditions, or an imposed execution pace outside initial tolerances, the situation requires establishing a new unit price via a negotiated addendum.
- Occasional work not measurable by work unit: If the intervention is of very short duration, localised, and cannot be linked to a measurable physical unit (square metre, cubic metre, tonne), using controlled daywork is necessary, provided the site management has issued a formal site work order.
Social compliance monitoring, safety, and impacts on accounts
Financial control on site links directly to monitoring the social compliance of contracting firms. On Swiss construction sites, the use of posted workers or subcontractors is subject to heightened scrutiny. Under the Posted Workers Act, minimum working and wage conditions are guaranteed to workers posted to Switzerland, and the employer is required to declare the assignment to the designated cantonal authority before work begins.
In the event of non-compliance with these duties, administrative penalties of up to 5000 francs or 30 000 francs may be imposed under art. 9 LDét, notably for breaches of notification obligations or minimum terms. Likewise, cantonal bodies conduct inspections regarding compliance with declaration and authorisation duties pursuant to the Federal Act on Combating Undeclared Work. Any administrative breach can lead to the immediate shutdown of a team's activity, disrupting physical progress and generating indirect site extension costs that the client cannot assume.
Furthermore, financial coordination encompasses strict consideration of the safety measures prescribed by federal legislation. When a design change involves trenching along public roads or working at height, site management must ensure collective protective measures are dimensioned in compliance with applicable rules. Installing edge protection comprising a top rail whose upper edge is at least 100 cm above the working surface, at least one intermediate rail, and a toeboard of at least 15 cm under art. 22 OTConst, or setting up facade scaffolding extending at least 80 cm above the edge of the drop zone pursuant to art. 26 OTConst, represents installation costs that must be clearly identified in Site Installations items and cannot be invoiced separately without prior agreement.
Handling financial claims and contractual preclusion
Swiss site management practice dictates proactive claims management. A contractor who believes they are entitled to additional remuneration due to unforeseen circumstances must register their claims as promptly as possible. Failing to assert a claim contemporaneously makes it harder to review the legitimacy of the alleged costs later on.
Site management must record in the weekly meeting minutes every event alleged to cause extra costs: delays in issuing detailed drawings, exceptional weather conditions, undiscovered underground pipes, or specific geotechnical findings. This objective logging enables claims to be processed on the basis of tangible evidence, ruling out global lump-sum requests submitted late when the final account is delivered.
In summary, financial management on a Swiss construction site relies on strict adherence to contract documents, traceability of daily operations, rigorous field measurement, and administrative responsiveness to project modifications. This framework ensures the legal compliance of accounts and shields both the client and contractors from cost overruns that jeopardise the success of the work.
Financial implementation by execution scenario on the Swiss construction site
Operational management of financial flows on site demands rigorous adaptation depending on critical construction site phases and the nature of the interventions. Site management must reconcile technical progress requirements with the formal stipulations of standard SIA 118, reference scales such as the ACIP index, and KBOB guidelines. The following analytical table details the action protocols, mandatory supporting documents, and vigilance points for three recurring financial situations encountered during the execution of a works contract.
| Site situation | Nature of financial contingency | Recording and formalisation procedure | Contractual impact and settlement rule | Site management point of attention |
|---|---|---|---|---|
| Special earthworks and encounter with unforeseen buried utilities | Cost overrun linked to manual clearance, additional shoring, and removal of contaminated excavated material. | Immediate joint inspection record on site, geometric survey of cubatures, prompt written notification under the contractor's duty to notify. | Establishment of an addendum for additional work or daywork settlement strictly limited to unforeseen operations at agreed rates. | Strict verification of the separation of soil and mineral waste in compliance with waste ordinance requirements, without extrapolation to existing unit price items. |
| Modification of the finishes programme by the client | Substitution of floor coverings, recalibration of screeds, and adjustment of laying layouts. | Written change order issued by the mandated representative prior to execution, accompanied by a detailed price quote from the contractor. | Application of contractual unit prices for comparable services; determination of negotiated derived prices if the pace or constraints change significantly. | Verification that the contractor does not start works before formal cost validation is transmitted, avoiding any subsequent undocumented claim. |
| Emergency intervention to secure an unstable slope following severe weather | Additional heavy plant, continuous pumping, installation of unplanned temporary ground anchors. | Daily daywork reports drawn up on the same day, detailing operating personnel, machinery, and consumables, countersigned by the local management. | Payment on a daywork basis according to the contractual rate agreement or, failing that, based on documented local customary wages and rates. | Verification of machinery compliance and staff qualifications, rejecting the billing as daywork of routine collective protective measures already contractually owed. |
Sectoral application of joint measurement protocols
In earthworks and structural work (CFC chapters 211 and following), taking off quantities relies on systematically comparing the initial working drawings with dimensions measured in situ before backfilling or concreting. The contractor calls upon the site management to measure excavation depths, blinding concrete thicknesses, and concealed reinforcement. Any delay in this joint inspection record entails a major risk of forfeiture or complex expert appraisal: if a layer is covered without validation, the burden of proving the quantity actually executed falls upon the party asserting the payment claim. The measurement minutes must record the dates of intervention, cross-sections, references to survey grid lines, and the joint signatures of the construction manager and the site management.
