Drafting Facade Scaffolding (CFC 114), Brackets and Roof Catch Platforms in Plan and Elevation

Draft CFC 114 scaffolding, brackets and roof catch platforms to OTConst and SUVA standards. Compliant site installation drawings and elevations in Switzerland.

Table of contents
The 3 Major Site Risks
  1. Financial / Margin: Omitting a bracket or roofer-tinsmith catch scaffold on the drawings leads to unforeseen addenda under art. 363 CO, representing an extra cost of around 4 000 CHF to 12 000 CHF in scaffolding erection.
  2. Legal / Joint Body / SUVA: The lack of facade scaffolding where fall heights reach 3 m under art. 26 OTConst, without compliant measures under art. 41 OTConst at roof edges, exposes parties to criminal penalties under art. 229 CP in the event of endangerment.
  3. Administrative / Handover: Failing to graphically show tie-ins and catch platforms delays validation of the construction site installation plan under art. 3 OTConst and halts site access for secondary trades.

Rigorous graphical representation of facade scaffolding under Construction Cost Code CFC 114 is a cornerstone of safety and execution drawings in Switzerland. This technical guide helps draftspersons, architects, construction managers and civil engineers geometrically draft temporary works, widening brackets and roof-edge catch systems according to SUVA requirements.

During both the tender and execution phases, plan and elevation drawings must clearly specify base plates, safe access via stair towers and structural tie-ins to the building. In compliance with art. 22 OTConst for the geometric sizing of guard rails and art. 26 OTConst for deploying facade scaffolding, each layout ensures seamless spatial coordination across sites in the French-speaking cantons.

Graphical representation method in plan and section for CFC 114

Drafting facade scaffolding under CFC 114 requires strict geometric coordination between the construction site installation plan, facade elevations and roof sections. On formwork and architectural drawings, the draftsperson plots the exact layout of standards, the clearance to the finished wall face and the locations of structural anchors. Under art. 3 OTConst, construction work must be planned so that the risk of accident or health impairment is kept as low as possible, requiring safety measures to be integrated right from the initial technical sketches.

In plan, the clear working width of platforms must be laid out taking into account the final thickness of the external thermal insulation. In vertical section, the designer draws internal or external widening brackets, catch platforms and top guard rails. Art. 22 OTConst sets out the requirements for edge guard rails: a top rail at least 100 cm above the working surface, at least one intermediate rail, a toeboard of at least 15 cm and a maximum clear opening of 47 cm between horizontal members. Where eaves are present, roof brackets and tinsmith platforms must be dimensioned relative to the eaves edge to satisfy art. 41 OTConst, which mandates suitable measures to prevent roof-edge falls starting at a height of 2 m.

Drawing requirements for brackets, catch platforms and guard rails

Roof catch platforms and cantilevered brackets represent critical elements on 1:50 or 1:20 detail drawings. At workstations and access ways, measures must be taken so that workers are not endangered by collapsing elements or falling objects and materials, pursuant to art. 17 OTConst. The designer must plot tool-drop protection nets and waterproof debris sheeting on elevation sections whenever work overhangs the public domain or traffic routes.

Scaffolding component Plan representation (2D/3D) Section / elevation representation Regulatory reference
Main standards CFC 114 Dimensioned ground grid layout Lift heights and tie-in levels art. 3 OTConst
Perimeter guardrail Continuous outer protective line Top rail at 100 cm, mid rail, 15 cm toeboard art. 22 OTConst
Eaves brackets Dashed projection of working overhang Horizontal setback below cornice or gutter art. 41 OTConst
Catch platforms and protective netting Footprint of object retention areas Vertical debris screens and rubble nets art. 17 OTConst
Access trapdoors and ladders Positioning of stair runs Unbroken continuity of landings art. 3 OTConst

Common drafting errors and financial consequences

Failing to account for the thickness of plaster or the external thermal insulation composite system frequently leads to erecting the scaffolding too close to the bare masonry. Inability to fix insulation boards then requires the complete dismantling and re-anchoring of the structure, generating unexpected extra costs on the order of 6 000 CHF to 15 000 CHF depending on the facade surface. Similarly, omitting cantilever brackets to bypass a balcony forces the scaffold builder to alter the assembly on an hourly basis, leading to additional expenses of around 3 500 CHF under standard SIA 118.

From a legal standpoint, supplying uncoordinated drawings that lead to a collapse or a fall engages the criminal liability of designers under art. 229 CP, which penalises anyone who intentionally or through negligence breaches recognized engineering standards and endangers life or bodily integrity. Before work starts, the employer ensures there is a written plan detailing the measures required for the operations carried out, in accordance with art. 4 OTConst.

Illustrative practical cases (typical scenarios on Swiss construction sites)

The following figures and situations are illustrative examples designed to model technical drafting practices.

In the canton of Vaud, raising a three-storey residential building by one floor requires the simultaneous intervention of carpenters, tinsmiths and plasterers, representing an average workforce of eight operatives on the roof. The draftsperson modelled an external working scaffold in elevation, supplemented by tinsmith brackets placed 30 cm from the roof edge, with a guard rail extending 100 cm above the highest working point. This sizing ensures compliance with art. 41 OTConst and provides space for temporary storage of Sheet-metal Work components without obstructing circulation routes.

In the canton of Valais, the renovation of a semi-detached village facade requires scaffolding standards to be erected along a narrow alleyway. The designer incorporated folding interior brackets and debris netting into the phasing plan to meet the requirements of art. 17 OTConst. This proactive drafting prevented work from being shut down by municipal authorities and avoided scaffolding erection cost overruns.

Surfaces, standards and permits: free tools

SIA 416 floor areas and volumes, cantonal zoning ratios, U-values and dew points, acoustics, planning enquiry requirements.

View engineering tools

Frequently asked questions

At what height is facade scaffolding mandatory on Swiss drawings?

Under art. 26 OTConst, facade scaffolding must be installed as soon as the fall height exceeds 3 m, with a top rail extending above the top working edge.

What minimum dimensions must be drafted for edge protection guard rails?

Art. 22 OTConst sets a top rail at least 100 cm high, a toeboard of at least 15 cm and a maximum opening of 47 cm between horizontal members.

How should safety be detailed for work on sloping roof edges?

Art. 41 OTConst requires appropriate measures starting at a 2 m fall height, providing a tinsmith catch scaffold or guard rail depending on roof pitch, at an illustrative cost of around 45 CHF/lin.m.

What written document must accompany scaffolding drawings under Swiss regulations?

Art. 4 OTConst requires a written plan detailing safety and health protection measures, along with the first-aid organisation, prior to starting on-site work.

Who must appoint the person in charge of scaffolding inspections on the construction site?

Under art. 5 OTConst, the employer appoints a competent person on each construction site responsible for occupational safety, authorised to issue instructions to eliminate hazards.

What warranty remedies apply to erection plans in the event of building defects?

Art. 367 CO gives the client a 60-day notice period to notify defects in an immovable work, while art. 371 CO sets the limitation period at five years.

Technical coordination and roof fall protection compliance

Accurate drafting of CFC 114 scaffolding and catch platforms guarantees operational safety and compliance with Swiss requirements. Detailed drawings prevent fall hazards on built structures while clarifying the legal responsibilities of designers and consultants. To enhance your graphical planning and construction site safety, consult our specialised guides: