Dimensioning Excavation Slopes, Shoring and Safety Distances to Overhead Power Lines (SUVA)

Swiss guide to dimensioning excavations, slopes, trench shoring, and clearance distances to overhead power lines on plans under OTConst and SUVA rules.

Table of contents
The 3 Major Site Risks
  1. Financial / Margin: Inaccurate slope dimensioning or unreferenced shoring leads to unplanned earthworks and quantity disputes that can exceed 45'000 CHF in extra costs under standard SIA 118.
  2. Legal / Joint Body / SUVA: Under art. 229 CP, intentionally breaching recognized engineering rules during unstable excavation and knowingly endangering human life carries a custodial sentence of up to five years or a monetary penalty.
  3. Administrative / Sign-off: Failing to graphically indicate safety envelopes beneath overhead lines blocks plan approval by the site management and delays the start of excavation.

This technical guide details the geometric dimensioning of earthworks, the drafting representation of slopes, the sizing of shoring systems, and safety envelopes beneath overhead electrical lines. It is designed for civil engineering firms, architects, and draftspersons in Switzerland preparing execution drawings and safety plans.

The employer applies art. 82 LAA to prevent occupational accidents by adopting technically feasible and appropriate measures, supported by the workforce, while art. 3 OPA mandates installations conforming to the state of the art. Art. 68 OTConst, art. 71 OTConst, and art. 77 OTConst specify berm widths and shoring strength requirements.

Geometric dimensioning of slopes, shoring, and safety berms

Drafting execution plans requires a strict graphic distinction between theoretical excavation bottoms, actual earthwork lines, and retaining structure footprints. Pursuant to art. 68 OTConst, earthworks deeper than 1 m 50 that are neither propped nor shored must be sloped in accordance with art. 75 OTConst or secured through equivalent methods. Art. 76 OTConst requires a geotechnical safety justification prepared by a specialist engineer or geotechnical expert whenever excavation depth exceeds 4 m, if slopes deviate from standard ratios, or in the presence of surcharges and groundwater ingress.

On cross-sections at 1:50 or 1:20 scale, the draftsperson must dimension the clear safety strip along the top edge: art. 71 OTConst mandates a horizontal clearance of at least 50 cm when the excavation is shored, and at least 1 m when the cut is sloped. For prefabricated shoring (trench boxes, sheet piles, or soldier pile walls), art. 77 OTConst requires these assemblies to resist all foreseeable loads, including spoil heaps and excavator traffic. If the slope exceeds 45° for depths over 2 m, edge protection compliant with art. 22 OTConst and art. 23 OTConst must be installed at the top of the excavation.

Clearance distances for overhead lines and 3D clearance envelopes

Operating earthmoving equipment near overhead electrical lines requires plotting three-dimensional clearance envelopes. Applying art. 82 LAA and art. 3 OPA, the employer enforces technical safety measures to prevent electrical arcing. The site layout plan must dimension the line alignment, the maximum line sag under summer temperatures, and the kinematic envelope of the excavator or dump truck.

This trajectory analysis prevents any hazard to operators within the meaning of art. 17 OTConst. When safety distances recommended by SUVA cannot be maintained, the plan must specify mitigation measures: grid operator de-energization, insulating line covers, or overhead restriction gantries limiting hydraulic boom elevation.

Comparative summary of dimensioning rules and requirements

Excavation configuration Required slope or profile Mandatory clear berm Retaining or safety system Legal basis or reference
Standard sloped excavation (< 4 m) Slope adapted to soil conditions (art. 75 OTConst) 1 m 00 minimum Edge protection if slope > 45° and h > 2 m Art. 23 and art. 71 OTConst
Deep excavation (> 4 m) Based on geotechnical sizing 1 m 00 minimum Specialist engineer calculation report Art. 76 OTConst
Shored or propped trench Retained vertical walls 50 cm minimum Shoring sized for structural surcharges Art. 71 and art. 77 OTConst
Earthworks beneath overhead lines Kinematic clearance under cables Demarcated buffer zone Height restriction gantries or shutdown Art. 82 LAA, art. 3 OPA
Unshored excavation > 1 m 50 Mandatory sloping or equivalent safety 1 m 00 minimum Hard hats mandatory during earthworks Art. 6 and art. 68 OTConst

