Why a site loses money without anyone seeing it
A quotation sets a budget: so many hours, so much material, a share of subcontracting. The site produces variances every day: an extra hour on an unforeseen substrate, a material bought again, a job requested on the spot. Recorded at the end of the week or at the close, these variances can no longer be corrected.
Daywork is the most fragile spot: work carried out at the request of the client or of the site supervision is invoiced without friction if there is a dated, signed report. The later the signature is requested, the harder the discussion.
- Hours recorded on paper, entered at the office at the end of the week.
- Daywork sheets not signed before the crew leaves.
- Purchases not attached to the site, found again when the invoices arrive.
- Variations accepted verbally, never confirmed in writing.
Hours also sit within a framework: the collective labour agreement (CCT) applicable to the company defines, among other things, working time. This page does not interpret it; it starts from a simple principle: an hour that is recorded and attached to a site is easier to check. To explore the effect of a CCT, try the HR and CCT simulator.
What the ERP attaches to the site
The Art Construction ERP, hosted in Switzerland, brings quotations, sites, invoices and teams together. The functions below correspond to the Support guides and to the Daywork module in service.
Hours recorded on a phone
Teams record their time from the phone; the site manager finds the hours attached to the site. The hours export makes it possible to pass them on, for example to the accountant.
Signed daywork sheets
The sheet is filled in on the phone and signed electronically: the signature is recorded with the date, time and name. Daywork rates and site photos are part of the same module.
Variations and additional work
Variations keep their history, so that additional or omitted work can be confirmed in writing before it is carried out.
Costs and purchases per site
Hours, purchases, purchase orders and supplier invoices are attached to the site, to compare actual figures with the quotation.
For the rest of the circuit, from interim payment to final account, see the page construction invoicing: progress invoices and QR-bill.
Three steps to know where you stand before the site ends
Tracking starts from the quotation, which provides the budget against which everything else is compared.
Step 1: start from the quotation
Create the quotation, open the site, then check the daywork rates. The budget in hours and purchases becomes the reference for comparison.
Step 2: record, sign, attach
The team records its hours on the phone. Any daywork is signed before leaving the site. Purchases and variations are attached to the same site as soon as they are entered.
Step 3: compare as the site progresses
The site manager compares the attached costs with the quotation and spots a variance while it can still be corrected, then invoices daywork and variations. The hours export and the PDF documents go to the accountant.
Paper, accounting software or construction ERP: where the tracking lives
Paper and spreadsheets have the advantage of simplicity; general-purpose accounting software is the benchmark for accounting. The table compares what a company tracks on a site and where that tracking lives; a product’s functions depend on its plan and should be checked with the vendor.
| Data to track | Paper folder and spreadsheet | General-purpose accounting software | Art Construction ERP for construction |
|---|---|---|---|
| Team hours | Sheets to re-enter at the office | Depends on the product and plan | Phone time recording, hours export |
| Signed daywork | Signed paper daywork book | Check with the vendor | Electronically signed daywork sheet (date, time, name) |
| Comparison with the quotation budget | Manual calculation in a spreadsheet | Depends on the product and plan | Costs attached to the site, compared with the quotation |
| Purchases and supplier invoices | Manual attachment to the site | Strength: entering and paying invoices | Purchases, purchase orders and invoices per site |
| Variations and additional work | Separate letters and files | Check with the vendor | Variations with history |
Comparison of categories of tools, non-exhaustive. Any brands mentioned belong to their owners; check functions and prices with each vendor.
14-day trial, starting price and limits
The trial lasts 14 days, with no card required: at the end, nothing is charged. The ERP starts at CHF 39 per month, excl. VAT (Starter plan: 1 user, 5 GB, 13 modules out of 36); the Pro plan costs CHF 99 and the Business plan CHF 189, with Portail included. The price is per company, not per user. The modules included depend on the plan: see the plans page.
Frequently asked questions
How can I tell whether a site is profitable before it ends?
Attach recorded hours, daywork sheets, purchases and variations to the site, then compare them with the quotation at regular intervals, for example every week. The ERP groups this data per site: a variance spotted is discussed with the team while the works are under way. The accounting interpretation remains with the accountant.
Why have the daywork sheet signed before leaving the site?
Because the work, the time spent and the date are known at that moment, and the person who can sign is still on site. In the ERP, the sheet is signed electronically on a phone; the signature is recorded with the date, time and name. The value of a document in a dispute depends on the circumstances: it is not a legal guarantee.
Does the ERP apply my CCT rules to the hours entered?
This is not presented as a function of the ERP. It records hours per site and lets you export them; applying a collective labour agreement (working time, supplements) remains the company’s responsibility and, if needed, the accountant’s. A simulator with no registration helps explore these rules: the HR and CCT studio.
What is the difference between the cost of an hour and the daywork rate?
The daywork rate is the price charged to the client for an hour. The cost of an hour includes salary, social charges and a share of overheads; the gap between the two is the margin on daywork. The ERP manages daywork rates. To estimate the cost of an hour, try the worker cost and daywork rate simulator.