The 3 Major Site Risks
- Financial / Margin: Forfeiture of defect notices for apparent defects not reported before the end of the two-year period, shifting the financial burden of remedial work to the client for an amount of around 3 % to 7 % of the construction cost under the Code of Obligations (CO).
- Legal / Joint Body / SUVA: Unjustified release of the joint and several guarantee provided for under art. 492 CO and liability risk under art. 229 CP in the event of substandard work affecting structural safety that was not recorded during the joint inspection.
- Administrative / Acceptance: Permanent loss of the right to remedial work under standard SIA 118 and formal dispute of the snagging list by the contractor for lack of a joint inspection record drawn up before the exact expiry of the claim period.
The end of the two-year warranty period is a critical milestone for site management and the client under the rules of standard SIA 118. During this initial period, the client retains the right to invoke any defect discovered without having to establish that it was a hidden defect upon delivery. Organizing a thorough joint inspection before the exact deadline allows all parts of the works to be inspected, a joint inspection record to be established, and any non-conformities that appeared during the first twenty-four months of operation to be recorded.
Under contract management pursuant to the Code of Obligations (CO) and standard SIA 112 Phase 53, the lack of a formal protocol before the end of the two years deprives the client of the favorable presumption inherent to this regime. Once this deadline passes, the hidden defects regime applies, requiring a formal notice of defects under penalty of forfeiture of rights. Holding this joint inspection guarantees valid notification of notices of defects prior to the release of the warranty guarantee and secures the execution of the necessary remedial work.
Methodological Protocol for the Two-Year Joint Inspection
Conducting a joint inspection near the end of the two-year period requires strict procedural rigor, complying with the guidelines of standard SIA 118 and the stages of Phase 53 under standard SIA 112. Site management must plan operations at least two months before the exact expiry of the two-year period, calculated from initial acceptance of the works.
Formal Notice to Contractors and Document Preparation
Site management sends a formal notice by registered mail or verifiable electronic means to each contractor involved in the CFC sections being inspected. The notice must grant reasonable advance warning, generally set at ten working days, specifying the date, meeting time, precise scope of the rooms to be inspected, and the mandatory attendance of a representative with signing authority.
In parallel, the preparatory file must compile:
- The initial acceptance report and the list of resolved or outstanding reservations.
- As-built drawings and technical maintenance manuals.
- The log of notifications submitted by users or property managers during the first 24 months of operation.
- Thermal, ventilation, and acoustic test sheets performed during commissioning.
Inspection Walkthrough and Exhaustive Defect Survey
On site, the joint inspection is conducted room by room, including roofs and basements. The delegation includes the client or their qualified representative, local site management, and the technical manager of the appointed contractor. Any defect observed is subject to immediate visual examination, a photograph pinpointed on a plan, and dimensional measurements where necessary.
The walkthrough prioritizes items showing abnormal wear, plaster cracking, air or water tightness failures, screed settlement, and HVAC technical installation malfunctions. Distinguishing between defective execution attributable to the contractor under art. 368 CO and wear resulting from lack of maintenance is the responsibility of site management, which records the observations of both parties without interrupting the survey.
Formalizing the Minutes and Setting Remedial Deadlines
The joint inspection minutes are drafted on the spot or finalized within 48 hours following the inspection. This official document details each defective item, its precise location according to the CFC code, the presumed cause, and the deadline set for completing the remedial work in kind.
The minutes must be countersigned by the contractor. In the event of a refusal to sign or a dispute regarding the origin of the defect, site management formally serves the document along with a formal notice to perform repairs within a reasonable period, pursuant to art. 107 CO, failing which the work will be executed by a third party at the debtor's expense pursuant to art. 366 CO.
Comparative Matrix of Situations Encountered at the 2-Year Expiry
Assessing defects observed during the end-of-warranty inspection requires rigorous legal and technical characterization to determine the applicable steps:
| Observed Situation | Legal Characterization | Impact on Guarantee Release | Action Required from Site Management | Consequence for the Client |
|---|---|---|---|---|
| Plaster cracking > 0,3 mm on concrete facade | Construction defect (art. 368 CO) | Partial withholding of security release | Formal notice with rectification deadline prior to the end of the 2 years | Right to free remedial work preserved without expert assessment costs |
| Infiltration on flat roof without interior signs | Proven waterproofing defect (art. 365 CO) | Full retention of the joint and several guarantee | Formal notice to perform leak detection and remedial work within a fortnight | Preservation of recourse against the roofer and design engineer |
| Window sash sticking due to structural work settlement | Execution defect or tolerance exceeded | Withholding of the related financial guarantee | Joint inspection record between carpenter / mason and formal order to adjust | Elimination of thermal bridges and preservation of user comfort |
| Clogged air handling unit filter without breakdown | Operational maintenance failure | No impact on the contractual warranty | Rejection of claim against installer and referral to property management | Financial charge attributable to building operating costs |
| Paint chipping following mechanical impact by user | Damage caused by a third party (art. 369 CO) | No security withholding permissible | Record in the minutes as not attributable to the contractor | Covered by operator's insurance or the client |
Common Procedural Errors and Associated Financial Damage
Disregarding formal inspection and notice rules exposes the client to substantial economic losses in Switzerland.