Recurring drafting errors and financial disputes

Omitting working clearances for trench boxes is a recurring issue. When actual excavation encroaches on adjacent plots because vertical shoring was overlooked, site operations grind to a halt. Such design errors incur extra removal costs and plant standing charges ranging from 18 000 CHF to 50 000 CHF. Under art. 365 CO, a contractor discovering discrepancies between site conditions and drawings must inform the site management immediately or assume liability for the resulting damages.

Overlooking overhead line envelopes also triggers emergency shutdowns by cantonal labour inspectorates. Proven negligence during site execution may incur criminal liability for responsible parties under art. 229 CP should bodily harm occur.

Illustrative practical cases (typical scenarios on Swiss construction sites)

The figures and scenarios below are illustrative examples intended to guide practical drafting methodology.

Standard Scenario A: Basement excavation in an urban area (Canton of Vaud)

On a small residential building project involving a team of 6 people, the excavation reaches 3 m 80. Along the property line, the initial drawing planned an open slope without adequate setback. Art. 71 OTConst requires a 1 m berm clear of any stored material. Constrained by site boundaries, the engineering office revises the section to incorporate a certified trench box under art. 77 OTConst, reducing the required clear strip to 50 cm and preventing encroachment onto neighboring land.

Standard Scenario B: Utility trenching beneath overhead power lines (Canton of Fribourg)

During a 2 m 20 deep pipe trench excavated by 4 workers near a medium-voltage line, the site layout plan defines an overhead clearance envelope. The contractor logged all safety protocols in the document required by art. 4 OTConst. The engineering office draws a physical height-limiting gantry ahead of the danger zone to comply with art. 82 LAA and prevent electrical arcing from the excavator arm.

Surfaces, standards and permits: free tools

SIA 416 floor areas and volumes, cantonal zoning ratios, U-values and dew points, acoustics, planning enquiry requirements.

View engineering tools

Frequently asked questions

What is the minimum clear width required along the crest of a sloped cut?

Under art. 71 OTConst, the upper edge must remain horizontally clear over a width of at least 1 m. Illustrative extra costs of around 450 CHF occur when unplanned obstructions arise.

At what excavation depth is sloping mandatory when no shoring is installed?

Pursuant to art. 68 OTConst, unshored earthworks exceeding 1 m 50 in depth must be sloped. Unplanned remedial work generates an estimated expense of around 1 200 CHF.

When must slope stability be verified by a geotechnical specialist?

Art. 76 OTConst requires a stability report by a specialist engineer or geotechnical expert from a depth of 4 m. A corrective geotechnical study incurs indicative engineering fees of around 2 800 CHF.

What fall protection is required for a steep slope deeper than two metres?

Art. 23 OTConst mandates perimeter edge protection for slopes exceeding 2 m in depth and steeper than 45 degrees, preventing site stoppages costing approximately 800 CHF.

How should trench wall slopes be adjusted on drawings for severe weather?

Art. 75 OTConst requires adapting slope angles to soil stability and heavy rainfall. Emergency drafting revisions incur indicative redesign costs of around 600 CHF.

Who bears criminal liability if an excavation trench collapses?

Under art. 229 CP, breaching recognized construction rules and endangering human life carries custodial sentences or monetary penalties, alongside indicative procedural costs of 5 000 CHF.

Accurate dimensioning of slopes, trench shoring, and overhead power line clearances on 2D/3D plans ensures full compliance with occupational health and safety standards. Continue refining your execution documentation using our specialized methodological guides: