Plotting Tower Crane Jib Radius, Interference, and Oversailing Adjacent Plots in 2D/3D

Plot tower crane location, jib radius, interference, and oversailing in Switzerland under the OTConst and neighbourhood law.

Table of contents
The 3 Major Site Risks
  1. Financial / Margin: Oversailing dispute or machine shutdown forcing an unplanned crane relocation, generating extra costs in the region of 15 000 CHF to 45 000 CHF not covered by the initial price.
  2. Legal / Joint Body / SUVA: Failure to provide measures against falling materials under art. 17 OTConst or endangerment incurring criminal liability under art. 229 CP in the event of non-compliance with the recognised rules of the art.
  3. Administrative / Acceptance: Installation blocked by the municipality or neighbour objection in the absence of an oversailing agreement, delaying the schedule set by the works contract under standard SIA 118.

Plotting the jib radius of a tower crane in a dense urban environment requires rigorous graphic precision to coordinate ground footprints, heights under hook, and slewing paths. Design engineers, structural engineers, and site supervisors must model the exact location of the machine, oversailing zones across neighbouring land, and no-load zones in 2D and 3D to meet construction site safety requirements.

This technical process is part of the planning required by art. 3 OTConst so that the risk of accidents is as low as possible, and is formalised before opening the site in the written plan provided for in art. 4 OTConst. Integrating anti-collision systems between neighbouring cranes guarantees the operational compliance of the installation.

Method for 2D/3D plotting of jib radius and managing crane interference

Technical layout drawings for a tower crane require an exact overlay of the official cadastral survey and the digital terrain model. 2D plan and 3D volume modelling incorporate the geometric axis of the mast, counter-jib radius, rated reach under hook, and the full weathervaning radius. In accordance with art. 3 OTConst, construction work is planned so that the risk of occupational accidents, occupational illnesses, or damage to health is as low as possible. The designer identifies existing buildings, public thoroughfares, and restricted oversailing zones to map out kinematic safety envelopes.

When multiple cranes share the same working radius, the 3D drawing defines spatial interference zones by establishing tiered working elevations. The plan details electronic anti-collision devices with automatic slewing or trolley-travel restrictions. These graphic drawings are integrated directly into the health and safety plan required by art. 4 OTConst, which sets out the necessary measures before work begins. The employer takes protective steps and measures that meet the recognised rules of the art pursuant to art. 3 OPA, ensuring that measures are taken at workstations and access routes to prevent endangering workers from falling objects in accordance with art. 17 OTConst.

Protocol for oversailing adjacent plots and temporary easements

Oversailing adjacent private property with the jib or suspended loads entails strict legal constraints under the Swiss Civil Code (CC). Although out-of-service free weathervaning is required for machine stability, carrying loads over third-party properties requires the formal consent of neighbouring owners via a temporary airspace use agreement. On tender and execution drawings, the draughtsperson clearly distinguishes graphically between the full unloaded slewing arc and the restricted envelope for active lifting operations.

Geometric component Graphic representation (2D/3D) Normative and technical constraint Impact on site layout
Maximum jib radius Solid circle or dimensioned arc, centred on slewing axis Rated lifting radius according to manufacturer datasheet Overall coverage of the building footprint
Counter-jib radius Hatched circle centred on the mast Minimum clearance relative to party walls Positioned clear of neighbouring building facades
No-fly / no-oversail zone Red-hatched polygon, 3D zoning No oversailing agreement, public domain Calibration of limit-switch sensors
Interference envelope Transparent 3D intersection of jibs Height difference between moving components Slewing priority management between crane operators
Weathervaning envelope 360-degree free slewing envelope Passive rotation driven by wind forces Verification of high obstacles when out of service

Common plotting errors and operational repercussions

Omitting the counter-jib clearance on site layout plans is a frequent oversight: placing a mast too close to an existing gable wall blocks rotation during erection, leading to construction site delays and demobilisation costs of around 18 000 CHF to 35 000 CHF. Similarly, failing to identify overhead power lines or cadastral boundaries can lead to immediate work stoppages ordered by supervisory authorities. Intentional disregard of these technical provisions constitutes an offence under art. 229 CP, which penalises violations of the rules of the art that endanger the life or physical integrity of persons.

Illustrative practical cases (typical scenarios on Swiss construction sites)

The figures presented in the following scenarios are illustrative examples intended to guide the drawing methodology.

Scenario A: Urban densification in a city centre (Canton of Geneva). Construction of a residential building on a narrow plot bounded by the public domain and two co-ownership properties. Average workforce of 18 workers. The designer specifies a luffing-jib tower crane to keep slewing within the plot boundaries. The 3D plan demonstrates that the cadastral boundary is never crossed with a load. This approach eliminates the need to negotiate oversailing agreements with third parties and ensures approval of the application by municipal building control authorities.

Scenario B: Commercial office complex with two cranes (Canton of Vaud). Construction of two commercial buildings employing a team of 35 people. The technical design office models two cranes whose jib radii overlap by 14 metres. The structural engineer designs sufficient vertical clearance between the bottom chord of the higher jib and the top of the lower jib. The drawing deliverable includes a 2D plan of restricted zones and a full vertical section, integrated into the construction site health and safety document to coordinate lifting operations without collision risk.

Surfaces, standards and permits: free tools

SIA 416 floor areas and volumes, cantonal zoning ratios, U-values and dew points, acoustics, planning enquiry requirements.

View engineering tools

Frequently asked questions

How do you depict crane oversailing on an adjacent plot under Swiss law?

Draw the jib arc as a red dashed line on the cadastral plan. An oversailing agreement with defined compensation, typically around 2 500 CHF as an illustrative fee, avoids disputes with the landowner.

What 3D clearance distances apply between two tower crane jibs?

Comply with SUVA requirements by providing vertical clearance and an electronic anti-collision system. The engineering office notes these safety dimensions directly on the project's vertical sections.

Must the crane layout appear in the OTConst safety plan?

Yes, under art. 4 OTConst, the employer prepares a written plan showing footprints, out-of-service slewing, and restricted zones for suspended loads to safeguard all workstations.

Which technical document governs slewing over the municipal public domain?

The municipality requires a dimensioned drawing showing restricted oversailing zones. An increased-use permit for the public domain, often subject to an administrative fee of around 600 CHF, remains mandatory.

How do you locate crane foundations near a sloped excavation?

In accordance with art. 77 OTConst, size trench support systems to withstand expected loads. Crane footings must strictly maintain the setback zones calculated by the geotechnical engineer on execution drawings.

What criminal liability applies to errors in crane layout drawings?

If physical integrity is endangered due to disregard of the rules of the art during erection or operation, penalties fall exclusively under art. 229 CP.

Rigorous modelling of jib radii guarantees regulatory compliance and safety on urban construction sites. To further develop your technical dossiers: