Table of contents
The 3 Major Site Risks
- Financial / Margin: Underestimating quantities in the CAN bill of quantities. An inaccurate price calculation on a private contract based on a fixed lump-sum price (art. 373 CO) leads to a margin loss of around 10 to 15%, since the contractor cannot claim any price increase.
- Legal / Joint bodies / SUVA: Failure to comply with social provisions. Property managers require compliance certificates. A breach of the duty to cooperate during inspections is punishable by a fine (art. 18 LTN), leading to exclusion from future private calls for tenders.
- Administrative / Acceptance: Poor incorporation of the architect's special conditions that derogate from standard SIA 118. Accepting unfair clauses on retainage ties up company cash flow, with retained amounts reaching up to 10% of total invoiced amounts.
Bidding on a private call for tenders in Switzerland requires a different approach from public procurement. Unlike procedures governed by the Federal Act on Public Procurement, tenders organized by property management firms and architects benefit from broad freedom of contract under the Code of Obligations (CO). This flexibility allows for direct price negotiations, but exposes construction firms to increased financial risks. Tender documents, often structured according to the CRB Construction Cost Code and Standard Description Catalogue, frequently incorporate special conditions modifying standard rules. Scrutinizing every file before committing is imperative.
Standard SIA 118 forms the baseline for these private contracts, although its application must be expressly agreed upon. Architects, acting as site management, routinely impose derogating clauses unfavorable to contractors regarding notice of defects deadlines. To win these contracts while safeguarding profitability, your firm must submit a competitive bid and anticipate property managers' administrative demands. They systematically demand proof of social compliance, such as certificates of payment to SUVA and compliance with collective labor agreements. Mastering the Swiss normative landscape is key to turning a tender into a profitable contract for work and services.
Legal framework and freedom of contract in private tenders
In the Swiss construction sector, calls for tenders issued by private parties—such as property management firms, architectural offices or private institutional clients—fall entirely outside strict public procurement legislation. The procedure rests primarily on freedom of contract governed by the Code of Obligations (CO). The ultimate goal of this consultation is entering into a contract for work and services, whose legal definition provides that the contractor undertakes to carry out a work in return for payment of a price by the client (art. 363 CO).
Unlike a public procedure where award criteria are strictly regulated and published, a private client enjoys absolute freedom to invite firms of its choice, negotiate prices down, and award the contract to whichever firm suits it best, without having to justify its decision. A contract is concluded when the parties have, reciprocally and concordantly, expressed their intent, either expressly or tacitly (art. 1 CO). In this specific context, the architect or property manager's representative very often acts on behalf of the client. The rights and obligations arising from a contract made in the name of another party by an authorized representative pass to the represented party (art. 32 CO). It is therefore critical for the bidding firm to verify the exact scope of site management's power of representation before signing the quote or incurring preparation costs.
Incorporating standard SIA 118 and specification standards
Although the tendering procedure is unconstrained, Swiss construction professionals systematically rely on standards from the Swiss Society of Engineers and Architects. Private calls for tenders are generally structured and drafted according to the Construction Cost Code (CFC) and the Standard Description Catalogue (CAN). This technical standardization enables property managers and architects to compare bids that are completely identical in terms of quantities, and to ensure that all services required for the work are properly priced.
From a purely contractual standpoint, private tenders almost always incorporate standard SIA 118. However, it is essential to understand that this technical standard does not have the force of law by default: it must be expressly incorporated into the contract for work and services to take legal effect. If standard SIA 118 is not formally referenced in the signed tender documents, only the default provisions of the Code of Obligations (CO) apply, fundamentally altering defect management.
For instance, under the strict statutory regime, upon delivery, the client inspects the condition of the work as soon as feasible and notifies the contractor of defects; for immovable structures, the client has 60 days to report them, and any shorter contractual deadline is void (art. 367 CO). Regarding long-term warranty rights, the limitation period for client claims arising from defects is five years for defects in an immovable structure against the contractor, architect, or engineer, and this period cannot be shortened to the detriment of the client (art. 371 CO).
Comparison table: Private tender vs Public procurement
To properly grasp the strategic stakes of bidding on a private call for tenders, one must assess the fundamental differences with public procedures governed by federal law.
| Assessment criterion | Private call for tenders (Property manager / Architect) | Public call for tenders (Municipality / Canton / Confederation) |
|---|---|---|
| Applicable legal basis | Code of Obligations (CO) and standard SIA 118 (if expressly incorporated) | Federal Act on Public Procurement (LMP) or cantonal legislation |
| Selection of participants | Fully discretionary, often by direct invitation or through an established network | Open, selective, or invitation procedure according to statutory thresholds |
| Price negotiation | Allowed and very common (rebates, cash discounts, technical variants) | Strictly prohibited once the bid has been officially submitted |
| Award criteria | Unrestricted, unpublished, entirely at the discretion of the client | Weighted criteria mandatorily published in the tender documents |
| Right of appeal | No administrative appeal available against the choice of the successful bidder | Appeal possible within 20 days of notification |
Common mistakes when submitting a private bid
The great flexibility of private contracts hides perilous pitfalls for construction firms lacking pricing rigor. The first major mistake involves the remuneration structure. Architects very often require a global or fixed lump-sum price to lock down the client's budget. A contractor who commits to a fixed lump-sum price must carry out the work for the agreed sum and cannot claim any increase, even if the work required more labor or expense (art. 373 CO). An inaccurate assessment of quantities on the provided drawings results in a direct financial loss for the firm. The statutory exception allowing a judge to grant a price increase applies solely in the event of extraordinary circumstances that were impossible to foresee or excluded by the parties' assumptions, which courts grant only very rarely.