In finishing work and building services (plumbing, ventilation, electrical, interior joinery), the joint measurement focuses on verifying installed linear lengths, special fittings, and dimensional adjustments dictated by the reality of the existing structure. The parties agree to check measurements by geographical sectors (floors, stairwells, or technical rooms) prior to closing shafts and suspended ceilings. The absence of written contestation within the deadlines set by standard SIA 118 confers decisive evidential weight upon the established measurements during the final liquidation of advance payments.
Administrative management and traceability of daily daywork slips
Daywork, which is subsidiary to work remunerated on the basis of unit prices or lump sums, demands daily recording discipline. The site foreman draws up daywork reports every working day, detailing the identity and trade classification of each worker, the actual hours spent on the ordered task, the type of machine mobilised with its precise operating time, as well as the type and quantities of materials incorporated or consumed. These reports are submitted to the site management within the standard timeframes of practice in French-speaking Switzerland, generally on a weekly or bi-monthly basis depending on the provisions of the works contract.
The site management reviews the entries without delay. The signature affixed to a daily report exclusively certifies the factual reality of the work performed (actual presence of personnel, operating hours of plant, materials installed). It does not constitute automatic acknowledgement of the obligation to pay for these hours as daywork if the task actually fell within the routine contractual duties specified in the quote. When the site management disputes the principle of daywork itself or a recorded number of hours, it enters its reasoned reservations in writing directly onto the slip before returning it to the contractor. Unresolved disagreements are immediately recorded in the construction site financial register to be formally arbitrated before the corresponding monthly advance payment is issued.
Illustrative practical cases (typical scenarios on Swiss construction sites)
The figures and data appearing in the scenarios below are constructed illustrative examples intended to clarify calculation mechanisms and financial decision-making on a Swiss construction site.
Standard Scenario 1: Managing quantity variances and unforeseen daywork on a residential building (Canton of Vaud)
As part of the construction of a development of three rental buildings comprising 36 flats in the district of Nyon (canton of Vaud), the project is awarded to a general contractor for the structural work and external works. The average workforce assigned to structural work operations ranges between 18 and 24 workers. The original contract is concluded on the basis of a unit-price quote based on the Standard Item Catalogue (CAN), for a reference contract value of 4 850 000 CHF excluding VAT (or 5 242 850 CHF including Swiss VAT of 8,1 %). The works contract incorporates standard SIA 118 as an integral part.
During the general bulk excavation phase and execution of drainage trenches (CFC 211), the contractor encounters an area of heterogeneous fill not identified during the preliminary geotechnical investigation, containing fragments of old masonry mixed with wet clay soil. The contractor immediately notifies the site management in writing and requests instructions to carry out the removal and replacement with compacted gravel of approved quality.
Two items of the quote undergo major quantitative changes:
- CAN item 211.101 "Bulk excavation" initially specified a volume of 6 200 m³ at the contractual unit price of 32,00 CHF per cubic metre, representing a base sum of 198 400 CHF excluding VAT.
- The volume actually excavated and jointly measured on site reaches 8 350 m³, representing a net increase of 2 150 m³, or a 34,68 % rise over the initial quantity in the quote.
- CAN item 211.305 "Supply and placement of 0/45 non-frost-susceptible gravel" increases from an initial planned quantity of 1 100 m³ to 2 450 m³, an increase of 1 350 m³ (+ 122,73 %) at the contractual price of 68,00 CHF per cubic metre.
In parallel, the contractor submits weekly daywork reports totalling 165 machine operator hours on a 22-tonne tracked excavator (agreed daywork rate: 165,00 CHF per hour), 240 hours of site mason (agreed daywork rate: 92,00 CHF per hour), and the supply of geotextile stabilisation sheets for 4 800 CHF excluding VAT, citing unforeseen difficulties with temporary shoring of the access platform.
Faced with this potential cost overrun in the region of 220 000 CHF excluding VAT, the site management initiates the following decision protocol:
- Analysis of the quantitative variation (plus-or-minus 20 % rule): For the excavation item (an overrun of 34,68 %, exceeding the standard 20 % threshold specified by standard SIA 118), the site management requests the contractor to justify its cost structure. Output analysis shows that using a higher-tonnage excavator reduced the unit extraction time on the excess volumes. Following joint negotiations, volumes up to 7 440 m³ (+ 20 %) are paid at the initial contract price of 32,00 CHF per cubic metre (totalling 238 080 CHF), whereas the excess 910 m³ are subject to a newly agreed unit price of 28,50 CHF per cubic metre (totalling 25 935 CHF), yielding savings of 3 185 CHF excluding VAT for the client.
- Assessment of claimed daywork hours: The site management rejects full coverage of the 240 mason hours claimed as daywork. An analysis of the initial quote confirms that routine works to secure site access are included in the contractor's site setup overheads. Only the 65 hours of precision excavation around live underground pipes and the 165 excavator hours expressly ordered to strip the contaminated area are approved. The amount accepted as daywork is thus reduced from 49 305 CHF to 33 205 CHF excluding VAT (or 35 894,60 CHF with 8,1 % VAT).
- Execution of a formal change order addendum: All quantitative adjustments and additional services lead to the drafting of addendum no. 1 to the works contract. This instrument establishes the final agreed cubatures, the adjusted unit price for the portion exceeding 20 %, the balance of approved daywork, and an extension of time of 8 working days granted to account for the geotechnical constraints, without financial compensation for idle equipment.
This protocol ensures strict adherence to the client's financial interests while ensuring the contractor recovers its reasonable actual costs, in accordance with the principles governing fair price adjustments when baseline project conditions are altered.
Standard Scenario 2: Addenda arbitration and advance payment management on a commercial refurbishment (Canton of Geneva)
The second illustrative scenario concerns the major refurbishment of an administrative building located in the Meyrin business district (canton of Geneva). The scope covers the complete overhaul of ventilation, air conditioning, and electrical installations (CFC chapters 230 and 240), as well as the reconfiguration of lightweight partitions and suspended ceilings (CFC 271 and 281). The site team averages 14 fitters and specialist technicians. The works sum awarded to a total contractor amounts to 3 200 000 CHF excluding VAT (or 3 459 200 CHF including 8,1 % VAT). The contract specifies the full application of standard SIA 118, an overall completion period of 9 months, and a monthly schedule of advance payments tied to installation progress.
During the fourth month of work, the client submits a substantial variation request: the executive floor must be reconfigured to integrate modular meeting rooms equipped with enhanced acoustic insulation and a room-by-room building automation system. These modifications cause work on partitions on this floor to stop temporarily and require completely redesigning the routing of ducts and cabling.
The contractor submits an overall claim broken down as follows:
- A proposed addendum no. 2 amounting to 245 000 CHF excluding VAT for the supply and installation of technical plant not included in the basic contract.
- A claim for compensation of 38 000 CHF excluding VAT for "loss of productivity and crew disruption" on the other floors of the construction site.
- An advance payment claim no. 4 for 420 000 CHF excluding VAT, anticipating 50 % of the additional work detailed in unexecuted addendum no. 2, alongside a request to release the contractual retention money on the grounds that the firm's financial standing is certified by a bank guarantee.
The site management intervenes to structure the legal and economic processing of this claim:
- Analytical breakdown of the addendum: Site management demands the submission of a detailed price schedule in compliance with the applicable CAN sub-chapters. Prices for standard technical components (glazed partitions, air diffusers) are benchmarked against local market rates documented by French-speaking Swiss databases and Indice ACIP reference values. After revising the estimated installation times, which were excessive given the modularity of the selected components, the addendum cost is adjusted and mutually agreed at 208 500 CHF excluding VAT (or 225 388,50 CHF including 8,1 % VAT).