Holding the Inspection Late After the 730th Day
Organizing the joint inspection even a few days after the exact two-year term shifts the warranty regime of standard SIA 118 to the restrictive hidden defects regime under art. 370 CO. Any apparent defect not notified in time is deemed accepted. On a typical office building, repairing ventilated facade defects or motorized blinds accepted in this manner represents a loss of around 45 000 CHF to 90 000 CHF, borne entirely by the owner.
Absence of Written Notice in Case of a Verbal Promise to Repair
Relying on a verbal commitment from a tradesperson present on the construction site without recording the defect in formal minutes is poor management. If the contractor fails to intervene, the limitation period under art. 371 CO continues to run. Without a formal tolling of the limitation period within the meaning of art. 135 CO or a written waiver under art. 141 CO, the client's rights lapse, leaving a residual repair bill often between 15 000 CHF and 35 000 CHF for cracked screeds or tiling.
Premature Release of the Joint and Several Guarantee
Releasing the bank or insurance guarantee deed before verifying that end-of-warranty remedial work has actually been carried out strips the client of financial leverage. If the contractor goes into bankruptcy or refuses to intervene, hiring a third-party company to complete the defective work causes emergency intervention cost overruns of around 20 000 CHF to 60 000 CHF that cannot be recovered.
Illustrative practical cases (typical scenarios on Swiss construction sites)
The following figures and situations are illustrative examples designed to explain the practical application of inspection protocols in Switzerland.
Standard Scenario 1: Rental Housing Development in Lausanne (Canton of Vaud)
On a residential complex of 24 units completed in structural work and finishing work (CFC 211 and 271), initial acceptance took place on 15 October 2024. The two-year period expires on 15 October 2026. The total workforce deployed on the construction site includes 14 appointed contractors.
On 20 August 2026, local site management issues formal notices to all finishing work trades for a three-day inspection tour in early September. While inspecting basements and underground parking facilities, active infiltrations through concrete construction joints are detected, threatening the durability of the reinforcement.
The masonry firm disputes liability, citing ground movements. Site management draws up detailed minutes, refuses the release of the 80 000 CHF guarantee provided by the contractor, and gives it until 30 September 2026 to inject the necessary waterproofing resins. The remedial work was carried out at a cost of approximately 28 000 CHF, fully covered by the contractor prior to the final release of securities.
Standard Scenario 2: Commercial Building in Meyrin (Canton of Geneva)
An administrative building featuring district heating and complex glazed facades was commissioned two years earlier. As the two-year deadline approaches, the facility manager reports temperature drift in south-facing offices.
During the joint inspection with the ventilation and controls contractor, site management identifies a programming fault in the control valves combined with failing damper actuators. The estimated cost of third-party replacement is roughly 22 000 CHF.
Thanks to the inspection minutes signed before the two-year deadline, the client directly asserts the right to repair under standard SIA 118 and art. 368 CO. The installer replaces the equipment under its own warranty the following month, thereby preserving the facility's operating margin without subsequent litigation.
Contracts and SIA 118: free tools
Advance payments and retentions, surety bonds, price escalations, daywork reports, subcontractor monitoring.
Frequently asked questions
What should be done if a contractor refuses to sign the inspection minutes?
Site management records this refusal in the joint document. It serves the document by registered mail before the two-year deadline expires. Under the Code of Obligations (CO), material proof of the notice of defects safeguards the client's rights, even against a 15 000 CHF dispute.
What is the risk if the inspection takes place after the exact two-year deadline?
Unreported apparent defects are deemed accepted under art. 370 CO. The regime shifts to hidden defects, where the client bears the burden of proof. Screed remediation estimated at 8 500 CHF may then end up entirely at the client's expense.
Can the full release of the joint and several warranty guarantee be refused?
Yes. Under art. 492 CO governing guarantees, release may be withheld in proportion to the value of the notified remedial work. If facade rectifications are valued at 22 000 CHF, the guarantor bank maintains coverage until the reservations are formally lifted by site management.
How can a remedial agreement be formalized without compromising the limitation period?
The remediation agreement must be set down in writing as an acknowledgement of debt under art. 135 CO, which interrupts the limitation period. For waterproofing worth 35 000 CHF, it is also recommended to demand a written waiver of the limitation period pursuant to the provisions of art. 141 CO.
Which authority settles a persistent technical dispute during the two-year inspection?
The parties may appoint a panel of experts under art. 367 CO to assess the technical defects objectively. If the expert finds non-conformity on ventilation worth 12 000 CHF, the report serves as evidentiary findings before any referral to the competent cantonal civil court.
Does the absence of a duly summoned contractor invalidate the joint inspection?
No. A written summons sent with reasonable notice allows the inspection to be conducted unilaterally. The site management draws up the complete minutes and serves them formally. For defective joinery worth 6 400 CHF, proper notification is sufficient to validate the notice of defects within the deadline.
Rigorous management of the joint inspection protects the client against tacit acceptance of defects and sets the condition for releasing the financial securities. To explore the contractual and technical protocols of construction site supervision in Switzerland in greater depth, consult our specialist guides:
- Warranty Site Management in Switzerland: 2-Year / 5-Year Deadlines, Surety Bonds and Latent Defects (SIA 118 / CO 2026)
- 2-Year Defect Notification Period (SIA 118) vs 60-Day Notice Period in Revised CO 2026: Burden of Proof
- Performance Joint and Several Guarantee (SIA 118): Amount (5% to 10%), Duration and Release Terms
- Hidden Defects Between Years 2 and 5 (SIA 118 / CO 2026): Rules for Valid Notice