The 3 Major Site Risks
- Financial / Margin: Forfeiture of rectification rights due to late notice, transferring the full cost of complex remediation to the client (on the order of 40'000 CHF to over 150'000 CHF by way of illustration for basement tanking or building services), in accordance with the limitation period rules under art. 371 CO and the defect scheme under standard SIA 118.
- Legal / Joint bodies / SUVA: Reclassification of the defect as an apparent defect due to lack of conclusive evidence upon discovery, leading to deemed acceptance of the work under art. 370 CO and engaging the professional liability of the site management toward its principal for breach of duty of care.
- Administrative / Acceptance: Contractual remedies blocked and contractor refuses to intervene due to imprecise notice failing to meet the requirements for technical description and formal summons under the Code of Obligations (CO) and standard SIA 118.
The period between the end of the second year following acceptance and the end of the fifth year is a critical phase for monitoring real estate works in Switzerland. Once the two-year notice period under standard SIA 118 expires, its facilitative default regime ceases to apply. Deficiencies that appear subsequently are classified as hidden defects: they no longer benefit from the option of being reported at any time until the two-year deadline. For construction professionals, particularly clients and site management, managing this period requires strict procedural discipline to prevent the forfeiture of the client's rights.
Since 1 January 2026, art. 367 CO sets a sixty-day deadline to report defects in an immovable work after their discovery, a provision that applies alongside the contractual rules of standard SIA 118. As soon as a defect that was undetectable during the initial inspection comes to light, notice must be given without unjustified delay, in a documented and explicit form. The operational challenge lies in establishing the burden of proof, classifying the non-conformity accurately, and serving compliant notice to the contractor before the five-year limitation period under art. 371 CO has expired.
Legal framework for hidden defects after two years: interaction between SIA 118 and the revised CO
In Swiss site management practice, the relationship between standard SIA 118 and the Code of Obligations undergoes a critical shift upon expiry of the two-year claim period. During the first two years following acceptance of the work, the client benefits from the ability to notify defects at any time, without risking forfeiture simply through the passage of time. Once this two-year milestone is passed, this advantageous regime ends. Defects emerging between the start of the third year and the end of the fifth year fall under the strict rules governing hidden defects.
Acceptance of the work releases the contractor from liability for apparent defects not reported during verification, pursuant to the principles laid down in art. 370 CO. Only defects undetectable during ordinary inspection or intentionally concealed by the contractor remain covered by statutory warranty rights. For these hidden defects, the revision that came into force on 1 January 2026 amends general statutory law: for an immovable work, the client has 60 days to report defects after their discovery, under art. 367 CO. Standard SIA 118 also requires notification immediately upon discovering a hidden defect, requiring site management to maintain thorough traceability from the very first signs of an anomaly.
Under art. 368 CO, the client may claim rectification, a price reduction, or damages, and any clause restricting the right to repair is void for building works. These rights become time-barred under art. 371 CO after five years for defects in an immovable work as against the contractor, the architect, or the engineer. This five-year limitation period cannot be modified to the detriment of the client, firmly locking in the coverage period.
Valid notice procedure: method and formal requirements
To preserve all of the client's legal rights, the notice of defects must meet strict formal and substantive requirements. An informal message via phone or a brief mention in site meeting minutes does not constitute formal notice within the meaning of contract law for works.
The site management must formalise the notice in writing by registered mail, including a detailed description of how the defect manifests itself. This technical description must state the precise location, the symptoms observed, any secondary physical damage identified, and the history of appearance. The notice must explicitly state that the client does not accept the work as compliant and declare the formal intention to hold the contractor liable for its obligations under art. 364 CO.
The document must contain a clear summons inviting the contractor to conduct a joint on-site inspection and carry out rectification works. Under art. 366 CO, if repairs are not carried out properly through the fault of the contractor, the client may set a reasonable deadline, warning that, once that deadline expires, the work will be entrusted to a third party at the contractor's expense and risk. This substitute performance mechanism protects building operations without sacrificing rights.
Comparison table: defect management according to the warranty period
The table below summarises the procedural differences between the initial two-year regime and the subsequent phase running from the second to the fifth year after acceptance.
| Assessment criterion | Initial two-year period (0 to 2 years) | Hidden defects period (2 to 5 years) |
|---|---|---|
| Notice regime | Notice possible at any time until the two-year deadline under standard SIA 118 | Notice required upon discovery, 60-day period for an immovable work under art. 367 CO |
| Nature of covered defects | Reserved apparent defects and defects discovered during operations | Hidden defects only, undetectable during initial inspection (art. 370 CO) |
| Burden of proof | Presumption linked to performance during the contractual warranty period | The client must prove the hidden defect, its pre-existence to acceptance, and the date of discovery |
| Financial securities | Warranty or joint and several guarantee generally active under the contract | Frequent release of securities after 2 years; reliance on the contractor's direct solvency |
| Extinctive limitation | Action suspended or active within the contractual two-year period | Statutory 5-year limitation period for an immovable work under art. 371 CO |
Common procedural mistakes and financial impacts on site
The most common mistake made by site management or the client is delaying action following the discovery of a technical defect. When facing intermittent water ingress or structural cracking, waiting for the damage to worsen before taking action risks outright dismissal of the claim. If the contractor proves that the condition was known for a period exceeding the notice deadline, the defect is deemed accepted under art. 370 CO. The financial damage is direct: remediation costs for a plant-room flat roof or basement tanking, running on the order of 60'000 CHF to 140'000 CHF by way of illustration, fall entirely on the owner.