- Rejection of unsubstantiated compensation claims: The 38 000 CHF disruption claim is dismissed in its entirety. Site management demonstrates, backed by the site log, that finishing work crews could be redeployed to lower levels without any stoppage, in accordance with the general duty of diligence and loyalty under the law of agency governing architects and engineers, as well as the contractor's duty to mitigate losses. With no material evidence of enforced personnel idle time, no compensation is due.
- Review of the advance payment claim and enforcement of retention money: Site management refuses to include any work from Addendum no. 2 in advance payment claim no. 4 until the addendum is countersigned by the client. Furthermore, it enforces the agreed 10 % retention money on each monthly advance payment under SIA 118 contract clauses, reiterating that substitution with a bank guarantee or joint and several guarantee may only occur upon completion of the work or through an express agreement approved by the client. Claim no. 4 is finally certified for a gross amount of 315 000 CHF, minus the 10 % retention (31 500 CHF), giving a net payable amount of 283 500 CHF excluding VAT (306 463,50 CHF including 8,1 % Swiss VAT).
This methodical approach eliminates the risk of double billing, restricts financial commitments to approved work, and ensures that the required level of financial security is maintained until acceptance of the work.
Operational checklist: Auditing financial flows and site measurements
This checklist summarises the essential checks site management must carry out at every stage of interim billing and account settlement:
- Prior verification of contractual authority: Ensure that every change order is backed by a written instruction issued exclusively by an individual authorised to commit the client, pursuant to the rules of contractual representation under the Code of Obligations (CO).
- Compliance of periodic quantity surveys: Ensure that joint on-site surveys are recorded on dated sheets, identified by grid line and level, including the necessary dimensioned sketches, before elements are concealed by subsequent building stages.
- Review of daily daywork sheets: Check the submission of daywork reports weekly; cross-check labour and machine hours against entries in the site log; approve only operations that have received prior authorisation.
- Enforcement of the 20 % quantity variation threshold: Track cumulative completed quantities line by line against the bill of quantities; identify CAN items nearing the plus or minus 20 % threshold without delay to start negotiations on a new unit price before the excess portion is completed.
- Application of retention money: Systematically apply the agreed contract retention (typically 10 % on monthly advance payments up to standard ceilings, then 5 % upon acceptance of the work) and verify the legal validity of any replacement bank guarantee or deed of surety submitted by the contractor.
- Handling material price fluctuations: If the contract includes a price escalation clause, review price adjustment calculations based on the KBOB parametric formula or the voucher method, strictly applying official indices published by the Swiss Federal Statistical Office.
- Consistency with safety regulations: Check that site-specific safety measures are consistently maintained and that the contractor complies with statutory duties, in particular by appointing the competent individual responsible for health and safety on the construction site under art. 5 OTConst, without seeking to bill these general obligations as additional daywork.
- Monitoring final account deadlines: Formally notify the expiry of the contractual review period for the final account (customarily 30 days from receipt of the documents under standard SIA 118) and document any disputes in a detailed comparison table delivered to the contractor.
Frequent mistakes on Swiss construction sites and their financial consequences
Experience in handling disputes on Swiss construction sites highlights several recurring failures in managing quantity surveys and daywork. Failing to understand formal rules exposes both clients and contractors to direct financial losses.
1. Automatic signing of daywork sheets without entering reservations
The most widespread mistake made by site management or the site manager is mechanically signing daily daywork sheets without checking the nature of the work listed. If signed without written reservations, the contractor can argue that the work was legitimately accepted as daywork, including tasks that were actually covered by its base quote (such as routine work area cleaning or sealing duct penetrations). The result is a direct financial loss for the client, who is billed for hours at daywork rates when the work was already included in the initial unit price or lump sum.
2. Carrying out substantial addenda on purely verbal instructions
Programme pressure frequently prompts parties to agree on project changes during weekly site meetings without formalising a written addendum before work begins. If a budget overrun subsequently occurs, the client may refuse to approve the extra charge, claiming that no additional paid work was ever authorised. The contractor is then confronted with the burden of proving an agreement on the essential terms of the contract, risking having its extra work categorised as complimentary or unpayable, leading to protracted disputes during final account settlement.
