Notice of defects: the 60-day deadline in force since 1 January 2026 (Art. 367 CO)
· 9 min read
Financial stake All your warranty rights regarding a defect: remediation, reduction in price, damages. In the leading case (ATF 118 II 142): CHF 20'563.90 claimed in total, for unfinished works and damaged timber facades.
Legal basis Art. 367 para. 1bis, 368 para. 2bis, 370 para. 4 and 371 para. 3 CO (Swiss Code of Obligations); Art. 839 para. 3 CC (Swiss Civil Code). "Construction Defects" Act (RO 2025 270), in force since 1 January 2026.
Fatal error Applying the 60-day time limit to a contract signed before 2026 — or, under the former law, waiting five weeks before writing.
Immediate countermeasure Write within the week following each discovery, and record for each site whether the contract dates from before or after 1 January 2026.
1. The facts: five weeks to write a letter
In 1982, a purchaser acquired a plot of land with a house still under construction, for a global price of CHF 430'000. The land and the construction were not priced separately: the Federal Supreme Court regarded this as a mixed contract (sale and contract for work and services) and applied the contractor's warranty for defects under Art. 368 et seq. CO to the building.
The house was not completed on the agreed date, 1 October 1982: the purchaser waived the remaining works and entrusted them to third parties. Then, in the winter of 1985/86, the timber facades warped: the boards buckled, the paint flaked. Returning from a skiing holiday, he noticed the damage on 17 January 1986 at the earliest, and wrote to the seller on 24 February. The seller did not respond. The purchaser obtained an order for taking of evidence for future use before the district court, had the facades repaired by a third party, then claimed a total of CHF 20'563.90, including unfinished works. The cantonal judges largely found in his favour: CHF 19'981.40, with 5% interest.
The Federal Supreme Court set aside that judgment. A notice given five weeks after discovery is late; it recalled that, in an earlier judgment (ATF 107 II 176), a complaint sent about three weeks after the discovery of water ingress had already been held to be late. The case was remitted to Aargau to determine the exact date of discovery.
2. What Swiss law says, before and since 2026
Before 1 January 2026: "immediately"
Art. 367 para. 1 CO requires the employer to examine the work "as soon as feasible in the normal course of business". Art. 370 para. 3 CO requires, for defects that become apparent only later, a notice "immediately" after their discovery; otherwise, the work is deemed accepted with its defects. The statute specifies no number of days.
The Federal Supreme Court therefore judges on a case-by-case basis. The time limit is short where waiting risks worsening the damage; a brief period for reflection remains permissible. For defects that appear gradually, discovery is only established when their serious nature becomes clear. And the burden of proof rests on the employer: it is up to him to prove that his notice was dispatched on time, including the date of discovery.
Since 1 January 2026: 60 days for an immovable work
- Art. 367 para. 1bis CO: the employer has 60 days to give notice of defects in an immovable work. Any agreement imposing a shorter deadline is void.
- Art. 370 para. 4 CO: for defects that could not be detected during inspection and acceptance, 60 days from discovery.
- Same rules for defects in a movable work incorporated into the building, and for those in an architect's or engineer's plan used as a basis for the construction, where they give rise to the defects in the immovable work.
- Art. 368 para. 2bis CO: any clause agreed in advance that restricts or excludes the right to remediation is void if the defect relates to a construction.
- Art. 371 para. 3 CO: the five-year limitation period cannot be shortened to the detriment of the employer.
What the statute does not settle: earlier contracts
The statute contains no transitional provisions: one finds only the referendum clause and the date of entry into force, nothing else. In the absence of an express rule, the cautious interpretation — the one we recommend following until a ruling has decided the issue — is that the law in force upon conclusion of the contract continues to apply. A contract signed in 2025 thus remains subject to the "immediately" notice requirement, with its five-week risk.
The same reform affects statutory charges on immovable property (contractor's liens): to avert registration, the security offered by the owner must cover default interest for ten years (Art. 839 para. 3 CC).
3. What this mistake actually costs
| Item | What the judgment says |
|---|---|
| Claim at stake | CHF 20'563.90 claimed (completion of works and remediation of facades); CHF 19'981.40 plus 5% awarded by the cantonal judges before the annulment. The published extract does not break down the share for the facades. |
| Timeframe in question | 38 days between the earliest possible discovery (17 January 1986) and the letter (24 February 1986) |
| Duration of proceedings | Claim lodged in December 1987, cantonal appeal judgment of 27 December 1990, then appeal to the Federal Supreme Court |
| Burden of proof | On the purchaser: he must establish the date of discovery and the promptness of his notice |
The sum is not huge; it is the mechanics that matter. For an SME, remediation that the client can no longer claim or, conversely, a late notice that releases the contractor, has an immediate effect on the project's net margin.
4. Site protocol: four reflexes
- Date the discovery. Timestamped photograph, email sent to yourself, entry in the site diary. The burden of proving the date rests on whoever invokes the warranty.
- Write within the week, not on the 59th day. Registered letter and email, with a factual description (where, what, since when) and a demand for remediation. The statutory time limit is a ceiling, not a target; if the defect may worsen, case law expects notice to be given even faster.
- Sort your contracts by signing date. A column "before / from 1 January 2026" in your site register. For earlier contracts, work as if "immediately" applies.
- Review your terms and standard forms. A clause providing for less than 60 days, or excluding remediation of a construction in advance, is void for contracts governed by the new law: replace it.
Compare both regimes side by side. The SIA 118 / CO 2026 comparator from Art Construction provides a point-by-point comparison between the standard SIA 118 (Swiss Society of Engineers and Architects) and the revised CO: time limits, burden of proof, warranties. The complete table of warranties and the rejection letter can be found in the dossier on warranties for defects and limitation periods; for site practice, read the guide on the 2-year warranty period (SIA 118) versus 60 days (CO).
5. Frequently asked practical questions about this case
Does the 60-day period apply to my contract signed in 2025?
Probably not. The statute contains no specific transitional provision, and the cautious reading is that the law in force when the contract was signed continues to apply. As a precaution, a 2025 contract therefore remains subject to the "immediately" notice requirement. Have the situation checked by a legal professional if significant interests are at stake.
From what point do the 60 days start to run?
For defects that could not be detected during inspection and acceptance, Art. 370 para. 4 CO causes them to run from discovery. For patent defects, Art. 367 para. 1bis does not specify a starting point: it links back to the inspection of the delivered work, which must be carried out immediately (Art. 367 para. 1).
Is a simple email enough to give notice of a defect?
Art. 367 and 370 CO do not require any specific form. An email is therefore possible, but you bear the burden of proving transmission and date. Back it up with a registered letter and retain the postal slip. If your contract incorporates standard SIA 118, check the formal requirements it provides for notices.
Official sources
- Federal Act of 20 December 2024 (Construction Defects), RO 2025 270 — Fedlex
- Code of Obligations, Art. 367, 368, 370 and 371 (as of 1 October 2026) — Fedlex
- ATF 118 II 142 — Federal Supreme Court
Compliance notice. This article is a technical and educational analysis based on Swiss law in force and published decisions; the parties are anonymised as in the judgments. It does not replace the advice of a specialist lawyer for an ongoing dispute. Art Construction is independent of the SIA and CRB: their standards are not reproduced. Legal texts and judgments reviewed on 18 November 2026. This version is an automatic translation of the French article, which remains the authoritative text in the event of any discrepancy.