A second recurring omission is failing to set a formal deadline backed by default warnings. Demanding action verbally without relying on art. 366 CO prevents commissioning remediation by a third-party firm at the defaulting contractor's expense. Finally, failing to perform acts that interrupt the limitation period under art. 135 CO (such as debt enforcement proceedings or an application for conciliation) or obtaining a written waiver of the limitation defence under art. 141 CO before the five-year deadline of art. 371 CO permanently extinguishes all legal claims, leaving the client to finance complete remediation works.
Illustrative practical cases (typical scenarios on Swiss construction sites)
The figures and situations described below are illustrative examples designed to clarify the application of contractual and statutory rules on construction sites.
Scenario 1: Basement water ingress in a residential building (Vaud)
In a 24-unit residential building in the canton of Vaud, three years and four months after acceptance of the work, damp patches appeared on the earth-retaining wall in the second basement. The work was carried out by a general contractor deploying an average workforce of 18 workers during the structural work. The works contract is governed by standard SIA 118.
The site management retained an engineer to instrument the area. As soon as a failure of the construction joint waterbars was technically confirmed (a defect undetectable upon initial acceptance), formal notice by registered mail was sent to the contractor within twenty days. The document detailed the moisture readings, called upon the contractor to carry out exploratory openings, and set a 30-day intervention deadline pursuant to art. 366 CO. Given the contractor's failure to act, the client had resin injection works carried out by a specialised firm for an amount on the order of 48'000 CHF, seeking full reimbursement from the main contractor on the basis of its execution liability.
Scenario 2: Debonding of self-levelling screed in a trade park (Fribourg)
In a 1'500 m² workshop in the canton of Fribourg, four years after taking possession of the premises, cracking and spalling appeared across the interior floor slab. The work had been carried out by a plastering and screeding contractor employing 8 workers during this phase.
The expert assessment revealed improper binder dosing and the lack of a bonding agent compliant with technical standards. This defect in materials and execution engaged the contractor's liability under art. 365 CO and art. 364 CO. The client gave notice of the defect 15 days after receiving the technical report. Because the contractor requested time to check its insurance coverage, the client insisted on the formal signing of a declaration of waiver of the statute of limitations under art. 141 CO, preventing expiry of the five-year limitation period provided for in art. 371 CO. The parties subsequently agreed on a protocol for complete milling and resurfacing, estimated for illustrative purposes on the order of 95'000 CHF, carried out on a time and materials basis under the supervision of the site management.
Contracts and SIA 118: free tools
Advance payments and retentions, surety bonds, price escalations, daywork reports, subcontractor monitoring.
Frequently asked questions
What deadline applies to report a defect that appears in year four under standard SIA 118?
After two years, the hidden defects regime applies under standard SIA 118. Notice must be given immediately upon discovery to preserve the client's rights. Illustrative remediation costs of 18 000 CHF remain recoverable provided formal notification satisfies contractual duty-of-care requirements.
Does the 60-day deadline of art. 367 CO apply if the SIA 118 standard governs the contract?
SIA 118 takes precedence as a specific agreement. However, art. 367 CO sets a baseline framework for immovable structures. As a precaution for damage estimated at 35 000 CHF, notifying the defect without delay secures remediation without risking forfeiture against the contractor's arguments.
What are the client's rights if a hidden defect compromises basement waterproofing?
Under art. 368 CO, the client may demand remediation of the work or a price reduction. If corrective work amounts to, say, 42 000 CHF, the contractor must repair it at their own expense, unless the cause of the damage is attributable to the client.
How does the five-year limitation period under art. 371 CO tie in with the defect notification?
Art. 371 CO sets the limitation period for claims regarding an immovable structure at five years from acceptance. The notification of the hidden defect must occur before this expiry date. For a representative dispute of 60 000 CHF, any legal action or debt enforcement must be initiated before this five-year deadline.
Can the contractor refuse to repair a crack that appeared in year three?
The contractor cannot refuse if the defect was undetectable at acceptance under art. 370 CO. For an estimated remediation cost of 12 500 CHF, the right to repair remains guaranteed under art. 368 CO, provided the client did not delay once the defect was actually discovered.
How can you validly interrupt the five-year limitation period for a defect notified after 4.5 years?
Art. 135 CO allows interrupting the limitation period through debt enforcement, an application for conciliation, or a written acknowledgement of debt. For an illustrative claim of 85 000 CHF, a mere formal notice letter is not sufficient to halt the expiry of the statutory deadline under art. 371 CO.
Rigorous management of hidden defects ensures the technical durability of structures and preserves financial guarantees. To explore warranty management and project traceability in greater depth, see our specialised guides:
- Warranty Site Management in Switzerland: 2-Year / 5-Year Deadlines, Surety Bonds and Latent Defects (SIA 118 / CO 2026)
- 2-Year Defect Notification Period (SIA 118) vs 60-Day Notice Period in Revised CO 2026: Burden of Proof
- Joint Inspection Prior to the 2-Year Warranty Expiry: Full Protocol to Safeguard the Client's Rights
- Performance Joint and Several Guarantee (SIA 118): Amount (5% to 10%), Duration and Release Terms