3. Overlooking the 20 % threshold on high-volume items
On large civil engineering or earthworks sites, site management sometimes fails to track the volume of quantities used. When an initially under-measured item doubles or triples in volume, renegotiating the unit price once all work is finished becomes difficult: the contractor argues that its resources were deployed based on the original rate card and rejects any price reduction. As a result, the client loses the chance to secure a volume discount reflecting the contractor's economies of scale on large quantities.
4. Billing upfront for stored materials not incorporated into the work
Including supplies that have merely been delivered to the construction site but not yet permanently built into the building (such as packaged sanitary appliances or cable reels) in advance payment claims poses a serious legal risk. In the event of contractor bankruptcy or on-site theft, the client has paid an advance payment on goods that can be claimed by third-party creditors or that remain the contractor's responsibility. Advance payments must strictly cover the actual value of work already executed and inspected on-site.
5. Failing to express formal reservations when applying contractual penalties
When a construction contract provides for a contractual penalty for delays in executing the work (under the liquidated damages and penalty clause mechanism in art. 160 CO), site management commits a fatal legal error if it accepts the delayed work without entering an express reservation at the time of acceptance. Handing over the work without reservation constitutes an irrevocable waiver of the right to claim the agreed contractual penalty, depriving the client of any deduction leverage on the final account balance to offset operational losses.
Ongoing monitoring: Document tracking, archiving, and financial audit
Sustained financial site management depends on meticulously organising substantiating documents throughout the project lifecycle and in the years following acceptance of the work.
Setting up and maintaining the financial register
From site opening onward, site management establishes a centralised financial register containing all original contracts, broken down by construction cost code (CFC). This living document is updated monthly to include:
- A summary table of submitted, approved and rejected change orders, with their projected and final cost impacts.
- A cumulative summary of signed joint quantity surveys, cross-referenced with original bill of quantities projections for each CAN chapter.
- A statement of advance payment claims submitted by contractors, detailing deductions made for retention money, any penalties and direct payments to subcontractors.
- A tracking log of received bank guarantees and deeds of surety, including expiry dates and liability caps.
This dashboard forms the core of the periodic reporting due to the client under site management's duty of diligent and faithful performance of its mandate.
Substantiating document archiving protocol
All documents used to draw up accounts (dimensioned survey drawings, levelling sheets, countersigned daily daywork sheets, concrete delivery dockets, construction waste disposal slips certifying cleared tonnages) must be digitised and stored in a secure folder structure. These records retain crucial evidential value in any subsequent legal proceedings or arbitration regarding the final account.
Statutory and contractual retention periods must be strictly observed. While standard commercial accounting rules require books and accounting records to be kept for 10 years, technical and financial records for a building project should be retained at least throughout the warranty and liability periods for defects. Detailed accounts, as-built drawings, and joint survey records make it possible to reconstruct the precise history of the work should a dispute arise later during the contractor's or design team's statutory liability period.
Social compliance audits and liaison with the financial management team
The financial management team must not overlook statutory requirements governing social compliance among contractors on site. Failure to comply with minimum wages set by branch collective labour agreements or breaches of due diligence obligations when using posted workers can severely disrupt construction progress. Site management ensures that contractors regularly provide joint social compliance certificates before major advance payments are released. This diligence protects the client from administrative complications that could bring work to a standstill or compromise the financial closeout of the project.
By consolidating control tools, contractual decision criteria and written record requirements, site management professionals deliver balanced, transparent and sustainable financial control on their construction sites, in full compliance with Swiss law and local building trade practice.
Contracts and SIA 118: free tools
Advance payments and retentions, surety bonds, price escalations, daywork reports, subcontractor monitoring.
Frequently asked questions
How must site management handle a disputed daywork report under standard SIA 118?