Another frequent mistake is starting work prematurely based solely on verbal agreement from site management, without a formally signed contract. Where the offeror, owing to the nature of the transaction or the circumstances, could not expect an express acceptance, the contract is deemed concluded if the offer was not rejected within a reasonable period (art. 6 CO). However, proving the exact scope of agreed services and unit prices becomes exceptionally difficult in the event of a subsequent dispute.
Finally, the contractor is liable for the good quality of materials supplied; if materials provided by the client or the building site designated by the client turn out to be defective, or if any other circumstance jeopardizes regular or timely execution of the work, the contractor must inform the client immediately, under penalty of bearing the consequences (art. 365 CO). This duty to notify is a central obligation that bidders often neglect to formalize in writing.
Illustrative practical cases (typical scenarios on Swiss construction sites)
The figures and situations presented below are illustrative examples and not actual construction sites.
Scenario 1: Apartment renovation by a property manager (Canton of Geneva)
Context: A Geneva property manager launches a private call for tenders by invitation for the complete repainting and floor coverings of three apartments. The tender dossier does not mention standard SIA 118. A finishing work firm submits a fixed lump-sum bid of 45 350,00 CHF (8,1% VAT included).
Issue: During the works on the construction site, the contractor discovers that the walls require full surface smoothing not specified in the initial description, representing an estimated additional cost of 6 500,00 CHF. The firm requests an addendum from the property manager to cover these unforeseen costs.
Analysis and outcome: Since the contract is governed exclusively by the Code of Obligations (CO), the fixed lump-sum price rule applies strictly. The contractor executes the work for the agreed amount and cannot claim any increase, even if the work required more labor or expenses (art. 373 CO). As wall smoothing does not constitute an extraordinary circumstance impossible to foresee for a tradesperson inspecting the premises prior to tendering, the firm must absorb this margin loss. This scenario highlights the importance of stating clear reservations or proposing unit prices for uncertain preparatory work.
Scenario 2: Detached villa construction overseen by an architect (Canton of Vaud)
Context: A Vaud architectural firm oversees the call for tenders for the construction of a detached villa with a total estimated budget of 1 250 000,00 CHF. The contract for work and services for the masonry package, totaling 215 000,00 CHF, expressly incorporates standard SIA 118. The architect signs the contract for work and services on behalf of the private client.
Issue: The masonry firm falls significantly behind schedule from the very first weeks of excavation. The architect threatens to terminate the contract and bring in another local firm.
Analysis and outcome: The architect acts as an authorized representative; rights and obligations arising from a contract made in their name pass to the represented party, namely the client (art. 32 CO). Faced with established delays, the client, through their architect, holds clear rights: if the contractor does not start the work on time, delays execution, or falls so far behind schedule that completion within the agreed timeframe is no longer possible, the client may withdraw from the contract without waiting for the scheduled delivery date (art. 366 CO). The masonry firm risks not only losing the contract permanently, but also having to indemnify the client for additional costs incurred by bringing in an emergency replacement contractor.
Calls for tenders: free tools
Direct public procurement tenders, AIMP thresholds by canton, converting SIA 451 to Excel, quantity takeoff from an IFC model.
Frequently asked questions
Can a property manager adjust quote quantities after tender submission?
Yes, in a private contract, the property manager may adjust quantities before signing. The contract for work and services (under the Code of Obligations (CO)) governs variations. Where the price was set approximately, art. 374 CO provides that it is determined based on the value of the work and the contractor's expenses.
The architect is demanding a 10% discount on our initial bid; is this legal in Switzerland?
Absolutely. Unlike public procurement subject to the LMP, private calls for tenders allow free negotiation. The architect often acts as a representative (art. 32 CO). You can accept, refuse, or propose a technical variant to safeguard your margin on the project.
Which warranty period applies if the private call for tenders mentions nothing?
Without a specific mention, the Code of Obligations (CO) applies. Art. 371 CO sets the limitation period for the client's rights regarding defects in an immovable work at five years. The inclusion of standard SIA 118 must be expressly agreed upon to benefit from its rules.
How can you contest the award of a private contract to a cheaper competitor?
There is no formal right of appeal in a private contract. Freedom of contract prevails (Code of Obligations (CO)). The site management selects the firm of its choice without any obligation to justify its decision, unlike under the strict rules of the LMP.
The call for tenders imposes a fixed lump-sum price, what are the financial risks?
Art. 373 CO stipulates that the contractor performs the work for the agreed sum, without claiming any increase, even if the work requires more expenditure. An exception applies in the event of extraordinary circumstances. A precise cost calculation, for example 50 000 CHF, is essential.
Can a general contractor impose its own purchasing terms?
Yes, it can impose its conditions during the call for tenders. The contract is concluded by a mutual and concordant expression of will (art. 1 CO). It is crucial to check whether these terms deviate from standard SIA 118, particularly regarding deadlines.
To succeed in private calls for tenders in Switzerland, mastering standard SIA 118 and the Code of Obligations (CO) is essential. Property managers and architects expect precise tenders, priced in CHF. Unlike public procedures, negotiation remains open, offering opportunities to showcase your expertise. To deepen your knowledge and boost your chances of winning new construction sites, explore our resources:
- Public Procurement and Private Contracts in Switzerland: Procedures, Access and Tender Strategy for Construction Firms
- AIMP and LMP Thresholds: Open, Selective, or Invitation Procedure, Which Applies to Your Contract?
- Exceptional Direct Contract: Conditions Set by the AIMP and Practical Implications for Contractors
- General Contractor and Design-Build Contractor: Responding to a Call for Tenders as a Bidder