In the workshop as on site, waste costs twice: material bought and then thrown away, and time spent looking for a bar that is long enough. Cutting in the order of the cutting list often leaves remnants too short to use, and the next order starts again on new bars while the yard already holds some.
The cut optimisation and panel layout module is built into the Art Construction ERP: it is not offered as a public tool. It handles two cases: cutting bars in one dimension (sections, reinforcement, timber, in millimetres, with saw kerf and mitre cuts) and laying out panels in two dimensions (with grain direction and rotation allowed or not). Each calculation ends with a feasibility check, dimensioned cutting diagrams and the list of new bars and panels to order.
Worked example: a set of 30 parts in 6 m bars
A workshop frame needs 6 uprights of 2450 mm, 8 rails of 1180 mm, 10 spacers of 760 mm and 6 braces of 430 mm, i.e. 30 parts and 34.32 m of useful length. Stock is new bars of 6000 mm, and the saw kerf is 3 mm (the module's starting value, editable). Example values, to be replaced by your own cutting list.
| Bar | Parts cut (mm) | Length of parts (mm) | Remaining offcut (mm) |
|---|---|---|---|
| 1 | 2450 + 2450 + 760 | 5660 | 334 |
| 2 | 2450 + 2450 + 760 | 5660 | 334 |
| 3 | 2450 + 2450 + 760 | 5660 | 334 |
| 4 | 5 × 1180 | 5900 | 88 |
| 5 | 3 × 1180 + 3 × 760 | 5820 | 165 |
| 6 | 4 × 760 + 6 × 430 | 5620 | 353 |
| Total | 30 parts | 34 320 | 1608 (+ 72 of saw kerfs) |
Cut in the order of the list, the same parts need 7 bars: three bars with two uprights each (1097 mm left on each), then the rails, spacers and braces one after another, the last bar carrying only five braces. You buy 42.00 m for 34.32 m of parts: the waste rate on new material reaches 18.3 %. With the module's quick method (parts are sorted from longest to shortest, then placed in the first bar where they fit, and the best of several variants is kept), 6 bars are enough: 36.00 m bought, waste rate 4.7 %. Check: 34 320 mm of parts + 1608 mm of remnants + 24 saw kerfs of 3 mm (72 mm) = 36 000 mm.
One 6 m bar less on this single set, i.e. 14.3 % less new material. In the unoptimised plan, the 3838 mm left on the seventh bar could have gone into the offcut stock; the module does exactly that, storing offcuts from a chosen length (500 mm by default) and using them first in the next calculation.
In this example, the optimised plan buys 6 bars instead of 7 and brings the waste rate down from 18.3 % to 4.7 %.
3 common margin losses without an optimised cutting plan
Cutting in the order of the cutting list
The list follows the drawing, not the bar: long parts leave medium remnants that nobody uses, and one more bar is needed at the end of the run. The example above loses a whole bar this way on 30 parts.
Forgetting the saw kerf and the mitres
Every cut removes a few millimetres, and a mitre cut lengthens the part by the width of the section multiplied by the tangent of the angle. If these are ignored, a part worked out as an exact fit no longer fits in the bar when it is time to cut.
Buying new while offcuts sit in the yard
Without an inventory of reusable offcuts, every order starts again on new bars and panels. The module keeps the offcut stock with the set of parts and uses it first; for panels it also respects the grain direction so that a veneered board is not spoilt.
The module in the ERP in 3 steps
- Enter or paste the cutting list
In the ERP, open the module and enter the parts (description, material, length, quantity, mitre angles) and the stock of bars or panels; several rows can be pasted from Excel. Set the saw kerf, the end trim or the edge trimming of panels. - Calculate and check the plan
Choose the method: quick, or exact for a small number of parts; for panels, guillotine for a panel saw or dense placement for a CNC machine. The module shows the waste rate, the dimensioned cutting diagrams and the result of the feasibility check. - Update the offcuts and order
Add the reusable offcuts to the stock, export the order list as CSV or print the cutting plan as PDF. The set of parts is saved on the site with its versions, and suggested items from the ACIP database help to cost the material.
What the module does not do
Results are indicative: they depend on your entries and must be checked before cutting. The module does not drive any cutting machine and does not import any drawing file; it does not account for nesting mitres head to tail, which keeps the result on the safe side. The prices in the order list are the ones you enter or take over from an ACIP suggestion after your click.
The module is part of the Art Construction ERP: there is no public version. Starting lengths and areas can come from a take-off on a drawing: see the take-off guides of the Take-Off studio for drylining, tiling and roof structures. To cost a bid from quantities, Soumissions takes over your items with the price database and files per site.
Frequently asked questions
Is the cutting plan always the best possible one?
The quick method gives a good result without proof that it is optimal. The exact method looks for the best solution for a small number of parts and stops at the set time limit, keeping the best solution found; in each case the module states which one was used.
How does the module count a mitre cut?
It adds to the part the length lost by the mitre, equal to the width of the section multiplied by the tangent of the angle, and counts the saw kerf at an angle. You state which edge the length was measured on: the reference edge or the opposite edge.
Is the grain direction of panels respected?
Yes: on a grained panel, a part whose rotation is not allowed keeps its length along the length of the panel. On an ungrained panel, parts may be turned by 90 degrees to fill the board better.
Where are the offcuts and the order kept?
Reusable offcuts go into the stock of the set of parts, saved on the site in the ERP, and are used first in the next calculation. The list of new bars and panels to buy can be exported as CSV or printed with the cutting plan.