Managing daywork requires flawless documentation to safeguard the project's financial balance. When a contractor submits a daily or weekly daywork report containing work not ordered in advance or manifestly disproportionate hours, site management cannot simply remain silent. In accordance with the principles of standard SIA 118, reports must be verified promptly and returned with reasoned written comments. Site management must sign the document, expressly adding the note "accepted subject to verification" or "rejected for lack of prior order". If the contractor claims the work involved a technical emergency, it bears the burden of proving imminent danger to the structure or to persons. In a typical case on a structural work construction site, operator hours billed at an indicative rate of 165 CHF per hour without a formal purchase order must be isolated from the monthly account. Site management notifies in writing the rejection of the disputed item in the advance payment request, instructing the contractor to produce the relevant site instruction. Failing to lodge a reasoned objection within customary verification deadlines exposes the client to a presumption of tacit acceptance, which later complicates the final account. It is imperative to attach an annotated copy of the rejected report to the site meeting minutes to stop any late claims in their tracks.
When does unit price renegotiation apply for a variance exceeding 20 % under standard SIA 118?
The unit price adjustment clause set out in standard SIA 118 applies when a change order instructed by site management leads to a variance of more than 20 % upwards or downwards on the total quantity of an item in the contractual specification. This mechanism does not apply automatically from the first surplus cubic metre: each party retains the right to demand that a new unit price be set, tailored to the new economic conditions, solely for the portion of quantities exceeding the 120 % cap or falling below the 80 % threshold. To illustrate this rule, consider a foundation slab concrete item initially planned at 500 m³ at the contract price of 280 CHF per cubic metre. If technical adjustments bring the final executed quantity to 750 m³, the base contractual volume of 500 m³ and the 20 % margin (i.e. 100 m³, totalling 600 m³) remain remunerated at the contractual unit rate of 280 CHF. By contrast, the remaining 150 m³ is subject to a new unit price calculation. The contractor must break down its variable costs and fixed installation costs to draw up its addendum. If the quantity increase generates productivity gains, site management is entitled to negotiate a discount on this additional volume. Raw unit price tables and detailed breakdowns are available on the specialised portal /indice-acip/.
What are the notice and preclusion rules for a joint quantity survey on site under standard SIA 118?
A joint quantity survey on site provides the evidential basis for payments based on unit prices. Standard SIA 118 requires measurements to be taken in the presence of site management and the contractor's representative, particularly for building elements that will subsequently be covered up, such as trenched pipes, slab reinforcement or road foundation layers. The contractor is required to call site management in good time before backfilling or concreting. If site management, having been duly notified, fails to appear without legitimate grounds, the contractor takes the measurements alone and forwards its measurement sheets along with dimensioned sketches and dated photographs. Upon receiving these documents, site management has a defined review period to formulate written objections. Failing an objection within the agreed deadline, the measurements drawn up unilaterally by the contractor are deemed accurate and serve as proof for invoicing, creating a practical preclusion regarding dimensional findings. On earthworks representing, for instance, 140 000 CHF of excavation no longer visible later on, the absence of a joint counter-measurement strips the client of any serious grounds for objection when drawing up the final account, except in the case of manifest calculation errors.
How do retention money and joint and several guarantees interact in advance payments under standard SIA 118?
As part of monthly financial verification, site management applies contractual retention money to each advance payment request, in line with the standard rules of SIA 118. This retention, generally set at 10 % of the value of work executed up to a cap of 5 % of the total contract sum, aims to secure proper execution of the works and the rectification of any defects. The contractor has the right to substitute this financial retention with a joint and several guarantee issued by a prime Swiss banking institution or an approved insurance company. The deed of guarantee must strictly comply with Swiss law requirements and cover warranty obligations for building defects without adverse reservations. Upon receipt of a compliant security instrument, site management releases the sums retained on previous advance payments in the following accounting statement. On a finishing work technical package priced at 850 000 CHF excluding VAT (8,1 %), cumulative retention may reach an illustrative amount of 42 500 CHF. If the guarantor entity loses its licence or suffers financial default, the contractor must reinstate the security without delay, failing which site management will immediately reinstate the financial retention on remaining payments.
What is the deadline for submitting the final account under standard SIA 118 and what is the effect of a receipt in full and final settlement?
The financial close-out of the construction site follows a strict timetable laid down by standard SIA 118. The contractor must submit its complete final account, along with all measurement sheets, approved daywork slips and supporting documents for addenda, no later than two months after the taking-over of the works. Site management then carries out a detailed verification of the file within 30 days, before forwarding its settlement proposal to the client and the contractor. As soon as the parties agree on the settled amount, final payment is made. Acceptance of payment together with a mention of full and final settlement definitively extinguishes all ordinary financial claims arising from the execution of the works contract. The contractor can no longer assert subsequent claims for unforeseen work or omitted wage increases. Only warranty obligations for building defects under the Code of Obligations (CO) remain unaffected. For example, if a contractor belatedly claims 28 500 CHF in daywork hours six months after signing off without reservation on the final account settled at 1 200 000 CHF, this claim faces a formal procedural bar based on the full discharge agreed between the signatories.
