SIA 118 · Art. 47 Tool 3.4 Online

Daywork Report Generator (Art. 47 SIA 118) & Billing Calculator

Generate your daywork reports, calculate hourly surcharges and track the deadlines of Article 47.

Interactive tool

Deadlines under Article 47 SIA 118

Report to be drawn up and signed
Each day of execution (Art. 47 para. 1)
Return of the copies signed by the site management (D + 7)
—
Any discrepancies to be settled no later than (1 month)
—

Labour

Hours by qualification, daywork rate and hourly surcharge
QualificationHoursDaywork rate (CHF/h)Hourly surchargeAmount (CHF)
Team leader
Cl. CE / Team leader / Chief fitter
0.00
Skilled worker CFC
Cl. Q / Cl. A / Cat. A
0.00
Labourer
Cl. B / Cl. C
0.00
Apprentice (2nd year)
Apprentice CFC
0.00

Materials and supplies

Hired machines and tools (hours × hourly price)

%
%
Labour hours
0 h
Labour
0.00
Materials
0.00
Machines
0.00
Gross total excl. TVA (HT)
0.00
Discount
0.00
Net total excl. TVA (HT)
0.00
TVA
0.00
Total incl. TVA (TTC, CHF)
0.00

Daywork rates prefilled with the ACIP 2026 average for the chosen sector (editable). The surcharges (+25%, +50%, +100%) are examples of common practice: apply those of your collective agreement, only if they were actually paid (Art. 51 SIA 118). A discount on fixed prices applies to daywork only if it was agreed (Art. 54).

Embed this calculator on a website page

Paste this code into the page, or write [outil code="3.4"] in the content of a page on the site.

📄 Files and templates linked to this tool (free)

Move from calculation to full management

Keep your references at hand, then automate them in your quotes, bids and final statements.

⚡ Automate this calculation in our ERP / Soumission software (Trial)

Technical reference guide

The golden rules of daywork under Articles 44 to 57 of the SIA 118 standard

Daywork SIA 118 Art. 47 to 57 is paid according to the hours and materials actually used (Art. 48), at the rate agreed in the contract or, failing that, at the rate of the trade associations in force at the place and time of the work (Art. 49). Daywork is provided for in the contract or ordered by the site management (Art. 44); without an order, it may be carried out only with its consent, except in an emergency (Art. 45). A good Swiss construction site daywork report template is the best proof of what was done: the tool above generates one.

1. Obligation to draw up a daily daywork report (Art. 47 SIA 118) and hand it to the site management within 7 days

The contractor draws up and signs a report on the daywork every day, kept available to the site management in the agreed number of copies; it lists the number of workers, the machine and labour hours and the materials used, and describes the work done (Art. 47 para. 1). Hand it to the site management the same day or the next: the seven-day period of Art. 47 para. 2 is the one within which the site management must return the signed copies.

Minimum content of a report: site and date, names of the workers and hours by qualification, machines and tools, materials, description of the work, order received (who gave it and when), signature of the contractor and endorsement of the site management.

2. What does the signature of the site manager (DT) on the daywork slip mean legally? (Acknowledgement of hours and materials + 30-day review period)

On the signature daywork slip site management 7-day period: the site management examines each report without delay and returns the signed copies within seven days; it notes any discrepancies on the reports and specifies their subject; these discrepancies are dealt with within one month (Art. 47 para. 2 and 3). The endorsement certifies that the details have been examined; the recorded discrepancies remain to be settled. The standard does not say that the site management's silence amounts to acknowledgement of the hours: follow up in writing if the report does not come back signed.

As for the daywork invoice dispute 30-day period, the daywork invoice is submitted every month, the claim falls due upon submission, without retention (Art. 55 and 149 para. 2), and the client must pay it within 30 days (Art. 190 para. 1): it is within this period that objections must in practice be raised.

How to price hourly surcharges (evening, night, Saturday, Sunday work) and tools in daywork

Daywork prices include wages and wage-related costs, personal tools, storage and site services, materials, overheads, and risk and profit (Art. 50). They are increased if the workers received wage supplements provided for by law or a collective agreement and actually paid: overtime, shift work, night work, Saturday, Sunday, public holidays, travel, bad weather (Art. 51).

Example of hourly surcharges on a daywork rate of 108.00 CHF
SituationSurcharge (usage example)Hourly daywork rate
Normal hours+0 %108.00 CHF
Overtime / Saturday+25 %135.00 CHF
Night work+50 %162.00 CHF
Sundays and public holidays+100 %216.00 CHF

Average ACIP 2026 daywork rate for a CFC-qualified skilled worker in structural work (108.00 CHF/h). The percentages are examples: apply those of your collective agreement, only if they were paid.

  • Tools and site installations: if installations already provided for under separate items of the bill of quantities are used for daywork, the daywork price includes only their operating and routine repair costs; if they are used for longer than planned, the extension is added (Art. 52).
  • Discount on the daywork rate: unless otherwise agreed, the discount granted on fixed prices does not apply to daywork; an agreed cash discount does apply (Art. 54).
  • Indicative estimate: if it is at risk of being exceeded, notify the client without delay (Art. 56 para. 3); price escalation applies to this work only if it was agreed (Art. 56 para. 4; see the price escalation calculator).

For quantities that vary on a unit-price item, see the change-order calculator (Art. 86 SIA 118). ⚡ Enter your reports in Soumission

Frequently Asked Questions on Invoicing Daywork (FAQ)

1. Is the daywork report mandatory?

Yes: for daywork, the contractor draws up and signs a report every day, kept available to the site management in the agreed number of copies (Art. 47 para. 1 SIA 118). It lists the number of workers engaged, the machine and labour hours and the materials used, and describes the work done.

Without a signed report, the daywork invoice will be hard to defend. Daywork not provided for in the contract may in principle be carried out only with the consent of the site management (Art. 45).

2. Within what period must the site management sign the report?

The site management examines each report without delay and returns the duly signed copies to the contractor within seven days (Art. 47 para. 2). It notes any discrepancies on the reports and specifies their subject; these discrepancies are dealt with within one month (Art. 47 para. 3).

The standard does not provide that the site management's silence amounts to acknowledgement of the hours: follow up in writing if the signed copies do not come back within seven days.

3. Can surcharges be invoiced for night, Saturday or Sunday work?

Yes, if these surcharges correspond to the law or a collective agreement and were actually paid to the workers: daywork prices are then increased (Art. 51 SIA 118). Daywork prices already include wages and related costs, personal tools, overheads, risk and profit (Art. 50).

The tool's surcharges (+25%, +50% and +100%) are examples of common practice: apply those of your collective agreement. The discount agreed on fixed prices does not apply to daywork unless otherwise agreed; the cash discount does apply (Art. 54).

4. When and how should daywork be invoiced, and what period applies for disputing the invoice?

The contractor submits the daywork invoices to the site management every month; the claim falls due at that moment, without retention (Art. 55 and 149 para. 2). The client pays within 30 days (Art. 190 para. 1): it is within this period that it must raise its objections. The discrepancies noted on the reports are dealt with within one month (Art. 47 para. 3).

Attach the signed reports to the invoice and, if you submitted an indicative estimate, stick to it: if it is at risk of being exceeded, notify the client without delay (Art. 56 para. 3).

Indicative information drawn up from the text of the SIA 118 standard (2013 edition); the particular conditions of the contract may modify these rules.