Heat Pump in the Wrong Location: Removal Confirmed Even Below Planning Values (ATF 141 II 476)
· 8 min read
Financial stakes The removal of an already installed heat pump, and its relocation. The amount is not stated in the judgment; the measurement in question: 49 dB(A) at the first-floor window, for a night-time planning value of 50 dB(A).
Legal basis ATF 141 II 476; Art. 11 para. 2 and Art. 25 para. 1 of the Federal Act on the Protection of the Environment (LPE); Art. 7 para. 1 let. a and b of the Noise Abatement Ordinance (OPB).
Fatal mistake Installing the heat pump somewhere other than where the permit stipulated, then attempting to regularise it with noise barriers and acoustic hoods.
Immediate workaround Choose the quietest location before installing, and never change it without a new permit.
1. The facts: one permit, another location
On 12 May 2009, a Valais municipality granted permission for the construction of a residential building on a plot with sensitivity level III. The permit required technical installations to comply with noise legislation and demanded an acoustic report before the start of works. The approved plans showed the heat pump inside the building.
The pump was ultimately installed outside. On 15 November 2010, the owner of a neighbouring built plot located approximately 40 m away complained. On 22 November, the developer filed an application for authorisation, including a 1.80 m by 1.80 m acoustic baffle. The neighbour opposed it.
The municipality refused the permit on 8 February 2011: installation without prior authorisation and failure to comply with planning values. The Council of State overturned this and remanded the case so that a demolition order could be issued under cantonal law. Remediation measures were carried out in September 2012: a timer limiting operating hours, a modified hood, three acoustic screens. Insufficient, according to the municipality, which ordered the removal on 27 November 2012. The Council of State dismissed the main parts of the appeal; the Cantonal Court confirmed on 19 December 2014. The developer and an Sàrl owning two condominium units took the matter to the Federal Supreme Court.
2. What Swiss law says
An outdoor heat pump is a new stationary installation. It may only be erected if the noise it produces at the neighbour's property does not exceed the planning values of the OPB (Art. 25 para. 1 LPE, Art. 7 para. 1 let. b OPB). But that is only the first condition. In addition, emissions at source must be limited by preventive measures, as far as technically and operationally feasible and economically bearable (Art. 11 para. 2 LPE, Art. 7 para. 1 let. a OPB).
Both requirements apply cumulatively. Planning values are not emission limit values: complying with them does not prove that all preventive measures have been taken. The principle of prevention requires noise to be taken into account as early as the selection of the location; it dictates choosing the quietest location.
Why the developer lost
The Federal Supreme Court acknowledged that, short of demolition, every conceivable technical measure had been taken, in accordance with the enforcement aid from Cercle Bruit for air/water heat pumps, and that further alterations might even risk creating resonance. This did not save the installation: by positioning the unit without legal right, at the location of their choice and without demonstrating that this location minimised noise, the developers confronted the authority with a fait accompli and prevented it from applying the principle of prevention. They cannot invoke the technical impossibility of further reducing noise, since that impossibility stems from their unlawful choice. Other solutions were preferable, notably an indoor installation as originally authorised, which they did not claim to be technically unfeasible or economically unviable.
The Federal Supreme Court dismissed the appeal. It did not have to decide whether planning values were exceeded on the undeveloped plot situated between the two buildings.
3. How much this mistake actually costs
| Item | What the judgment states |
|---|---|
| Measured level | 49 dB(A) at the first-floor window, for a night-time planning value of 50 dB(A) (sensitivity level III) |
| Distance to neighbour | Approximately 40 m |
| Measures taken (September 2012) | Limiting timer, modified hood, three acoustic barriers: weak improvement on the first floor |
| Baffle proposed in 2010 | 1.80 m by 1.80 m |
| Duration | From the complaint (15 November 2010) to the cantonal judgment (19 December 2014): over four years, then an appeal to the Federal Supreme Court |
| Outcome | Removal order of 27 November 2012 confirmed |
The direct cost is not published, but can be deduced: the unit, its connections, the noise barriers, acoustic assessments, removal, then the replacement installation at the location planned originally.
4. Site protocol: four habits
- Respect the location on the permit. If the heat pump is planned inside, do not place it outside without a new permit application: a change of location is a new project.
- Carry out the noise study beforehand, comparing at least two locations. The judgment requires the choice of location to be analysed from the perspective of prevention; it is better to prove this before rather than after.
- Do not aim for "just below the limit". Complying with a planning value is not a clearance certificate. Move the source further away from sensitive rooms, or select a quieter unit: according to the cited enforcement aid, these are the only two measures left once the installation is already erected.
- If the neighbour complains, do not simply add acoustic enclosures hoping to regularise the unit. Prepare the relocation to the quietest spot: that is what the authority will demand.
Check before installing. The SIA 181 acoustic checker and Cercle Bruit simulator for heat pumps estimates the sound level of a heat pump; the acoustic memo and validation guide for heat pump noise compiles the requirements. The guide on soil protection, noise (OPB) and air (OPair) places the topic in the context of the construction site.
5. Frequently asked practical questions about this case
Is complying with the planning value sufficient?
No. According to the Federal Supreme Court, planning values and the principle of prevention apply cumulatively. Even below the planning value, the authority can require emissions to be reduced as long as it is technically and economically feasible, in particular by selecting the quietest location.
Can a heat pump installed without a permit be regularised by arguing that further noise reduction is impossible?
Not in this case. The Federal Supreme Court noted that the technical impossibility of further measures stemmed precisely from the unlawful choice of location. The developers did not claim that an indoor installation, as originally authorised, was unfeasible or too costly. The removal order was confirmed.
Which measures were judged insufficient?
A timer limiting operating hours, a modified hood, and three acoustic barriers, completed in September 2012, only weakly improved the situation: at the first-floor window, 49 dB(A) was still measured against a night-time planning value of 50 dB(A).
Official sources
Compliance notice. This article is a technical and educational analysis based on Swiss law in force and published decisions; the parties are anonymised as in the judgments. It does not replace the advice of a specialist lawyer for an ongoing dispute. Art Construction is independent of the SIA and CRB: their standards are not reproduced. Legal texts and judgments reviewed on 18 November 2026. This version is an automatic translation of the French article, which remains the authoritative text in the event of any discrepancy.