How do you calculate and verify price escalation under the KBOB method on a Swiss construction site?
Adjusting the contract price to fluctuations in labour and building material costs is commonly carried out using the recommendations of the Coordination Conference of the Building and Real Estate Services of Public-Sector Clients (KBOB). Two main methods are recognised: the parametric method based on statistical indices from the Federal Statistical Office and the actual cost calculation method based on supporting receipts. Under the KBOB parametric method, the contract defines a contractual formula weighting the respective shares of wages, key materials (steel, concrete, timber) and energy. Site management applies the official monthly indices published for the date of execution of the works against the base indices set when the offer was submitted. The calculation is applied to the net value of services performed during the relevant month, less daywork invoiced at current rates. For a monthly infrastructure account of 320 000 CHF subject to an average index escalation of 3,2 % according to the applicable KBOB table, the price supplement amounts to an illustrative figure of 10 240 CHF. Site management checks that weighting coefficients are applied scrupulously to prevent any improper overlapping with addenda already negotiated at updated fixed prices.
What is the responsibility of site management upon discovering hazardous waste not included in the initial quote?
The financial management of a construction site goes hand in hand with environmental compliance and worker safety. During remediation or earthworks, the unforeseen discovery of contaminated materials (presence of coal tar, heavy metals or solvents) requires strict protective measures. In accordance with art. 16 OLED, the client must provide precise information on the nature and disposal route of waste whenever the volume exceeds 200 m³ or dangerous pollutants are present. Art. 3 OPA also requires the employer to take all protective measures consistent with recognised occupational health and safety rules. From a contractual and financial standpoint, site management must immediately record the event in writing, order the required laboratory testing and suspend operations in the affected area. Sorting, transport to a regulated landfill and decontamination services constitute change orders leading to a formal addendum based on approved tracking forms. Additional costs for testing and disposal in regulated landfills, which frequently amount to several tens of thousands of Swiss francs, must be allocated to a separate financial chapter to avoid holding up the main account.
Within what limits can site management apply delay penalties or contractual penalties?
Applying a financial penalty for failing to meet intermediate or final completion deadlines requires an express contractual stipulation. Under Swiss law, conventional penalties are governed by art. 160 CO, which provides that the creditor may claim the agreed penalty in the event of non-performance or late performance, subject to formal notice rules and the clauses of the work contract. Under art. 161 CO, the conventional penalty is incurred even if the client has suffered no direct economic loss. However, to remain enforceable, site management must imperatively reserve its right to the conventional penalty as soon as the breached deadline passes or, at the latest, upon formal acceptance of the work. Unreserved acceptance of late delivery extinguishes the right to claim the penalty. Furthermore, in accordance with art. 163 CO, the amount of the penalty is freely determined by the parties, but a court may reduce penalties it deems excessive. If a delay of 15 calendar days is subject to a contractual penalty of 2 000 CHF per working day on an overall contract of 1 800 000 CHF, site management deducts an illustrative amount of 20 000 CHF from the next advance payment, provided it has previously rejected the contractor's requests for deadline extensions due to substantiated bad weather.
The financial management of a Swiss construction site relies on the rigour of joint records, proactive management of addenda, and scrupulous adherence to the contractual procedures of standard SIA 118. To explore each technical aspect in greater depth and safeguard your professional practices in the field, read our detailed guides:
- Daywork (SIA 118): Daily Signing of Reports and Unordered Daywork
- Order Amendments and the ± 20% Rule on CAN Quantities (SIA 118): Renegotiating a Unit Price
- Joint On-Site Quantity Surveying vs As-Built Plans (SIA 118): Procedures and Forfeiture
- Checking Advance Payments, Performance Bonds (10% / 5% - SIA 118) and KBOB Price Fluctuations
- The Final Account (SIA 118): 2-Month Deadline, 30-Day Audit, and the Settlement Receipt Trap