Site Management of Warranties in Switzerland: 2-Year / 5-Year Periods, Guarantees, and Hidden Defects (SIA 118 / CO 2026)

Master the 2-year and 5-year warranty periods under SIA 118 and the revised 2026 CO. Defect notices, retentions, and joint and several guarantees.

Table of contents
The 3 Major Site Risks
  1. Financial / Margin: Loss of retention money and unjustified calling of the bank or insurance joint and several guarantee. Poor management of snag clearance exposes the contractor to remediation by a third party at the debtor's expense, typically amounting to 5% to 15% of the total cost of the work in CHF, not including contractual default interest in the event of default.
  2. Legal / Joint Body / SUVA: Formal forfeiture of warranty rights or the five-year statutory limitation period. Failure to comply with notice forms and deadlines results in tacit acceptance of the work under the Code of Obligations (CO). In parallel, any corrective on-site action requires strict compliance with the safety measures prescribed by the Construction Works Ordinance, failing which the contractual and civil liability of the parties involved may be engaged.
  3. Administrative / Acceptance: Frozen release of financial guarantees, disputes over the joint inspection record, and refusal by the municipality to issue the occupancy permit due to technical non-completion. Confusing the conventional regime of standard SIA 118 with the mandatory statutory regime paralyses the administrative closing of the final account.

Site management and supervision of the warranty phase represent the ultimate economic and legal safeguard protecting the profitability of construction stakeholders in Switzerland. Too often seen as a mere post-handover administrative formality, the period following the acceptance of the work concentrates major risks spread across a five-year horizon. Between physical completion of the structural work, the commissioning of Plumbing & Sanitary Installations, heating, and ventilation, and handing the keys to the client, a highly regulated contractual sequence begins where every formal notification, joint inspection record, and release of financial securities must follow strict rules. In Swiss construction law, the boundary between the standard contract for work governed by federal law and projects subject to the contractual incorporation of professional standards creates a dual management structure that frequently ensnares unwary practitioners. The entry into force of the revision to construction defect law on 1 January 2026 profoundly redefined these established balances. For immovable structures, lawmakers enacted a mandatory statutory notice period of sixty days, voiding any shorter contractual deadlines seeking to reinstate immediate notice requirements. Faced with this legal shift, standard SIA 118 retains its operational relevance thanks to its two-year warranty regime, during which defects of any nature may be reported at any point until the end of the two-year period. This comprehensive manual provides an operational and legal analysis designed for site management, clients, site supervisors, and civil engineers operating in Romandie. It covers initial inspections, defect handling over the first twenty-four months, organizing the joint inspection before warranty expiry, managing hidden defects through year five, and managing financial securities, payment retentions, and guarantees. For questions on initial costing, estimates, or responding to public and private calls for tenders, professionals can consult the dedicated portal for tenders. For detailed labour rate analyses and unit remediation costs, reference data is available on the Indice ACIP according to standard access terms. Finally, hiring site supervisors or trade specialists is managed through the specialized recruitment and jobs portal.

Managing these five years of shared liability effectively requires a clear understanding of the hierarchy of standards and traceability protocols. This document lays out a structured chronological approach across several core sections: carrying out the initial joint inspection and drafting an unambiguous acceptance report; exercising the right to rectification of the work and supervising remediation work; monitoring the two-year and five-year expiration deadlines; the evidentiary rules governing the burden of proof between the two-year warranty regime and the hidden defects regime; and finally, the steps required to interrupt the limitation period legally via debt enforcement under the Federal Act on Debt Enforcement and Bankruptcy (LP) or via a written waiver agreement. The objective is to provide every project manager with the decision-making tools needed to safeguard structural integrity while preventing costly litigation and erosion of execution margins.

Managing warranties for an immovable work sits at the heart of contractual relationships governed by Swiss law. Site management is responsible for coordinating two distinct sets of rules: the statutory baseline regime under the Code of Obligations (CO) and the contractual regime under standard SIA 118. Applying these frameworks together determines the formal validity of defect notices, the safeguarding of financial guarantees, and the allocation of the burden of proof between the client and appointed contractors.

Under the ordinary statutory regime, executing a contract for work binds the contractor to an obligation of result to produce a work that conforms to the agreed specifications. When the parties expressly incorporate standard SIA 118 into the contract, it legally supersedes the non-mandatory provisions of federal law. However, mandatory rules introduced by the revision to construction law effective since 1 January 2026 apply to all contracts, voiding any clause that attempts to restrict the minimum statutory rights granted to the client for immovable structures.

Interaction Between the Code of Obligations and Standard SIA 118

The key difference between the general statutory regime and the professional standard lies in the timing of the notice of defects. Under the Code of Obligations (CO), handover requires the client to inspect the condition of the work as soon as feasible in the normal course of business. For immovable works, the law provides a 60-day period to give notice of observed defects, strictly prohibiting shorter contractual deadlines.

Conversely, contractual adherence to standard SIA 118 introduces an initial two-year warranty period starting on the day of acceptance of the work. During these two years, the client may notify defects at any time without forfeiting rights due to late notification. This contractual mechanism reduces the daily administrative burden on local site management while keeping the contractor under an ongoing obligation to rectify reported defects.

