The 3 Major Site Risks
- Financial / Margin: Unexpected double payment of a trade package representing, for example, an amount in the region of 80 000 CHF to 250 000 CHF if an unpaid subcontractor requests the provisional registration of a statutory mortgage lien of craftsmen and contractors on the property under art. 837 CC and art. 839 CC, compelling the client to deposit security to clear their parcel of land.
- Legal / Joint Body / SUVA: Joint civil liability of the contracting contractor for unpaid net minimum wages of a subcontractor under art. 5 LDét, accompanied by administrative sanctions of up to 5000 francs under art. 9 LDét in the event of a breach of the duty of due diligence, or cantonal fines under art. 18 LTN for obstructing inspections by the cantonal authority.
- Administrative / Acceptance: Blocking of final work accounting during acceptance under standard SIA 118, refusal by banking institutions to release completion guarantees, and freezing of construction loans as long as mortgage lien registrations or joint body summonses remain pending on the land register.
On Swiss construction sites, contractual management of subcontractors demands absolute documentary rigor from site management, site supervisors, and clients. Two distinct but often combined legal mechanisms directly jeopardize the financial stability of projects: on the one hand, the legal framework of the Posted Workers Act (LDét) and the Federal Act on Combating Undeclared Work (LTN), which governs the joint liability of the contracting contractor in the event of failure to pay net minimum wages and meet notification requirements; on the other hand, the property right granted to craftsmen and contractors by the Civil Code (CC), allowing the registration of a statutory mortgage lien on the owner's parcel of land to secure payment for their labor or delivered materials, even in the absence of a direct contractual relationship with the client.
Steering a construction project therefore requires the continuous exercise of a duty of due diligence under art. 8c ODét, combining formal checks prior to work on site with regular on-site attendance controls during execution. In the event of default by an intermediate contractor, coordinating prior notices, adhering to the four-month registration deadline following completion of the work set out in art. 839 CC, and ensuring financial traceability represent the only operational safeguards against joint wage claims and double payment for the same work.
Joint liability mechanisms under the LDét and LTN
On construction sites governed by Swiss rules, the subcontracting chain exposes the contracting contractor to direct financial risk. Under art. 5 LDét, the contracting contractor bears civil liability for subcontractors' failure to comply with net minimum wages and working conditions. This provision states that they are held jointly liable only to the extent that the subcontractor has previously been debt-collected without success or cannot be pursued. Art. 8a ODét specifies that the net minimum wage means after deduction of amounts payable by the worker for social security contributions, withholding taxes, and contributions stipulated in extended collective labor agreements.
To be released from this joint civil liability, art. 5 LDét provides that the contracting contractor must prove that they exercised their duty of due diligence. Art. 8c ODét specifies that this duty of due diligence requires taking the necessary contractual and organizational measures to require subcontractors to demonstrate compliance with minimum wage and working conditions. Art. 8b ODét lists the verifiable documents: posting declaration, signed statement certifying minimum wage conditions, certificate from joint enforcement bodies, or entry in a control register. In the event of a breach of the duty of due diligence under art. 5 para. 3 LDét, art. 9 LDét provides for administrative sanctions of up to 5000 francs or a ban on offering services in Switzerland for one to five years.
The prior notification requirement constitutes another safeguard. Under art. 6 LDét, the employer notifies the designated cantonal authority in writing of the information required for monitoring prior to starting the assignment, and work may only begin eight days after this notification. A breach of this notification requirement exposes the employer to an administrative sanction of up to 5000 francs under art. 9 LDét. In parallel, art. 6 LTN provides that the cantonal control body verifies compliance with notification and authorization obligations under social insurance, foreign nationals, and withholding tax legislation. Art. 18 LTN provides that anyone who opposes or intentionally obstructs inspections shall be punished by a fine.
How the statutory mortgage lien of craftsmen and contractors works (CC)
The statutory mortgage lien constitutes a real property lien granted to secure the claims of executing contractors. Under art. 837 CC, craftsmen and contractors may request the registration of a statutory mortgage lien on the property for which they supplied materials and labor, or labor only, notably for construction work, demolition of buildings, assembly of scaffolding, or securing excavations. This legal protection is mandatory; art. 837 CC specifies that beneficiaries cannot waive these statutory mortgage liens in advance.
