The 3 Major Site Risks
- Financial / Margin: Joint and several liability among partners represents a major financial hazard. In the event of bankruptcy of one member, the others assume all remaining costs, which can reduce the profit margin by around 15 to 30 %. Art. 530 CO defines the simple partnership through which members unite their resources, leading de facto to this joint liability on the project.
- Legal / Joint Body / SUVA: The consortium faces exclusion from the call for tenders if even a single partner defaults. If a member does not pay due taxes or social contributions, the contracting authority can exclude the bidder or revoke the award, as provided for in art. 44 LMP.
- Administrative / Handover: Tender rejection due to administrative non-compliance is a frequent risk. If the internal agreement fails to demonstrate clearly that the characteristic performance is provided by the bidder, as required by art. 31 LMP, the contracting authority may deem that the conditions for participation are not met.
Faced with the growing complexity of public and private contracts in Switzerland, construction firms often choose to join forces to submit a tender. Forming a consortium, legally classified as a simple partnership under art. 530 CO, makes it possible to pool resources, technical expertise, and financial capacities. This strategy is particularly relevant for meeting the qualification criteria set by contracting authorities while spreading the workload on large-scale projects. However, teaming up entails joint and several liability, which demands rigorous contractual preparation before the tender is submitted.
The Federal Act on Public Procurement expressly allows consortiums of bidders to participate, provided that the characteristic performance is delivered by the bidder itself, in accordance with art. 31 LMP. For company owners and estimators, drafting a detailed consortium agreement is crucial to govern the allocation of shares, warranty management, and representation vis-à-vis the client. A poorly structured joint bid exposes the group to exclusion from the procedure if the conditions for participation are not satisfied by all partners.
Legal framework of a consortium: the simple partnership under the Code of Obligations
In Switzerland, when companies team up to submit a tender, they form a simple partnership. Under art. 530 CO, this is a contract whereby two or more persons agree to combine their efforts or resources to achieve a common purpose (here, winning a contract). This flexible legal form requires neither commercial register entry nor minimum share capital, but it entails full joint and several liability.
Unlike a joint-stock company (SA) or a limited liability company (Sàrl), a consortium has no legal personality. The member companies commit themselves personally and jointly and severally to the client. To interface with the contracting authority, the group generally appoints a lead contractor. Under art. 32 CO, the rights and obligations arising from a contract made in the name of another party by an authorised representative pass directly to that party. Thus, the signature of the lead company, duly empowered by the consortium agreement, binds all partner firms indivisibly.
In public procurement, the participation of consortiums of bidders is permitted by art. 31 LMP, unless the contracting authority limits or excludes it in the call for tenders or tender documents. This rule enables small and medium-sized enterprises (SMEs) to pool their technical and financial capacities to compete with major construction groups. However, the law stipulates that the characteristic performance must, in principle, be provided by the bidder (art. 31 para. 3 LMP). A consortium created solely to circumvent financial requirements, without genuine division of operational work, risks having its tender rejected.
Decision criteria for forming a joint venture of companies
The decision to form a consortium rests on a strategic analysis of the tender specifications. Contracting authorities establish strict suitability criteria, particularly regarding annual turnover, track record on similar projects, and workforce capacity. When a company cannot meet these criteria on its own, partnering in a simple partnership makes it possible to aggregate resources. The technical references of the various members are combined to demonstrate the group's overall capacity to deliver the works.
Complementary skill sets represent another decisive factor. A complex infrastructure project may demand specialised expertise in civil engineering, special geotechnical works, and structural steelwork. Rather than engaging these specialists merely as subcontractors, bringing them together within a consortium enables you to present a more robust bid, where each specialist assumes direct liability towards the client.
However, such an alliance requires complete trust between partners. The contracting authority evaluates the consortium as a single, jointly liable entity. If one member fails to pay due taxes or social contributions, the contracting authority may exclude the bidder from the procedure or revoke the award (art. 44 LMP). Conducting thorough preliminary due diligence on future partners before signing a consortium agreement is therefore vital.
Comparison table: Consortium (Simple partnership) vs Subcontracting
| Assessment criterion | Consortium (Simple partnership art. 530 CO) | Conventional subcontracting |
|---|---|---|
| Liability towards the client | Joint and several, unlimited for all group members. | Only the awarded main contractor is liable. |
| Contractual relationship | Direct contract for work with the contracting authority for all members. | No direct contractual link between subcontractor and contracting authority. |
| Tender evaluation (LMP) | Aggregation of project references, staffing numbers, and financial strength. | Evaluation focused primarily on the main bidder. |
| Sharing of profits and risks | According to the internal agreement (or equal shares by default). | Fixed markup for the bidder, negotiated unit price for the subcontractor. |
| Characteristic performance (art. 31 LMP) | Delivered jointly by the members of the bidding group. | Must in principle be delivered by the main bidder. |
| Coordination and representation (art. 32 CO) | A designated lead contractor represents all partners jointly and severally. | The main contractor directs its subcontractors alone. |
Common mistakes and financial consequences
Forming a consortium without a detailed internal agreement is the most critical mistake. Without a specific written agreement, default provisions of the Code of Obligations apply, dictating an equal split of profits and losses, which almost never reflects the actual division of work on site. A consortium agreement must specify financial allocation keys, invoicing procedures, cash flow management, and internal dispute resolution mechanisms.