The Mandatory Right to Remediation Under Revised Legislation

Since the legislative revision took effect on 1 January 2026, client protection has been strengthened by a strict ban on waiving the right to defect remediation. If the work exhibits non-conformities, the client may demand remediation free of charge, provided the resulting costs are not disproportionate to the intended benefit. Any clause providing for the advance exclusion of this right to rectification for an immovable structure is void as a matter of law.

This protective principle ensures the contractor cannot avoid physical remediation obligations simply by offering unilateral financial compensation, provided compliant repair remains technically viable. For site management, this legal framework requires formalising every repair notice with a firm deadline before arranging third-party substitute performance.

Financial Structure of the Joint and Several Guarantee

The financial security of warranty obligations depends on establishing dedicated guarantees. In line with Swiss trade practice under standard SIA 118, retention money is withheld from advance payments and the final account. This retention, typically ranging between 5% and 10% of the total work amount excluding taxes, is released upon acceptance against a joint and several guarantee issued by an approved Swiss bank or insurance company.

The guarantee contract assures the client that the contractor's debts will be paid in the event of default, particularly to cover remediation costs for defects notified during the warranty period. Site management must carefully verify that the wording of guarantee certificates complies with project terms, ensuring the guarantor's commitment covers all warranty obligations without unagreed restrictive clauses.

Occupational Health and Safety Liabilities on Remediation Sites

Performing remediation work during the warranty period does not exempt contractors from complying with health and safety regulations. Under art. 3 OTConst, construction work must be planned so that the risk of occupational accidents, occupational illnesses, or health hazards is kept as low as possible. This requirement applies fully to post-acceptance remediation sites, even for minor repairs in partially occupied buildings.

Site management must ensure that attending contractors deploy appropriate organisational measures in compliance with SUVA directives and worker protection regulations. Art. 229 CP establishes liability for anyone who, when managing or executing construction work, intentionally or negligently breaches recognised trade rules and thereby endangers the life or physical integrity of others. The safety of building occupants and repair crews is an absolute legal prerequisite before any snag clearance work begins.

Six-step protocol for managing the warranty period

Rigorous warranty administration requires a strict chronological methodology. Site management coordinates communications between clients, occupants, and construction contractors to prevent the forfeiture of rights and secure the timely financial closeout of the project.

Step 1: Initial Joint Inspection and Acceptance of the Work

Acceptance of the work establishes the starting point for warranty and limitation periods. As soon as the contractor announces completion, site management arranges an on-site joint inspection with all relevant stakeholders. Physical findings are recorded in a detailed acceptance report, clearly identifying compliant items, minor outstanding works, and patent defects noted at handover.

This record must specify the nature of acceptance. If the defects recorded are minor and do not prevent the construction from being used as intended, the work is deemed accepted, which formally starts the two-year warranty period under standard SIA 118 and the five-year limitation period laid down by federal law for building structures. Any reservations formulated are assigned a precise remediation schedule, with binding completion deadlines for each trade.

Step 2: Setting up and validating the register of financial securities

As soon as the acceptance record is signed, site management collects the deeds of joint and several guarantee provided by contractors to replace financial retainages withheld on interim payment certificates. Each instrument issued by a bank or an insurance company is subject to a rigorous legal review covering the exact identification of the parties, the guaranteed amount in CHF, the expiry date and the formal call conditions.

Data is consolidated into a centralised register of guarantees. This register ensures the chronological tracking of partial or total releases and enables the scheduling of contractual alerts. No final balance payment on the final account may be made without the prior receipt of the original deed of guarantee compliant with the requirements of the contract for work and services.

Step 3: Continuous management of notices of defects during the two-year period

During the two-year warranty period governed by standard SIA 118, the client and its representatives may report defects as they are discovered or group them in periodic submissions. Site management centralises notifications received from users or property management, filters out issues caused by poor maintenance or normal wear and tear, and drafts formal notices of defects.

Each notice of defects must accurately describe the physical manifestation of the issue, identify the work concerned, state the precise location and set a reasonable deadline to carry out the remedial work. The notification is sent by registered letter or verifiable electronic means to provide an irrefutable date of notification. If the contractor disputes liability, site management conducts a joint technical inspection to determine the causes of non-compliance.

Step 4: Organising the two-year warranty expiration inspection

Approximately three months before the exact expiry of the two-year period following acceptance, site management summons the contractor and the client to the formal warranty expiration inspection. This comprehensive examination of the work identifies all defects that have emerged since acceptance and verifies the proper execution of previously ordered repairs.

The findings are recorded in a two-year warranty sign-off record. If any defects remain, a summary list of reservations is appended to the document, granting the firm an ultimate completion deadline. This record marks the end of the period during which defects can be reported without particular urgency. After this pivotal date, the rules governing hidden defects take effect for the remaining duration of the five-year limitation period.

Step 5: Managing hidden defects between the second and fifth year

Upon expiry of the two-year period under standard SIA 118, defects that were not identifiable during standard inspection and manifest later are classified as hidden defects. Under the applicable rules, the discovery of such a defect calls for increased diligence: the client must notify the contractor of the defect without delay as soon as it manifests physically.