The subcontractor holds this real property right against the property owner, even without any contractual relationship with them. While the contract for work and services between the subcontractor and the main contractor falls under art. 363 CO, the lien encumbers the client's land parcel. The exercise period is absolute: under art. 839 CC, registration of the lien may be requested from the day the craftsmen undertook to execute the work, and at the latest within four months following completion of the work. Art. 839 CC also specifies that registration takes place only if the amount of the lien is established by the owner's acknowledgment or by the court, and cannot be requested if the owner provides sufficient security. Where multiple liens are registered, art. 840 CC establishes that craftsmen and contractors rank equally among themselves, even if the registrations bear different dates.
Risk comparison matrix: LDét, LTN, and statutory mortgage lien
The table below summarizes the statutory criteria, monitoring obligations, and direct consequences on construction sites governed by Swiss law:
| Legal mechanism | Applicable statutory basis | Target debtor or guarantor | Due diligence obligation | Typical financial impact |
|---|---|---|---|---|
| Joint liability for net wages | LDét (art. 5, art. 9) and ODét (art. 8a, art. 8c) | Contracting contractor towards defaulting subcontractor | Securing joint body certificates and prior declarations | Payment of net wage arrears and sanction up to 5000 CHF |
| Notification requirement for posted workers | LDét (art. 6, art. 9) | Posting employer and supervisory chain | Verification of the eight-day notification period prior to works | Administrative fine up to 5000 CHF and suspension of operations |
| Combating undeclared work | LTN (art. 1, art. 6, art. 18) | Executing contractors and subcontractors | Cooperation during social security and work permit inspections | Cantonal fine for obstruction and construction site area shutdown |
| Subcontractor real property lien | CC (art. 837, art. 839, art. 840) | Property owner (client) | Monitoring payments across advance payments under standard SIA 118 | Depositing bank security of 50 000 to 250 000 CHF |
| Defects and subcontractor holdbacks | CO (art. 367, art. 368) and standard SIA 118 | Subcontractor towards the general contractor | Notice of defects within 60 days for immovable work | Remediation costs and holdbacks on advance payment statements |
Frequent operational errors and financial impacts
The first failure involves allowing a foreign subcontractor to intervene without respecting the waiting period set out in art. 6 LDét, which provides that work may only begin eight days after the assignment is notified. Such negligence exposes the employer to an administrative sanction of up to 5000 francs under art. 9 LDét. Concurrently, failing to check net wage payroll sheets within the meaning of art. 8a ODét forfeits the due diligence exemption under art. 5 LDét. The contracting contractor may then face wage back-payments in the region of 35 000 CHF to 90 000 CHF for a finishing work crew.
The second classic mistake concerns the monitoring of payments to subcontractors by the total or general contractor. When the general contractor collects advance payments from the client but fails to pay its own structural work or building services subcontractors, these subcontractors can take action against the real property parcel. Under art. 837 CC and art. 839 CC, the subcontractor has an absolute time limit of four months following completion of their work to request registration of their lien. To avoid a mortgage freeze ordered by the court through provisional measures, the client is frequently compelled to provide security within the meaning of art. 839 para. 3 CC in the form of a bank guarantee in the region of 100 000 CHF to 300 000 CHF, thus bearing the cost of a temporary double cash outlay.
The third mistake lies in on-site safety coordination. Art. 5 OTConst provides that the employer shall designate on each construction site a qualified person responsible for occupational health and safety who is empowered to issue directives to workers. Art. 5 para. 2 OTConst adds that any person who, through their behavior or condition, exposes themselves or endangers others must be removed from the construction site. Furthermore, under art. 4 OTConst, the employer must ensure before work begins that there is a plan detailing the necessary measures for the work they perform on the construction site. Failing to verify these documents upon a subcontractor's arrival undermines the general prevention mandated under art. 82 LAA and art. 3 OPA.
Illustrative practical cases (typical scenarios on Swiss construction sites)
The figures presented in the following cases are illustrative examples intended to model contractual risk management.
Scenario A: Finishing work posting in the canton of Vaud
On an office renovation project in Lausanne (canton of Vaud), a general contractor awards the plastering and painting trade package to a firm employing eight posted workers. During an inspection coordinated by the cantonal body under the LTN and the LDét, inspectors find that the prior notification under art. 6 LDét was submitted only three days before work actually began, in violation of the eight-day period required by art. 6 para. 3 LDét. Furthermore, the submitted wage declarations disclose pay rates below the net minimum wages defined by art. 8a ODét.
The administrative authority imposes a sanction of 4000 CHF pursuant to art. 9 LDét for failure to comply with notification rules. Because the subcontractor is insolvent and cannot be pursued successfully via debt collection, art. 5 LDét is triggered: the contracting contractor is held jointly liable for the wage shortfall amounting to approximately 42 000 CHF. Since the contracting contractor failed to demand the certificates required by art. 8b ODét and did not take the organizational steps mandated by art. 8c ODét, their duty of due diligence is not recognized.
