Take-off for plastering, drylining and painting (CFC 271 / 285) from a PDF plan

Measure the perimeter of each room on the PDF plan to obtain wall and ceiling areas, then set the rule for deducting openings.

Open the free studio →

Free, no account: your files stay in your browser.

Plasterers and painters price vertical surfaces that the plan does not show: it only gives perimeters and a ceiling height. What remains is deciding how to treat doors, windows and glazed openings.

The Take-Off & Métré studio opens the PDF plan in the browser; the file never leaves your computer. You draw the outline of each room: the studio gives the perimeter, the floor area, which also serves for the ceiling, and the wall area, perimeter multiplied by the height you enter. The lines go into layers with the codes CFC 271 and CFC 285.

Worked example: painting and plastering take-off for a three-room flat

Renovation of a flat in French-speaking Switzerland, plan at 1:50, ceiling height 2.50 m. To be skimmed and painted: a living room and two bedrooms. A door is 1.80 m² (0.90 × 2.00 m), a bedroom window 1.68 m² (1.20 × 1.40 m), the glazed opening in the living room 5.04 m² (2.40 × 2.10 m).

Wall and ceiling areas measured on the PDF plan, all openings deducted
RoomPerimeterGross wallsOpeningsNet walls
Living room19.60 m49.00 m²6.84 m²42.16 m²
Bedroom 114.20 m35.50 m²3.48 m²32.02 m²
Bedroom 213.40 m33.50 m²3.48 m²30.02 m²
Total47.20 m118.00 m²13.80 m²104.20 m²

The living room has a perimeter of 19.60 m: at a height of 2.50 m, that is 49.00 m² of gross walls. Take away the glazed opening of 5.04 m² and one door of 1.80 m², 6.84 m² in all; 42.16 m² remain. Each bedroom loses a window and a door, i.e. 3.48 m². Total net walls: 104.20 m². The ceilings take the floor areas: 23.40 + 12.10 + 10.80 = 46.30 m².

Everything then depends on the deduction rule. With a threshold of 2.50 m², only the living-room opening is deducted: 118.00 − 5.04 = 112.96 m², which is 8.76 m² more and covers the work on the reveals. The rule must be confirmed against the specification and the measurement practice of the trade.

For these three rooms, the take-off gives 104.20 m² of net walls and 46.30 m² of ceilings, or 112.96 m² of walls with a deduction threshold of 2.50 m².

3 common mistakes in a plastering and painting take-off

Taking the floor area for the wall area

The area written in each room applies to the ceiling, not the walls: a bedroom with 12.10 m² of floor has 35.50 m² of gross walls here. Measure the perimeter and multiply by the actual height.

Changing the deduction rule from one room to the next

Deducting every opening in one room and none in the next distorts the total without it showing. Set the rule once for the whole plan and write it into the quote.

Forgetting both faces of partitions and hidden surfaces

A drylining partition is built once, but both faces are painted, each in its own room. Reveals, niches, boxed-in ducts and cupboard ceilings easily slip through the take-off.

How to do a plastering and painting take-off in 3 steps

  1. Open the plan, set the scale and the height
    Drop the PDF plan of the storey into the studio and calibrate the scale on a known dimension. Enter the ceiling height, for example 2.50 m.
  2. Draw each room in its layer
    In a CFC 271 or CFC 285 layer, draw the inside outline of each room and give it a name. Choose the rule for deducting openings: none, all, or above a threshold.
  3. Read the table room by room and export
    The summary table gives the perimeter, wall area and floor area of each room, with the formula. Export to CSV to carry the quantities over into your quote.

Open the free studio →

What the free version does not do for a plastering and painting take-off

The studio does not recognise rooms: each outline is drawn by hand. It measures in plan and sees neither sloping ceilings nor downstand beams. Nothing is saved: once the tab is closed, everything is erased. The only free export is CSV, with the Art Construction notice.

Soumissions takes the quantities into the items of a quote, with the price database and one file per site. Plans Pro (2D/3D) saves layers and measurements site by site, allows teamwork and exports without a watermark.

Frequently asked questions

How do you get the wall area to be painted from a PDF plan?

Draw the outline of the room and enter the ceiling height. The studio calculates the wall area, perimeter multiplied by height, and the floor area, which corresponds to the ceiling.

Should doors and windows be deducted for painting and plastering?

Measurement practice often allows small openings not to be deducted, which offsets the work on the reveals. The threshold depends on the specification. The studio offers three settings: none, all, or a threshold.

Can plastering and painting be separated in the same take-off?

Yes. Create a layer with the code CFC 271 for drylining and plaster skims, and a CFC 285 layer for painting. The summary table groups the lines by layer.

What if the ceiling height varies from one room to another?

The studio applies the height you have set. For a higher or lower room, take its perimeter into your spreadsheet and multiply it by the actual height.