Notification must take place within the statutory deadlines to avoid tacit acceptance of the defective condition. Site management must then investigate the technical file, evaluate whether the defect arises from a design error, defective material or faulty workmanship, and formally claim under the warranty from the firm concerned and its financial guarantor.

Step 6: Protecting rights before the five-year limitation period expires

The limitation period for warranty actions regarding defects in a building structure expires five years after acceptance. In order to avoid permanently losing claims for remedial work or damages, the client must take formal actions that interrupt the limitation period before the critical five-calendar-year deadline.

Site management draws up a comprehensive assessment of unresolved disputes six months before the five-year deadline. To stay the running of time, the client may request a written waiver of the limitation period for a specified duration from the contractor and the guarantor, or serve a payment order through the debt enforcement office under the Federal Act on Debt Enforcement and Bankruptcy. Failing agreement, filing a conciliation request before the competent judicial authority is essential to fully protect the principal's financial rights.

Comparative table of warranty and liability regimes

The following table compares the various contractual and temporal situations encountered during the post-handover monitoring of a building structure in Switzerland, detailing applicable sources, operational impacts and key points of vigilance for site management.

Situation / Analysed itemRequirement or reference sourcePractical impact on the construction sitePoint of vigilance for site management
Acceptance of the workProcedure under standard SIA 118 and the contract for work and servicesTriggers warranty periods, transfers risk in the work and makes the price due.Draw up an exhaustive joint inspection record without leaving any non-conformities undocumented.
Initial notice period (revised CO 2026)Federal statutory rules under the Code of ObligationsThe client has a 60-day period to report defects discovered upon handover of a building structure.Ensure there are no conflicting contractual clauses, which are void if they shorten this period.
Two-year warranty periodContractual clause under standard SIA 118Right to notify defects at any time during the two years following acceptance.Systematically organise the joint inspection three months before the end of the two years.
Right to repairMandatory provisions of the Code of ObligationsThe contractor must repair the defect at its own expense if the costs are not disproportionate.Any advance waiver of this right in the contract is legally void for a building structure.
Joint and several guaranteeFinancial warranty securities (standard SIA 118)Replacement of the 5% to 10% retainage with a solvent bank or insurance instrument.Verify the formal validity of the deed and the exact adequacy of guaranteed amounts in CHF.
Hidden defects (years 2 to 5)Combined rules under standard SIA 118 and federal lawObligation to report the defect as soon as discovered to prevent the forfeiture of rights.Report the defect in writing by registered mail upon discovery without waiting to group notifications later.
Five-year limitation periodFive-year period for building structuresExtinction of legal actions for repair or damages after five years from acceptance.Obtain a written waiver of the limitation period or serve a payment order before the deadline.
Safety during remedial workArt. 3 OTConst and prevention rulesMandatory planning of measures to minimise occupational hazards during remedial interventions.Prohibit any work on roofs or façades without compliant protective equipment.

Decision criteria for managing warranties and disputes

Strategic decision-making when a dispute arises during the warranty phase relies on a methodical analysis of legal, technical and financial criteria. Site management must advise the client with sound judgement to preserve the property's value without initiating disproportionate proceedings.

Technical and physical assessment of the defect

The primary decision lies in clearly assessing the nature of the identified anomaly. Three categories of occurrences must be clearly distinguished:

  • Construction defect attributable to the contractor: Deviation from drawings, recognised rules of the art of building, descriptive quotes or contractual acoustic and thermal performance requirements. The contractor is fully liable for this under the warranty for the work.
  • Normal wear and tear and aging of materials: Gradual deterioration resulting from the normal use of the work over time. These conditions do not entitle the client to remedial work under the warranty.
  • Lack of maintenance by the client or operator: Omission of maintenance tasks recommended in manufacturer technical manuals (e.g. cleaning box gutters, servicing ventilation systems, lubricating fittings). This failure exempts the contractor from liability.

Financial appraisal and proportionality principle

The selection of corrective measures must balance the cost of remediation against the objective benefit for the client. When eliminating a purely aesthetic defect would require demolishing and completely rebuilding a major structural element at a disproportionate cost, demanding full rectification may run up against legal limits. In such a scenario, site management should steer negotiations towards an appropriate reduction in the price of the work, implemented via a financial deduction in CHF on the final account or through compensatory indemnity.

Conversely, whenever a defect impairs the durability of the work, its water- or airtightness, operational safety or regulatory compliance, demanding full rectification remains an absolute priority and is non-negotiable. The cost of remedial action must be estimated rigorously by site management to evaluate whether the amount covered by the active joint and several guarantee is sufficient.

Timeliness and choice of protective measures

The contractor's response to the formal request to repair determines the procedural course of action. Three operational situations commonly arise:

  • The contractor acknowledges the defect and schedules the repair: Site management approves the technical repair method, sets a binding execution deadline and conducts the joint inspection record to lift reservations after completion of the work.
  • The contractor remains passive or delays action: The debtor must be formally put in default with the setting of a final reasonable grace period. The notification must expressly state that, once this period has elapsed, remedial work will be carried out by a third-party firm at the defaulting contractor's expense and risk. A claim on the joint and several guarantee is then formally prepared.
  • The contractor disputes liability in principle: Where a complex technical disagreement arises (for example regarding the source of water infiltration or concrete cracking), obtaining an independent expert opinion is essential before starting destructive work. Site management appoints an independent expert to preserve physical evidence before altering site conditions.

