The 3 Major Site Risks
- Financial / Margin: Forfeiture of the right to rectification under art. 368 CO due to lack of timely notice, forcing the client to bear remedial costs that can illustratively range from 5 % to 15 % of the construction cost, or over 120 000 CHF on a mid-sized construction site.
- Legal / Joint body / SUVA: Judicial dismissal of claims due to late notification if the contractual regime is wrongly determined, since art. 370 CO provides that tacit or express acceptance of the work releases the contractor from liability for recognizable defects not reported within statutory or contractual deadlines.
- Administrative / Acceptance: Forfeiture of warranty rights and premature release of bank guarantees due to confusion between the 60-day statutory period of art. 367 CO and the derogatory two-year notice period at any time under standard SIA 118, blocking the final statement of account.
Managing notices of defects on a construction site in Switzerland requires a strict distinction between the default regime of the Code of Obligations (CO) and the contractual clauses of standard SIA 118. The entry into force on 1 January 2026 of art. 367 CO grants the client a 60-day deadline to give notice of defects identified after the handover of an immovable work, rendering void any shorter contractual period. This revision shifts the traditional balance by extending the statutory notice period, while still requiring verification as soon as feasible. For site management and site supervisors, the key challenge is identifying precisely which framework governs contractual relations to safeguard warranty claims and avoid formal forfeiture.
Incorporating standard SIA 118 into the construction contract introduces a specific regime that departs from statutory law: during the two-year notification period starting from acceptance of the work, defects can be reported to the contractor at any time. This temporal flexibility comes with a crucial shift in the burden of proof, requiring the contractor to prove the conformity of the work against defects notified during this period. Conversely, under the sole scope of art. 367 CO, the burden of proof rests from the outset on the client, who must establish the existence of the defect, that it is attributable to the contractor, and strict compliance with the 60-day notice period. Construction managers must master these differences to conduct joint inspections, draft minutes, and safeguard the five-year limitation period under art. 371 CO.
Applicable legal frameworks: SIA standard 118 vs statutory law
On a construction site governed solely by statutory rules, tacit acceptance of the work represents the main risk for the client. Upon delivery, art. 367 CO requires the condition of the construction to be examined as soon as possible. For an immovable work, the client has a 60-day period to notify identified defects, failing which the work is deemed accepted under art. 370 CO with respect to all unnotified apparent defects. Conversely, contractually adopting standard SIA 118 changes this timeframe by establishing a two-year notification period starting upon acceptance. During this two-year phase, the client can issue a notice of defects at any time, removing the risk of tacit acceptance resulting from the expiry of a short notice deadline.
This contractual distinction directly affects the inspection duties incumbent on site management. Under standard SIA 118, defects arising or detected during the initial two-year period may be compiled and sent in writing to the contractor, without the client's temporary inaction forfeiting their legal remedies. By contrast, under the Code of Obligations (CO) without standard SIA 118, each discovery of an apparent defect triggers the individual 60-day deadline laid down in art. 367 CO. Proving notice within that window rests entirely on the client, making site reports and minutes critical to date when defects first appeared.
Burden of proof and qualification of defects
The burden of proof varies substantially depending on whether the dispute falls within the two-year notification period of standard SIA 118 or under the ordinary regime of the Code of Obligations (CO). During the first two years following acceptance under standard SIA 118, a factual presumption supports the client: once a deviation from the contract is shown, the contractor must demonstrate that the work was carried out in accordance with recognized trade standards and that no fault is attributable to them, or that the cause lies in the ground designated by the client pursuant to art. 365 CO.
Upon expiry of this two-year period, or as of handover under statutory law for non-apparent issues, the rules governing latent defects apply. From then on, the client bears the full burden of proof. The client must prove:
- The physical non-conformity of the work in relation to contractual requirements or recognized technical standards;
- That the defect was undetectable during the initial inspection of the work carried out with due diligence;
- The exact date on which the latent defect was actually discovered;
- That the notice of defects was dispatched within the 60-day statutory period set out in art. 367 CO for immovable works, or immediately upon discovery if standard SIA 118 applies to latent defects.
If the contractor claims that the defect was detectable upon delivery or that it results from a lack of maintenance on the part of the operator, site management must supply technical records, site photographs, and the site journal to prove that the defect was invisible during the joint acceptance inspection.
Comparative overview of warranty and notification rules
| Assessment criterion | Revised Code of Obligations 2026 (default statutory law) | Standard SIA 118 (agreed contractual clause) |
|---|---|---|
| Notice period for apparent defects | 60 days from discovery after inspection (art. 367 CO) | 2-year notification period at any time starting from acceptance |
| Consequence of failure to notify | Tacit acceptance of the work for these defects (art. 370 CO) | Client's rights maintained throughout the 2-year warranty period |
| Presumption and burden of proof (0 to 2 years) | The client proves the defect and compliance with the 60-day deadline | The contractor must establish conformity regarding the notified defect |
| Notification of latent defects | Within 60 days of actual discovery (art. 367 CO) | Notice immediately upon discovery once the 2-year period expires |
| Limitation period for warranty claims (immovable works) | 5 years from acceptance of the work (art. 371 CO) | 5 years from acceptance as defined in the construction contract |
Common management errors and financial impacts on site
Failing to send a formal notice constitutes the most detrimental mistake observed in site management. Several non-compliant practices jeopardise the client's rights:
- Verbal notice on the construction site: Pointing out a defect during a meeting without written confirmation prevents establishing the date of the notice. If contested, the contractor can invoke tacit acceptance under art. 370 CO, resulting in the loss of claims for rectification. On a flat roof waterproofing repair, uncovered remedial costs can illustratively reach 45 000 CHF to 85 000 CHF.