Another major mistake involves mishandling joint and several liability if a partner fails. If a consortium member enters bankruptcy during execution, the remaining members must complete the works at their own expense. For example, on a masonry lot awarded at 3 000 000 CHF, the failure of a partner performing 50 % of the works can force the remaining firm to mobilise emergency resources, generating replacement surcharges and delay penalties that can eat into the profit margin by around 300 000 to 450 000 CHF.
Overlooking warranty rules is another common pitfall. The contract binding the consortium to the client is a contract for work (art. 363 CO). As such, the group is jointly and severally liable for building defects. The limitation period for the client's rights arising from defects in an immovable work is five years against the contractor (art. 371 CO). If a major waterproofing defect emerges four years after handover, the client may demand remediation from any member of the consortium, even if that member only carried out earthworks. The internal agreement must therefore provide for cross-guarantees or internal retentions to hedge this long-term risk.
Illustrative practical cases (typical scenarios on Swiss construction sites)
The figures and scenarios below are illustrative examples designed to show how procurement rules operate, and do not represent actual construction sites.
Scenario 1: Renovation of a school complex (Canton of Vaud)
Context: A municipality issues a public call for tenders under an open procedure (art. 18 LMP) to renovate a school. The financial qualification criterion requires an annual turnover of 12 million CHF. Any bidder may submit an offer.
Action: Two regional firms, each posting 7 million CHF in turnover, partner up as a simple partnership (art. 530 CO).
Rationale and outcome: By combining their capabilities, they reach 14 million CHF and satisfy the criterion. They draw up an internal agreement clearly delineating the work zones. The contracting authority evaluates the tenders based on criteria linked to the deliverables, including technical merit (art. 29 LMP). The consortium wins the contract. While both remain jointly and severally liable to the municipality, their agreement shields their respective margins in the event of cost overruns on either wing.
Scenario 2: Construction of a cantonal bridge (Canton of Geneva)
Context: The canton launches a selective procedure (art. 19 LMP) for a civil engineering structure requiring specialized expertise in foundations and steel construction.
Action: A civil engineering firm sets up a consortium with an SME specialising in structural steelwork instead of subcontracting the package.
Rationale and outcome: The contracting authority selects the bidders permitted to tender based on their aptitude. By onboarding the SME, the joint venture showcases outstanding project references, maximising its technical evaluation score. The client benefits from the joint and several liability of both firms, offering greater security than a subcontracting model where only the main bidder bears the risk.
Calls for tenders: free tools
Direct public procurement tenders, AIMP thresholds by canton, converting SIA 451 to Excel, quantity takeoff from an IFC model.
Frequently asked questions
Does a business consortium need to register in the commercial register to bid?
No. A consortium constitutes a simple partnership within the meaning of art. 530 CO. It has no separate legal personality and does not register in the commercial register. Member companies enter into a contractual agreement to bid, sharing the risks and rewards of the targeted contract jointly and severally.
Can a public contracting authority prohibit a consortium from bidding on a tender?
Yes. Under art. 31 LMP, the participation of consortiums of bidders is permitted in principle, but the contracting authority may limit or expressly exclude it in the call for tenders. You must always check the tender documents before incurring study costs estimated at 5000 CHF.
Who signs the contract for work if our consortium wins the public procurement contract?
All members of the simple partnership must sign the contract for work defined in art. 363 CO, unless an authorised representative signs on their behalf under art. 32 CO. They are thereby jointly and severally bound to the client for full execution of the works.
How should invoicing and VAT be handled within our joint venture of companies?
The consortium typically appoints a lead contractor to bill the client. This lead company collects the amounts, for instance 150 000 CHF, and distributes the shares to the partners. The simple partnership itself may require its own registration for Swiss VAT.
Can a consortium member subcontract its assigned share of the construction works?
Art. 31 LMP specifies that the characteristic performance must, in principle, be provided by the tenderer. If a member wishes to subcontract, they must comply with the tender requirements and guarantee that their subcontractors observe working conditions pursuant to art. 12 LMP.
What happens if a partner goes into bankruptcy during the execution of the works?
The members of the simple partnership are jointly and severally liable. If one partner goes into bankruptcy, the others must complete the works at their own expense to fulfill the contract for work and services. A robust internal agreement is essential to cover this financial risk, which can easily exceed 100 000 CHF.
Conclusion on business partnerships and consortia
Forming a consortium as a simple partnership offers Swiss SMEs a strategic opportunity to access major projects. By pooling your resources, you satisfy contracting authorities' requirements while sharing risks on a joint and several basis. Success depends on a rigorous internal agreement. To deepen your knowledge and optimise your procurement strategy, consult our dedicated resources:
- Public Procurement and Private Contracts in Switzerland: Procedures, Access and Tender Strategy for Construction Firms
- AIMP and LMP Thresholds: Open, Selective, or Invitation Procedure, Which Applies to Your Contract?
- Exceptional Direct Contract: Conditions Set by the AIMP and Practical Implications for Contractors
- Private Calls for Tenders: Property Management Agencies, Architects and Applicable SIA Rules