As the five-year limitation period approaches and negotiations have not resulted in a comprehensive settlement agreement, serving a formal legal instrument is the only way to avoid the forfeiture of financial claims. Securing a written waiver of the limitation period, signed jointly by the main contractor and the financial institution issuing the joint and several guarantee, constitutes the most effective and least adversarial means to extend negotiations or monitor ongoing repairs.

Operational implementation of warranties by type of situation

Managing defects and administering securities requires differentiated protocols depending on the contractual and physical context faced by site management. Post-acceptance interventions cannot follow a one-size-fits-all approach: the contractor's attitude, the severity of the damage and the nature of the issues require specific procedural steps to protect the client's claims.

Typical scenario on the construction siteContractual and technical setupMeasures required from site managementFinancial and administrative consequences
Explicit refusal to intervene or contractor inactionDefects notified in writing during the two-year trial period under standard SIA 118 or under the contract for work of the Code of Obligations (CO), which remain without corrective action within the stipulated period.Formal finding of default, summons with a peremptory deadline, followed by the exercise of rectification rights at the defaulting contractor's expense under the Code of Obligations (CO). Concurrent notification to the guarantor to suspend the release of the performance guarantee.Continued withholding of the 5% to 10% guarantee, appointment of a third-party contractor to rectify the defects, full charging of costs to the final account, or calling in the collateral.
Occurrence of a serious defect threatening the operation of the workWater infiltration through the roof or technical piping failure occurring between the second and fifth year after formal acceptance of the work.Immediate technical inspection, establishment of the hidden nature of the defect, detailed notification to the contractor pursuant to the duty to notify under the Code of Obligations (CO), summons to the site within 48 working hours for a joint examination.Preservation of the five-year warranty, protective ordering of emergency safeguards, joint technical expert assessment to determine the origin of the defect without loss of rights.
Occurrence of bankruptcy or cessation of business of the contractorBankruptcy declared by the competent judge or liquidation of the general contractor or trade contractor holding the package before the end of the five-year period.Identification of the bankruptcy authority (bankruptcy office), filing of the claim for rectification or damages, formal demand to the banking institution or insurance company issuing the joint and several guarantee.Transfer of the financial claim to the autonomous security, assessment of any shortfall in the guaranteed amount (capped at 5% or 10%), and adjustment of the client's maintenance budgets.
Dispute over the cause: normal wear and tear vs execution defectPremature degradation of floor/wall finishes or electromechanical malfunction during the fourth year of operation.Examination of maintenance logs, verification of compliance with manufacturers' instructions and trade standards, analysis of room use compared to the as-built documentation.Rejection of the notice of defects if the required maintenance was neglected by the client, or confirmation of the warranty obligation if an initial defect in assembly or material selection is demonstrated.

Procedures for site management in the event of contractor default

When the contractor disputes its warranty obligation or fails to rectify the notified defects, site management cannot automatically commission a third-party contractor without complying with the preliminary steps laid down by applicable law. Whether the work is governed by the contract for work under art. 363 CO or by the provisions of standard SIA 118, a rigorous procedure must be followed.

Site management begins by recording the facts precisely: time-stamped high-resolution photographs, location on construction drawings, record of collateral damage, and financial estimate of the repairs. A formal notice is then sent to the contractor, setting an appropriate deadline to carry out the remedial work. This letter must clearly specify the alleged defects, leaving no technical ambiguity. Under art. 102 CO, the debtor is placed in default by formal notice from the creditor, which formally establishes the contractor's liability for delays and resulting losses.

If the appropriate deadline set in the summons expires without tangible progress, the client is entitled to have the necessary work performed by a third party at the initial contractor's expense and risk. In disputes concerning monetary obligations arising from the recovery of these costs or from culpable delay, art. 104 CO provides that default interest of 5% per annum applies in the event of default on payment of a sum of money, unless a higher interest rate has been stipulated in the contract. This statutory basis strengthens the client's financial position when settling remedial accounts.

Relationship between the warranty certificate and the release of retentions

The administration of financial collateral is central to site management's prerogatives upon the expiry of warranty periods. Managing these instruments requires strict documentary discipline. Whether dealing with cash retention money on advance payments or the provision of a joint and several guarantee deed issued by a bank or insurance company established in Switzerland, release cannot take place until all reservations are fully cleared.

For a contract requiring a performance guarantee, the value of the security usually ranges from 5% to 10% of the total cost of the work or awarded package. As the end of the two-year warranty period approaches, site management draws up an exhaustive summary of outstanding notices of defects. Two courses of action are available:

  • Unconditional expiry: If all defects recorded upon acceptance of the work and during the two-year warranty period have been fully rectified, site management prepares a two-year closing record and issues a release certificate addressed to the client and the guarantor, authorising the return of the original guarantee deed.
  • Extension or calling of the guarantee: If defects notified in due time remain unrectified or are subject to an ongoing dispute, the release is formally suspended. Before the deed's expiry date, site management notifies the guarantor of a pending claim in liquidation to prevent automatic lapse of the instrument. If the contractor refuses to perform, the client calls on the financial guarantee to cover the cost of substitute quotes.