- Confusing the notification period with the limitation period: Assuming that the 5-year limitation period under art. 371 CO removes the need to issue a notice of defects within statutory deadlines. The limitation period bars legal action, whereas the notice deadline under art. 367 CO is a condition for the claim's validity. Forfeiture due to late notice on an underground drainage network results in replacement costs in the region of 60 000 CHF borne entirely by the client.
- Waiting out the two-year warranty without an inspection: Failing to hold the joint inspection before the two-year term expires under standard SIA 118 shifts the burden of proof back to the client for all defects appearing thereafter. Repairing a cracked screed can thus cost around 35 000 CHF with no recourse against the contractor.
- Hiring a third party unilaterally without formal notice: Entrusting remedial work to a third party without first serving a formal summons on the contractor to carry out the rectification provided for under art. 368 CO prevents the client from recovering the costs incurred, leaving a direct financial burden of roughly 20 000 CHF to 50 000 CHF.
Illustrative practical cases (typical scenarios on Swiss construction sites)
The situations and figures below are illustrative examples intended to guide site management and site supervisors when applying Swiss contractual rules.
Scenario 1: Residential building in the canton of Vaud (contract without standard SIA 118)
On an 18-unit residential construction site in Nyon, the client entered into construction contracts governed by the default statutory law of the Code of Obligations (CO), without including standard SIA 118. The work was handed over to the client on 15 March. During move-in on 10 April, water ingress appeared around the exterior aluminium joinery. Site management noted the defect on 12 April but only sent a registered letter to the window contractor on 20 June, 69 days after discovering the issue.
The contractor refused to intervene, citing late notification. Under art. 367 CO, the client of an immovable work had a 60-day period to give notice of defects. Since that period expired on 11 June, the work was deemed accepted within the meaning of art. 370 CO for this item. The client lost the right to rectification under art. 368 CO and had to fund waterproofing remedial works by a third party at an actual cost of around 48 000 CHF, with no possibility of compensation.
Scenario 2: Commercial building in the canton of Geneva (contract incorporating standard SIA 118)
In the industrial zone of Meyrin, the construction of a commercial facility involved a workforce of 35 workers. The construction contracts formally incorporated standard SIA 118. Official acceptance took place on 1 September. Over the following eighteen months, malfunctions in the HVAC thermal control system were noted by occupants. Site management logged these defects without forwarding them immediately to the building services contractor.
Twenty months after completion, site management summoned the installer and notified all technical defects recorded. The contractor contested the admissibility of the claim, invoking the 60-day statutory notice period. Because the contractual clause referring to standard SIA 118 prevailed, the client had validly exercised the right of notification within the two-year period following acceptance. The contractor remained obligated to carry out adjustments and replace defective actuators, representing an intervention estimated at approximately 32 000 CHF, at no additional cost to the client.
Contracts and SIA 118: free tools
Advance payments and retentions, surety bonds, price escalations, daywork reports, subcontractor monitoring.
Frequently asked questions
Which regime applies by default without contractual stipulation?
Without express integration of standard SIA 118, the contract for work is governed by the Code of Obligations (CO). For immovable works, art. 367 para. 1bis CO now imposes a notice period of 60 days from discovery, under pain of forfeiture of the client's rights pursuant to art. 370 CO.
Can an apparent defect be notified 18 months after acceptance under standard SIA 118?
Yes. Standard SIA 118 grants a two-year notice period during which defects, whether apparent or hidden, may be reported at any time. The notice must simply reach the contractor before the exact expiry of the two-year term, preventing forfeiture under art. 370 CO.
Who bears the burden of proof during the first two years?
Under standard SIA 118, any defect is presumed attributable to the contractor during the two-year period, leaving it to the contractor to prove the absence of fault or an exonerating cause pursuant to art. 369 CO. Under the CO, the client must prove the defect from day one.
Is a clause shortening the notice period below 60 days valid under the revised CO?
No. Under art. 367 para. 1bis CO, for immovable works, any contractual period shorter than 60 days is void. Conversely, the two-year period under standard SIA 118 remains fully valid because it extends the client's rights without restricting this statutory baseline.
How can the five-year limitation period under art. 371 CO be validly interrupted?
A simple written notice does not toll the statutory five-year limitation period provided for in art. 371 CO. The client must obtain a written waiver of the limitation period pursuant to art. 141 CO, or initiate debt collection proceedings or file a conciliation request in accordance with art. 135 CO.
Can the contractor refuse to remedy a defect claiming disproportionate costs?
The right to repair provided for in art. 368 CO is strengthened for structures: any clause restricting this right is void under art. 368 para. 2bis CO. The contractor must carry out repairs at its own expense, for example waterproofing rework estimated at 18 000 CHF for illustrative purposes.
Mastering the schedule of proof and notice periods ensures that the client's rights against builders remain fully protected. Explore our operational guides to deepen your construction site protocols:
- Warranty Site Management in Switzerland: 2-Year / 5-Year Deadlines, Surety Bonds and Latent Defects (SIA 118 / CO 2026)
- Joint Inspection Prior to the 2-Year Warranty Expiry: Full Protocol to Safeguard the Client's Rights
- Performance Joint and Several Guarantee (SIA 118): Amount (5% to 10%), Duration and Release Terms
- Hidden Defects Between Years 2 and 5 (SIA 118 / CO 2026): Rules for Valid Notice