Uster 1985: “flawless condition” written without an expert, 12 dead and a conviction (ATF 115 IV 199)
· 8 min read
Financial stake / risk 12 dead and 19 injured or exposed to immediate danger (9 May 1985); personal criminal conviction of three professionals, including the one who gave reassurance in writing.
Legal basis Art. 117 CP (Swiss Criminal Code - homicide through negligence) and art. 227 no. 2 CP (causing a collapse through negligence); Federal Supreme Court judgment of 13 November 1989 (ATF 115 IV 199).
Fatal error Writing “flawless condition” after a rudimentary check, without bringing in a specialist and without telling the client what had been seen.
Immediate workaround Record what you observe, state what you do not know, and bring in the appropriate expert before writing that everything is in order.
1. The facts: a broken tie rod, a reassuring statement
The Uster (ZH) Hallenbad was built in 1971/72. Above the swimming hall hangs an undivided concrete slab of 830 m², held by 207 10 mm chromium-nickel steel tie rods cast into the structure. The pool water was disinfected with chlorine gas: the exhaust air, laden with fine chlorinated droplets, deposited an acidic film of moisture on the tie rods. Result, according to the facts established by the judges (supported by EMPA (Swiss Federal Laboratories for Materials Science and Technology) expert evidence): pitting corrosion, followed by stress corrosion cracking. The tie rods were also overstressed: their safety factor was 1.27, whereas the applicable SIA (Swiss Society of Engineers and Architects) standards required at least 1.8.
In the summer of 1984, during window refurbishment works, a tradesman discovered by chance, in the ceiling void, a broken tie rod. The HTL architect acting as local site supervisor was informed. With the HTL engineer from the engineering firm retained for the structure, he inspected a few adjacent tie rods: they bore brown spots. The idea of rust was raised, then immediately discarded in favour of another explanation: the rupture dated back to construction. A reinforcement bar was welded on, the invoice was settled within a grouped statement of ten items that the administration paid without further inspection, and the City was not informed of the damage.
In the summer or autumn of 1984, he verbally told a municipal councillor that a new inspection of the ceiling void had shown that “everything is in order”. On 26 November 1984, he put it in writing, within a window refurbishment cost estimate: “The construction is in a flawless condition!” The Municipal Council took note of it on 18 December 1984. On 9 May 1985, at 20:25, the slab fell as a single block into the pool: 12 dead, 19 injured or endangered persons.
2. What Swiss law says
The District Court of Uster convicted the three professionals of homicide through negligence (art. 117 CP) and of causing a collapse through negligence (art. 227 no. 2 CP). Only the HTL architect appealed; the Zurich Higher Court confirmed (28 October 1988), the cantonal Court of Cassation dismissed his appeal, and he then applied to the Federal Supreme Court.
What he was blamed for, and what he was not blamed for
Not for failing to recognise stress corrosion cracking: the judges accepted that such knowledge could not be demanded of a construction professional at the time. He was faulted for settling for the most benign explanation when faced with a situation he did not understand, for neither ordering nor having a serious examination carried out, and for failing to inform the authorities. EMPA established that a careful examination of the chamber concerned would have revealed not merely spots, but deposits and pitting due to old rust.
Act or omission?
The Federal Supreme Court corrected the cantonal legal classification: the communication to the City (“construction in a flawless condition”) was an act, not an omission. One who actively gives reassurance cannot hide behind a mere “I did nothing”.
The engineer colleague does not protect
Relying on a “specialist” does not assist someone who ought to have seen that the latter had carried out no serious check; the consulted engineer was neither a steel specialist nor a corrosion expert, and himself denied having any knowledge of metallurgy.
Causation
It suffices that the conduct was, with a high degree of probability, the cause of the outcome. The cantonal judges found, bindingly on the Federal Supreme Court, that the accident would have been avoided by a correct report or by direct recourse to an expert; the collapse was foreseeable and avoidable. The Federal Supreme Court dismissed the grievances: no breach of federal law.
3. What this mistake actually costs
| Item | What the judgment says |
|---|---|
| Lives and injured persons | 12 dead, 19 injured or exposed to immediate danger to their life or integrity |
| Tie rod overload | Safety factor of 1.27 versus at least 1.8 under the applicable SIA standards |
| Duration of the dangerous situation | Years, probably before 1979 |
| Interval between the written note and the disaster | Approximately five and a half months (26 November 1984 → 9 May 1985) |
| Sentence incurred (art. 117 CP, current wording) | Custodial sentence not exceeding three years or a monetary penalty; the published extract does not state the sentence handed down |
For a contractor or an engineering practice, the financial lesson follows the criminal lesson: a certificate of good condition serves as the basis for safety decisions by the client; if it is false, liability traces back to the person who signed it.
4. Field protocol: four reflexes
- A defect whose cause is unknown is not “repaired”, it remains open. Photographs, exact position, adjacent elements checked, all recorded in the site minutes or the site daily log, with the date.
- Bring in the specialist for the material in question. An extra signature in the office is no substitute for the expert in the relevant steel, concrete, or waterproofing.
- Report to the client everything you saw, not just your conclusion. A report that omits an observed fact (here the broken tie rod and the brown spots) remains an act.
- Only write “in order” for what you actually inspected: scope, date, method, limitations. Never slip a safety opinion into a document concerning another subject, such as a window estimate in this case.
Keep a record of what was observed. The guide Site minutes, daily log and evidential value explains how to record a finding in a usable manner; the dossier criminal liability on site (art. 229 CP) outlines where the delegation of safety ends.
5. Frequently asked practical questions about this case
Was he convicted for failing to recognise stress corrosion cracking?
No. The judges accepted that this knowledge was not required of a building professional at the time. They faulted him for settling for the most benign explanation without thorough examination, and for reassuring the client instead of informing them of his findings.
Does a hasty conclusion in good faith rule out negligence?
Not if the doubt was apparent. According to the judgment, even a false conclusion drawn lightly from the observed damage required further examination or notification of the authority, as other similar damage could not be ruled out. The fault lay in the absence of investigation.
Does relying on an engineer colleague provide protection?
Not if one can see that the inspection was not serious. The Federal Supreme Court confirmed that calling upon a “specialist” does not protect someone who ought to have noticed that the latter carried out no genuine check and was neither a steel specialist nor a corrosion expert.
Official sources
- ATF 115 IV 199 (judgment of the Criminal Court of Cassation of 13 November 1989) — Federal Supreme Court
- Swiss Criminal Code, arts. 117 and 227 — Fedlex
Compliance notice. This article is a technical and educational analysis based on Swiss law in force and published decisions; the parties are anonymised as in the judgments. It does not replace the advice of a specialist lawyer for an ongoing dispute. Art Construction is independent of the SIA and CRB: their standards are not reproduced. Legal texts and judgments reviewed on 18 November 2026. This version is an automatic translation of the French article, which remains the authoritative text in the event of any discrepancy.