Illustrative practical cases (typical scenarios on Swiss construction sites)

The figures and amounts presented in the scenarios below are illustrative examples intended to clarify decision-making mechanisms on Swiss construction sites and do not correspond to any actual project.

Scenario 1: Residential building of 18 condominium ownership units in Lausanne (Canton of Vaud)

On this new-build project representing a total construction volume of around 8 200 000 CHF excluding taxes (approx. 8 864 200 CHF including Swiss VAT of 8,1 %), site management coordinates a design team and oversees an average workforce of 25 workers on the construction site. The contract for flat roof waterproofing and Sheet-metal Work was awarded for a lump-sum amount of 320 000 CHF excluding taxes. The contract for work incorporates standard SIA 118 and requires the provision of a joint and several guarantee for 10% of the package value, i.e. 32 000 CHF, issued by a top-tier Swiss bank.

Acceptance of the work takes place in May. During the joint inspection, the minutes record the absence of major reservations regarding the roofs, thereby starting the two-year trial period. During the first 24 months, no anomalies are observed on this package. Twenty-two months after acceptance of the work, site management commissions a visual audit before the two-year deadline, in accordance with best practice. This joint inspection, carried out in the presence of the waterproofing contractor, confirms that the multi-layer systems and upstands appear to be in perfect condition.

However, 38 months after acceptance of the work (in the third year of operation), water infiltration occurs on the ceiling of the top-floor apartment during heavy rainfall. The condominium ownership administrator refers the matter to site management to investigate the incident.

The technical and procedural course of action chosen by site management proceeds according to the following rules:

  • Characterisation of the defect: As the damage appeared after the two-year period, it is no longer governed by the ordinary complaints regime under standard SIA 118, but falls into the category of hidden defects under the five-year warranty.
  • Prompt notification: As soon as the co-owner reports the incident, site management conducts an emergency inspection with targeted destructive testing. The expert report reveals internal delamination of a waterproofing membrane caused by an insufficient welding temperature during installation, a defect that could not be detected during earlier surface inspections. The notice of defects is sent to the contractor by registered post within the statutory time limit, detailing the exact location, the nature of the defect, and the resulting interior damage estimated at approximately 18 500 CHF including 8,1 % VAT.
  • Demand and formal notice: The contractor having initially alleged a blocked rainwater pipe attributable to a lack of maintenance, site management provides the semi-annual gutter cleaning reports completed by the building caretaker. Faced with this conclusive evidence, the contractor is issued a formal notice to perform the repairs within 15 days.
  • Managing the limitation risk: With the five-year warranty expiring 22 months later, site management closely monitors the timeline. Faced with delays by the contractor's civil liability insurer, the client requests and obtains from the firm a written waiver of the statute of limitations for a period of one year, thereby eliminating the risk of rights lapsing before repairs are completed.

Thanks to this procedural rigour, the contractor carries out the waterproofing remedial work and covers the repairs to damaged plaster and paintwork in the apartment, fully protecting the client's budget.

Scenario 2: Administrative and logistics building in Meyrin (Canton of Geneva)

This project involves a logistics and commercial centre with an award value of 14 500 000 CHF excluding taxes (around 15 674 500 CHF including 8,1 % VAT). The structural work and reinforced concrete package alone represents 4 800 000 CHF excluding taxes. The contract is governed by the Code of Obligations (CO) and the general conditions of standard SIA 118. A 5% financial retention money was converted upon acceptance of the work into a 240 000 CHF insurance joint and several guarantee certificate, expiring strictly two years to the day after the date of acceptance without major reservation.

The construction site workforce during the execution phase reached up to 40 workers under the supervision of a lead site engineer. Eighteen months after the client took possession of the building, the operator reports abnormal transverse cracks on the ground-floor industrial slab used by forklift trucks, as well as concrete spalling along the expansion joints.

Faced with this progressive deterioration, site management implements the following intervention strategy:

  • Protective measures and structural assessment: Site management tasks the project structural engineer with installing crack monitoring gauges and checking crack width. The technical analysis shows that the upper reinforcement spacers did not maintain the required concrete cover during pouring, causing localised settlement under moving loads.
  • Formal notice within the two-year period: The notice of defects is served on the structural work contractor before the two-year period expires. The notice requires the complete restoration of the joint edges using reinforced epoxy resin grout and the underpinning of settled zones, based on an estimated quote of approximately 85 000 CHF including VAT.
  • Opposition to guarantee release: Because the contractor disputes the repair method and attempts to delay matters until the two-year anniversary date, site management immediately files a formal opposition with the insurance company that issued the joint and several guarantee. This action suspends any release of the 240 000 CHF guarantee, holding the collateral for the benefit of the client.
  • Execution by substitution: As the contractor continues to refuse to implement the repair option approved by the structural engineer, the client obtains two comparative quotes from firms specialising in structural remediation. Following a final formal notice granting a deadline of 10 working days, the defaulting contractor is notified that the works are being assigned to a third party. The total invoice of 92 400 CHF (including 8,1 % VAT) is directly covered by a partial call on the insurance guarantee, with the remaining balance withheld until the performance of the remedial work has been verified.