Scenario B: Threat of a statutory mortgage lien on a rental property in Geneva
In Geneva, the construction of a residential building involved a general contractor and a subcontractor tasked with plumbing, sanitary installations, and heating for a contract amount of 180 000 CHF. Upon completing its services, the subcontractor faced non-payment by the general contractor, which entered bankruptcy proceedings. The subcontractor served formal notice and then filed an application for the provisional entry of a statutory mortgage lien of craftsmen and contractors against the client's plot, in accordance with art. 837 CC.
The application was filed 85 days after completion of the installation work, well within the four-month deadline prescribed by art. 839 CC. To prevent the formal registration of the lien in the land register, which would block bank refinancing for the project, the client exercised the option provided by art. 839 para. 3 CC: it deposited sufficient security in the form of a bank guarantee of 180 000 CHF. This amount remains frozen while the competent court rules on the merits regarding the existence of the claim. Subsequently, the client took recourse against the general contractor under art. 97 CO and art. 366 CO, but collided with the bankruptcy estate, thereby absorbing a significant net loss that could have been avoided by requiring proof of direct payment or a receipt before releasing each advance payment.
Contracts and SIA 118: free tools
Advance payments and retentions, surety bonds, price escalations, daywork reports, subcontractor monitoring.
Frequently asked questions
How does a general contractor prove its duty of due diligence under the LDét?
To satisfy its duty of due diligence and secure exemption under art. 5 LDét, the contracting contractor requires its subcontractor to provide the documents stipulated in art. 8b ODét. It collects the joint committee certificate, the wage compliance declaration, and verifies prior notification under art. 6 LDét. The organisational requirements of art. 8c ODét mandate written traceability prior to releasing any advance payment on the construction site.
What is the deadline to apply for the registration of a statutory mortgage lien under art. 839 CC?
Under art. 839 CC, registration must be requested no later than four months after completion of the work. This strict forfeiture period applies to any craftsman or subcontractor who provided labour or materials. If a claim—for instance, one of 85 000 CHF—is disputed, a provisional entry preserves the lien right pending a court decision or the provision of security.
Can the client have a craftsman's statutory mortgage lien cancelled?
Yes. Under art. 839 CC, registration cannot be requested if the owner provides sufficient security. The client then deposits equivalent bank guarantees, for instance up to 120 000 CHF, with the competent judge. This substitution discharges the property from the lien under art. 837 CC while securing future payment of the substantiated claim.
What administrative sanctions does a contractor face for breaching the LDét?
Art. 9 LDét provides for administrative sanctions issued by the cantonal authority. A fine of up to 5000 francs may be imposed for breaching the reporting duty under art. 6 LDét or the duty of due diligence under art. 5 LDét. In the event of a breach of minimum wage terms, the sanction may reach 30 000 francs along with a one- to five-year ban on offering services.
Can the cantonal inspection body inspect the construction site unannounced?
Art. 6 LTN tasks the cantonal inspection body with verifying compliance with registration and permit obligations at the workplace. Inspectors check identity documents and residence permits. Under art. 18 LTN, anyone who intentionally resists or obstructs inspections is punishable by a fine. Project participants on the construction site are under a strict duty to cooperate.
How do multiple statutory mortgage liens registered on different dates rank against each other?
Under art. 840 CC, craftsmen and contractors rank equally among themselves, even if registrations took place on different dates. In the event of a forced distribution of proceeds on an illustrative remaining balance of 300 000 CHF, each craftsman is treated with the same priority rank, regardless of the chronological order of registration in the land register.
Managing subcontracting risks requires unwavering contractual rigor on Swiss construction sites. Thorough adherence to the due diligence obligations of the LDét, monitoring compliance with the LTN, and tracking statutory mortgage lien deadlines ensure financial security for both the client and contractors. To explore construction site governance and the allocation of operational responsibilities under standard SIA 118 further, consult the following resources:
- Site Management in Switzerland: Project Management/Site Supervision Roles, SIA 118 Contracts and Governance (RPH 2026)
- DGP vs DLT vs Site Manager: Division of Civil and Criminal Responsibilities (RPH SIA 2026)
- Discrepancies Between Drawings and CAN Quotes: Order of Priority of Contract Documents (SIA 118)
- Contractor's Duty to Notify (SIA 118 / CO): Reporting a Design Flaw