For a tiler or floor layer, the quantity laid and the quantity ordered are not the same. The first is read off the plan; the second depends on the tile format and the laying direction. In between lies the waste, to be estimated as closely as possible.
The Take-Off & Métré studio opens the PDF plan in the browser, without uploading the file. You draw each room as a polygon area, subtracting the zones with no covering. The perimeter is the basis for the skirting, and the height you enter turns a screed area into a volume. The lines go into layers with the codes CFC 281 and CFC 282.
Worked example: tiling and screed take-off for the ground floor of a house
A new house in French-speaking Switzerland, plan at 1:50. Three rooms receive a 7 cm screed and 60 × 60 cm tiles: living room-kitchen and hall laid straight, bathroom laid diagonally. One box contains 1.44 m². Allowances used for the example: 10% laid straight, 15% laid diagonally.
| Room | Net area | Waste | To order | Skirting |
|---|---|---|---|---|
| Living room-kitchen | 34.60 m² | 10% | 38.06 m² | 23.70 m |
| Hall | 6.80 m² | 10% | 7.48 m² | 7.60 m |
| Bathroom | 5.90 m² | 15% | 6.79 m² | no skirting |
| Total | 47.30 m² | depends on laying | 52.33 m² | 31.30 m |
The three rooms total 34.60 + 6.80 + 5.90 = 47.30 m² laid. Laid straight, 34.60 × 1.10 = 38.06 m² and 6.80 × 1.10 = 7.48 m²; laid diagonally, 5.90 × 1.15 = 6.79 m². To order: 52.33 m², i.e. 52.33 ÷ 1.44 = 36.3 boxes, so 37. Skirting: 26.40 m of perimeter less three doorways of 0.90 m in the living room-kitchen, 11.20 m less four doors in the hall.
The screed is calculated on the net area: 47.30 × 0.07 = 3.31 m³. The allowances of 10% and 15% are example values: they vary with the format, the layout and the shape of the rooms, and the rule must be confirmed against the specification and the measurement practice of the trade.
For this ground floor, the take-off gives 47.30 m² of tiling laid, 52.33 m² to order, i.e. 37 boxes, 31.30 m of skirting and 3.31 m³ of screed.
3 common mistakes in a tiling and floor covering take-off
Applying the same waste allowance to every room
A large rectangular living room laid straight produces little waste; a small bathroom laid diagonally produces far more. A single rate hides these differences. Measure the rooms separately.
Counting skirting on the full perimeter
The perimeter includes doorways and fitted furniture, where no skirting is fixed. In the hall of the example, four doors account for 3.60 m out of 11.20 m. Take the doorways off, or measure section by section.
Confusing area laid and area ordered in the quote
Laying is in principle priced on the covered area, supply on the quantity delivered, rounded up to the box. Keep two separate quantities, and calculate the screed on the net area, without the waste.
How to do a tiling and screed take-off in 3 steps
- Open the plan and set the scale
Drop the PDF plan into the studio and calibrate the scale on a known dimension. For a distorted scanned plan, use the separate X and Y calibration. - Draw the rooms and the skirting by layer
Create a CFC 281 layer for the floors (screeds and tiling) and, if there is wall tiling, a CFC 282 layer. Draw each room as a polygon area. Measure the skirting as cumulative lengths. For the screed, enter a height of 0.07 m to obtain the volume. - Export and apply the waste in your spreadsheet
Export the summary table to CSV. In your spreadsheet, add the waste allowance room by room, divide the area to order by the contents of one box and round up to the next whole number.
What the free version does not do for a tiling take-off
The studio gives areas, lengths and volumes; it does not work out the tile layout, does not count cuts and does not apply the waste allowance, which is done in your spreadsheet. Nothing is saved from one session to the next; the only free export is CSV, with the Art Construction notice.
Soumissions carries these quantities into the items of a quote, with the price database and one file per site. Plans Pro (2D/3D) saves layers and measurements site by site, allows teamwork and exports without a watermark.
Frequently asked questions
What waste allowance should be planned for tiling?
There is no single rate. The values in the example, 10% laid straight and 15% laid diagonally, are common orders of magnitude. State the rate you have used in your quote.
How do you measure skirting on a PDF plan?
Two methods: measure the skirting as cumulative lengths, section by section, skipping the doors; or start from the perimeter of the room, given by the studio, and take off the width of the doorways.
Can the studio calculate the volume of screed?
Yes. Enter a height equal to the screed thickness, for example 0.07 m: the studio shows the volume in m³, area multiplied by height.
Does the studio take account of zones with no floor covering?
Yes, if you mark them. A floor opening, a shower tray or the footprint of fitted furniture is drawn as a void to be subtracted, and its area is removed according to the deduction rule chosen.