This oversight prevents any financial loss for the client and guarantees the continuity of the building's logistics operations without disrupting indoor traffic.

Operational checklist for managing warranties

Site management exercises systematic control over all chronological and documentary milestones for each construction package. The following list summarises the essential checks to carry out between the day of acceptance and the end of the fifth year:

  • Phase of acceptance of the work (Day D):
    • Drafting of the joint formal record signed by the client, site management and each successful contractor.
    • Detailed recording of the list of visible reservations and defects, assigned for each item a precise rectification deadline (usually 30 to 60 days).
    • Exact calculation of the retention money or verification of the compliance of the text of the deed of joint and several guarantee provided in replacement.
    • Immediate notification of the formal record to guarantor institutions whenever contractual terms require it for the securities to take effect.
  • During the two-year testing period:
    • Maintenance of a centralised register of notices of defects recording the date of occurrence, date of notification, responsible contractor, date of intervention and sign-off on clearance.
    • Strict monitoring of the clearance of initial reservations from the acceptance record: on-site inspection and signing of a joint completion voucher.
    • Organisation of intermediate site visits as soon as a recurring issue is reported by occupants or building technical management.
    • Periodic verification of the apparent solvency of successful contractors and the ongoing validity of deposited bank guarantees.
  • Two-year closing audit (at the latest at 22 months):
    • Formal convening of contractors and the client to a full joint inspection visit of the work.
    • Drawing up of the biennial audit report listing defects that have appeared during the first two operating years.
    • Serving formal notice on the contractors concerned to clear all open items before the exact two-year expiry date.
    • In case of non-performance: formal block on the release of the guarantee by reasoned written notification sent to the financial guarantor.
    • In case of full compliance: issuance of the guarantee release certificate for the portion eligible for release at two years.
  • Monitoring of the five-year period (from 2 to 5 years):
    • Rigorous application of the procedure for hidden defects: inspection, technical qualification and written notification to the contractor immediately upon discovery.
    • Ongoing watch over concealed elements of waterproofing, structure, thermal insulation and embedded building services.
    • Status review at 4 and a half years (54 months after acceptance) to record any structural defects before the limitation period expires.
    • Execution of acts interrupting the limitation period or securing written waivers of the defence of the limitation period before the fifty-ninth month.

Common site management mistakes and their consequences

Managing guarantees is an area where procedural lapses lead to irreversible financial losses. Analysis of disputes on Swiss construction sites highlights several typical mistakes made by professionals:

Site management errorProcedural breakdown mechanismLegal and financial consequence
Verbal reporting or simple email without acknowledgment of receiptReporting defects by telephone or informal message without proof of the date received by the contractor.Contractor challenges the timeliness of the notice of defects; client claims rejected due to formal forfeiture of rectification rights.
Confusion between the biennial testing period and the five-year limitation periodMistaken belief that reporting hidden defects can wait until the end of the fifth year to be bundled together.Irrevocable loss of warranty rights for hidden defects not notified promptly upon actual discovery by the client or its agents.
Failure to formally block the bank guaranteeAbsence of written notification to the guarantor before the expiry date on the security deed, while two-year defects remain pending.Automatic lapse of the guarantee deed by the bank or insurer; loss of financial security and client forced to bear rectification costs if the contractor proves insolvent.
Spontaneous performance of substitute works without prior warningOrdering repair work from a third-party firm without previously serving formal notice on the appointed contractor or setting a reasonable deadline.Refusal of cost coverage by the original contractor; client unable to backcharge incurred costs due to non-compliance with statutory substitute performance rules.
Neglecting the expiry of the five-year limitation periodPassively awaiting a reply from a contractor or their civil liability insurer past the strict 5-year limit without an act of interruption.Complete expiry of all warranty claims for defects under the limitation period; definitive dismissal of any claim for compensation or action before the courts.
Improperly treating a lack of maintenance as a construction defectReporting mechanical degradation caused by lack of periodic servicing of installations without checking the maintenance log.Rejection of the claim by the contractor, invoicing of unnecessary technical expert fees and damaged contractual relations with no benefit to the client.

Pitfalls in drafting the guarantee deed

Special vigilance is required when examining the deed of joint and several guarantee issued by the bank or insurance company upon releasing the retention money on the final bill. Practitioners frequently encounter restrictive clauses inserted by guarantor institutions into their standard forms. These restrictions include requiring prior debt enforcement proceedings against the contractor before calling on the guarantor, or introducing an automatic termination clause on a fixed date regardless of any notices of defects served.

Site management must ensure that the wording of the deed expressly confirms the guarantor's joint and several undertaking, allowing the client to claim payment directly for the amounts due if the contractor defaults. Furthermore, the document must state unequivocally that if a notice of defects is served before expiry, the guarantee remains in force until full, joint settlement of the dispute, without the passage of calendar time extinguishing the security obligation.

Monitoring over time, record keeping and evidentiary archiving

Effective management of guarantees relies on a rigorous archiving and traceability system spanning a minimum of ten years following the acceptance of the work. Administrative, technical and contractual documents must be kept in an accessible and orderly form to meet evidentiary requirements in late-stage judicial disputes.

