On a roof, what the plan shows and what is actually laid are two different things. The roof plan is a view from above: it gives the projected area, whereas the roofer, the carpenter and the sheet metal worker all work along the slope.
The Take-Off & Métré studio opens the PDF plan in the browser, without uploading the file, and measures in plan. You draw each roof slope as a polygon area, measure ridges and gutters as cumulative lengths and count the downpipes with numbered markers. You then work out the sloping area yourself: projected area divided by the cosine of the pitch. Layers with the codes CFC 214, 222 and 224.
Worked example: roofing and sheet metal take-off for a duo-pitch roof
A house in French-speaking Switzerland, roof plan at 1:100. The roof with two symmetrical slopes measures 12.40 m by 9.60 m in plan, eaves overhangs included, with a pitch of 35 degrees. The cosine of 35 degrees is 0.8192. Each slope is 4.80 m wide in plan.
| Item | Measured in plan | Correction | Quantity |
|---|---|---|---|
| Projected area | 12.40 × 9.60 m | none | 119.04 m² |
| Sloping area | 119.04 m² | ÷ 0.8192 | 145.31 m² |
| Ridge | 12.40 m | none | 12.40 m |
| Gutters | 2 × 12.40 m | none | 24.80 m |
| Verges | 4 × 4.80 m | ÷ 0.8192 | 23.44 m |
| Downpipes | 4 markers | count | 4 pcs |
The two slopes drawn in plan give 12.40 × 9.60 = 119.04 m². The area actually covered follows the slope: 119.04 ÷ 0.8192 = 145.31 m², which is 26.27 m² or 22% more. The ridge and the gutters, being horizontal, are read without correction. Each verge measures 4.80 m in plan, so 4.80 ÷ 0.8192 = 5.86 m in true length, and 23.44 m for the four.
The pitch is read from the section: the roof plan does not give it. Roof covering and battens apply to 145.31 m²; the rafters are derived from the sloping length of 5.86 m and their spacing. Allowances for laps and waste must be confirmed against the specification and the measurement practice of the trade.
For this roof, the take-off gives 119.04 m² in plan but 145.31 m² of roof covering, 23.44 m of verges, 24.80 m of gutters, 12.40 m of ridge and 4 downpipes.
3 common mistakes in a carpentry, roofing and sheet metal take-off
Pricing the roof covering on the projected area
This is the most expensive mistake: in the example, it makes 26.27 m² of tiles, battens and labour vanish. State in each description whether the area is projected or sloping.
Applying the pitch factor to horizontal items
The ridge and the gutters are horizontal and are measured at true length on the plan. Only the items that follow the slope, such as verges and rafters, need the correction.
Forgetting eaves overhangs, dormers and penetrations
The floor plan stops at the face of the walls; the roof goes further: draw the slopes on the roof plan, overhangs included. Dormers, chimneys and rooflights add sheet metal flashings.
How to do a roofing and sheet metal take-off in 3 steps
- Open the roof plan and set the scale
Drop the PDF roof plan into the studio. Calibrate the scale on a known dimension, or choose 1:100 if the document has not been resized. Read the pitch from the section. - Draw the slopes, measure the lines, count the items
In CFC 214, 222 and 224 layers, draw each slope as a polygon area. Measure the ridge, the gutters and the verges as cumulative lengths. Place a marker on each downpipe, rooflight or roof outlet. - Export and correct for the pitch
Export the summary table to CSV. In your spreadsheet, divide the projected areas and the verge lengths by the cosine of the pitch, and leave the ridge and the gutters as they are.
What the free version does not do for a roof take-off
The studio measures in plan and does not know the pitch: it calculates neither the sloping area nor the true length of verges, valleys and hips. Nothing is saved: closing the tab erases the take-off. The only free export is CSV, with the Art Construction notice.
Soumissions takes the quantities into the items of a quote, with the price database and one file per site. Plans Pro (2D/3D) saves layers and measurements site by site, allows teamwork and exports without a watermark.
Frequently asked questions
How do you go from the projected area to the sloping area of a roof?
Divide the area measured in plan by the cosine of the pitch. For 35 degrees, the cosine is 0.8192: 119.04 m² projected corresponds to 145.31 m² along the slope.
Can gutters and verges be measured on a PDF plan?
Yes, as cumulative lengths. Gutters and the ridge are horizontal: their length in plan is the real length. Verges follow the slope: divide the length read by the cosine of the pitch.
Does the studio calculate the number of tiles or rafters?
No. It gives areas, lengths and counts. The number of tiles is derived from the sloping area and the manufacturer's data; the number of rafters, from the length of the building and the spacing.
How do you count downpipes and roof outlets?
Use the unit counter: place a numbered marker on each item and assign it to a category. The summary table shows the number per category.