Compiling the guarantee archive file

Upon completion of the construction site, site management compiles a specific guarantee file for each trade package containing the following documents:

  • Core contract file: The original works contract, its priced addenda, the itemised quote by cost classification chapters, as well as particular conditions of contract setting out the applicable warranty schemes.
  • Original security documents: Joint and several guarantee certificates issued by banks or insurers, letters of acceptance and any extension addenda. These original documents must be stored in a physical safe or a secure digital archiving system compliant with federal statutory book-retention requirements.
  • Acceptance records: The signed original formal records, accompanied by the exhaustive list of reservations, plan annexes marking defect locations and timestamped condition photographs.
  • Chronological defect register: The consolidated dashboard tracking every reported issue, copies of registered letters containing notices of defects with postal receipts, joint inspection sign-offs on reservation clearance and work orders signed by contractors.
  • As-Built Documentation (DOE): As-built drawings, manufacturers' technical manuals, technical data sheets of installed materials, as well as servicing and maintenance logs handed over to the building operator.

Periodic updates and handover of management

During the five years following acceptance, the guarantee tracking schedule must undergo a systematic half-yearly review by site management. This review helps identify critical anniversary dates: the 60-day reservation clearance deadline, the joint audit before the 24th month, the partial or total release of guarantees, and the end of the five-year limitation period.

When the site management mandate ends after the physical execution phase or after the two-year warranty closes, a formal handover of responsibilities and archives must be carried out for the client or their property manager. This transfer takes place through the signing of a handover record detailing the progress of each open reservation, the location of original guarantee deeds, and the precise schedule of preservative steps required to safeguard the client's rights against hidden defects and the risk of limitation periods expiring.

00:00 - 00:15

AI Avatar: Hello. In Switzerland, dozens of site managers lose their clients' warranty rights every year because of a late notice or an improperly interrupted limitation period. Let us explore together how to protect your construction sites under the rules of the Code of Obligations (CO) and standard SIA 118.

00:15 - 01:10

Screen and Diagrams: On-screen diagram: comparative timeline of notification periods - 60 days under the Code of Obligations (CO) versus the two-year regime under standard SIA 118, followed by the five-year limitation period.. Voiceover: At the time of acceptance, the distinction between apparent and hidden defects determines the burden of proof. View our operational analysis matrix: during the first two years under a contract applying standard SIA 118, defects may be reported at any time, with the contractor obliged to prove the conformity of their work. From the third year onwards, the regime shifts, placing the strict burden of proof on the client. On-screen application demonstration: demonstration of the Art Construction deadline calculator.. We input the exact date of acceptance of the work, the total final account amount of 1 200 000 CHF, and the guarantee rate set at 10 %. The tool automatically calculates the two-year milestone, the notification schedule, joint inspection reminders and the crucial five-year limitation period deadline, exportable in universal calendar format for your team.

01:10 - 01:30

AI Avatar: Leave guarantee deadlines and financial securities to chance no longer. Download your joint inspection report templates right away, use our deadline calculators and join our specialist module in the Art Construction Academy to master all aspects of Swiss construction law.

Contracts and SIA 118: free tools

Advance payments and retentions, surety bonds, price escalations, daywork reports, subcontractor monitoring.

View the contracts and SIA 118 tools

Frequently asked questions

What is the exact scope of the two-year notification period under standard SIA 118 compared to the Code of Obligations?

Under the contractual framework of SIA 118, the client benefits from an initial two-year complaint period during which defects arising may be notified at any time, without forfeiture linked to accidental discovery. Conversely, the statutory regime of the Code of Obligations (CO) imposes a duty of prompt notice following inspection. The statutory revision in force since 2026 now grants a mandatory 60-day deadline to give notice of defects in an immovable construction, ruling out any more restrictive contractual limitation. Incorporating SIA 118 therefore provides major operational flexibility for the technical supervision carried out by the site management. To illustrate this dynamic, consider a corrective intervention estimated at 45 000 CHF on a cracked screed. Under a standard works contract governed by federal legislation, exceeding the 60-day notification deadline results in the forfeiture of defect rights. Under Swiss Society of Engineers and Architects rules, the contractor remains fully bound to carry out the rectification as long as the two-year deadline has not expired.

How must the site management formally organise the joint inspection before the two-year warranty expires?

The site management must schedule the final inspection at least three months prior to the two-year expiry, issuing a notice by registered mail with acknowledgement of receipt to all contractors and consultants concerned. This step ensures the joint nature essential to establishing liability. During the site walkthrough, an exhaustive record logs each disorder observed, its exact location and its impact on the works. Consider the example of an office building construction site where peripheral water seepage requires rectification works illustratively estimated at 85 000 CHF. The joint inspection report provides an accurate inventory of the defects, sets a formal performance deadline for the remedial works and details the arrangements for the follow-up inspection. The document is signed on the spot by all parties present. If a contractor refuses to countersign or disputes causation, the document is served by registered post within forty-eight business hours. This rigorous protocol preserves the owner's rights in full and paves the way, where necessary, for calling the financial guarantee or initiating court proceedings.

What conditions govern the release of a contractor's joint and several guarantee?

Releasing a joint and several guarantee issued by a prime bank or insurance company requires the formal extinction of warranty obligations or the prior consent of the client. Under SIA 118 rules, the financial security, generally set between 5 % and 10 % of the final account amount, guarantees proper performance and the rectification of defects emerging during the first two years. If a disorder is recorded at the end of this period, the site management refuses to grant the release for the disputed share. As a numerical illustration, consider a guarantee balance of 60 000 CHF withheld because of external joinery malfunctions valued at 28 000 CHF. The client releases the remaining 32 000 CHF via a partial certificate, retaining the residual bank holdback until technical reservations are fully and verifiably lifted. Only following the drafting of a compliant rectification report and the definitive clearance of open complaints is the final release certificate issued to the guarantor financial institution.

How do you validly notify a hidden defect discovered between the second and fifth year after acceptance?

Once the two-year complaint period specific to SIA 118 expires, defects that could not be detected during the regular inspection constitute hidden defects. They are governed by the provisions of Swiss federal construction law. The client must notify them without delay upon discovery, under penalty of forfeiture of its rectification or indemnity rights. The notice must specify the exact nature of the failure, its location and its observed physical extent. Consider a typical case where a basement waterproofing failure causes water ingress in the second basement level, with remedial works illustratively costed at 120 000 CHF. The notice must be served by registered letter with photographic evidence and an expert engineer's technical findings, calling upon the firm to carry out the repair. Pursuant to statutory federal provisions on works contracts, contractor liability remains engaged up to the end of five years from acceptance of the works, provided the notice scrupulously respects formal and substantive diligence requirements.

How do you interrupt the five-year limitation period to preserve the client's rights?

The five-year limitation period applicable to immovable constructions is triggered by acceptance of the works and expires on the fifth anniversary date if no formal interruptive act has occurred. A simple written complaint, a construction site report or an informal reminder by no means suffices to stop the statutory clock. To prevent the extinction of rights, the Code of Obligations (CO) provides specific remedies, including the service of an order to pay through the debt collection office or the filing of a conciliation request before the competent civil court. Alternatively, the builder or designer may issue a formal written waiver of the statute of limitations defence for a specified duration, not exceeding ten years per declaration under the rules of the law of obligations. In a situation where complex technical expert appraisals regarding slab settlement estimated at 250 000 CHF drag on, obtaining such a formal waiver protects the client's claims without requiring the immediate initiation of particularly costly court litigation.

What are the respective liabilities of the contractor and the engineer in the event of a structural defect?

When a pathology affects structural elements, such as undersized reinforcement or non-compliant concrete placing, the general contractor or masonry contractor and the civil engineer incur separate and joint liabilities. The contractor answers for the proper quality of its materials and technical execution under the works contract. For its part, the civil engineer is subject to Swiss mandate law rules, demanding utmost diligence and proper inspection of the reinforcement prior to concreting. Should major disorders arise, representing for example footing consolidation works valued purely indicatively at 340 000 CHF, the client takes action against both parties based on their respective contractual duties. Moreover, any qualified breach of the recognized rules of construction that knowingly endangers life or bodily integrity falls directly under art. 229 CP, engaging the individual criminal liability of those responsible for managing or executing the structure.

Can a contractual clause limit the right to rectify defects in a new building?

Under the revised Swiss construction defect law in force since 2026, contractual freedom is strictly curtailed to benefit the purchaser and the client. Any prior agreement aimed at excluding, restricting or unduly deferring the right to rectify an immovable work is null and void if the defect affects a construction. Previously, general contracts sometimes imposed a mere assignment of subcontractors' warranties or restricted remedies to modest financial compensation. Such arrangements are no longer lawful under Swiss private law. In a situation illustrating a ventilated insulated facade disorder where total rectification is valued at 180 000 CHF, the contractor cannot invoke any derogation clause signed in the main contract. The client may demand full on-site rectification at the defaulting builder's sole expense, provided the costs incurred are not disproportionate to the objective benefit gained by the owner of the remediated building.

What happens to securities and guarantees if a firm goes bankrupt during the warranty period?

The opening of bankruptcy proceedings against a contractor holding a construction contract results in the immediate cessation of its operations and the physical impossibility of discharging its remedial duties on the site. In this event, the paramount interest for the client lies in holding a joint and several guarantee issued by a solvent third party, whether a bank or an insurance company regulated by Swiss law. The guarantor is not released by the contractor's insolvency: it remains bound, under its joint and several security, to satisfy the debt up to the guaranteed amount specified in the certificate. If a roof defect illustratively estimated at 75 000 CHF occurs on a property development after bankruptcy is declared, the client immediately calls upon the financial guarantor to obtain the funds required for substitute performance. In parallel, any balance uncovered by the guarantee must be duly lodged as a claim on the schedule of claims with the bankruptcy office handling the general liquidation of the debtor.

Rigorous control of two-year and five-year warranty periods, meticulous management of hidden defects and proactive tracking of guarantees form the intangible pillars of top-tier site management across Switzerland. Between the contractual rules of SIA 118 and the mandatory framework of the Code of Obligations (CO), methodological rigor safeguards the client's investments and diffuses major financial disputes. To explore each operational and legal aspect of your construction sites in greater depth, consult our dedicated technical guides: