Practical guide

Drafting the Site-Specific Safety Concept: SUVA and OTConst Measures in Your Tender

Draft your site-specific safety concept under OTConst and SUVA to enhance your technical proposal in Swiss public procurement. Method and best practices.

Table of contents
The 3 Major Site Risks
  1. Financial / Margin: Omitting specific safety measures from the unit price or lump-sum price forces the successful bidder to fund unbudgeted capture or access systems out of pocket. Under art. 364 CO, the contractor procures the necessary means, machinery and tools at its own expense, which can result in an unforeseen margin erosion of 4 % to 8 % of total contract value.
  2. Legal / Joint committee / SUVA: Non-compliance with OTConst prevention rules or SUVA requirements triggers work stoppages ordered by the competent authority and exposes managers to criminal prosecution under art. 229 CP for endangering life or physical integrity through breach of the recognised rules of construction.
  3. Administrative / Acceptance: Submitting a generic or incomplete safety concept in the call for tenders file jeopardises contract award. Under art. 12 LMP, public contracts are awarded only to tenderers who comply with worker protection rules, and art. 44 LMP allows excluding any tenderer who fails to meet participation conditions.

In public procurement and private projects governed by Swiss law, drafting a site-specific safety concept forms a decisive part of your technical proposal. This document proves to the contracting authority and site management that your firm has identified the actual site hazards and incorporated the requirements of the Ordinance on the safety and health protection of workers in construction work alongside SUVA directives. This guide is designed for estimators, tender managers and business owners in French-speaking Switzerland looking to turn a regulatory constraint into a decisive competitive edge.

Far too many tenders still rely on vague statements of intent, dragging down the technical proposal's methodology score during jury evaluation. By formalising a methodical analysis of critical phases, appointing a competent person under OTConst, and aligning the prevention system with CFST directives, tenderers secure tender compliance while demonstrating thorough execution expertise on Swiss soil.

Method for developing the site-specific safety concept for your tender

Drafting a site-specific safety concept when responding to a Swiss call for tenders requires moving past generic statements of intent. Award panels evaluate the tenderer's ability to anticipate the parcel's specific topographical, structural and environmental constraints. In accordance with art. 29 LMP, the contracting authority evaluates tenders based on objective criteria such as technical value and cost-effectiveness. A targeted, structured concept demonstrates immediate operational capability.

To satisfy the requirements of federal legislation and applicable ordinances, the technical proposal must detail the allocation of responsibilities, interdisciplinary coordination and selected construction methods. The tenderer must integrate occupational health and safety management on the construction site by designating a competent person under the Ordinance on the safety and health protection of workers in construction work (OTConst). This approach aligns with Federal Coordination Commission for Occupational Safety (CFST) guidelines and SUVA directives.

Identifying critical risks and preventive measures right from tender stage

The first step involves analysing the scope of work, site setup plan and geotechnical report provided with the call for tenders documents. Tenderers must identify major hazards: work at height, trench stability, buried or overhead utilities, mixed traffic between heavy plant and site users, and exposure to mineral dust or pollutants such as asbestos. The site-specific concept must specify the chosen equipment, evacuation routes and secured access points right from the start of earthworks.

This preventive approach is also mandated by art. 364 CO, under which the contractor must carry out the work with care and procure the necessary means, plant and tools at its own expense, unless custom or agreement provides otherwise. A failure to anticipate these items in the tender shifts an unforeseen financial burden onto the winning firm. Furthermore, under art. 12 LMP, compliance with provisions on worker protection and working conditions is a mandatory award condition, applying equally to subcontractors pursuant to art. 12 al. 4 LMP.

Trade coordination and subcontractor management

Construction site safety depends on synchronising simultaneous or consecutive operations. In the tender, the site-specific concept must establish interfaces between structural work, scaffolding, building services and finishing work. Where a firm uses external partners, it must prove due diligence in selecting and supervising its agents.

Under art. 5 LDét, prime contractors are civilly liable for non-compliance by subcontractors with net minimum wages and working conditions, including occupational health and safety within the meaning of art. 2 LDét. To discharge liability under art. 5 al. 3 LDét, the contractor must demonstrate that it exercised due diligence. The safety concept submitted during the call for tenders formalises this operational setup by specifying site access controls, qualification checks and compliance audits planned on site.

Comparative analysis of safety measures in the tender

The table below sets out methodological choices to incorporate into technical submissions to meet the requirements of public or private clients, contrasting insufficient approaches with compliant technical responses.

Identified site hazardPenalising generic wordingRecommended technical measure for the tenderImpact on scoring and execution
Falls from slabs or roofsGeneric mention of complying with SUVA directives without a protection planInclusion of shored facade scaffolding or temporary edge protection installed per manufacturer specificationsHigh marks under the technical value criterion of art. 29 LMP and elimination of stop-work risks
Slope or trench collapseStandard commitment to respect the natural slope of the groundTrench box shoring plan or battered slopes verified against geotechnical ground propertiesValidation of construction methodology and lump-sum coverage with no earthwork cost overruns
Crane lifting and traffic routesRough mark-up of the presumed crane position on drawingsSlewing radius diagram with oversailing exclusion zones, sized outriggers and segregated pedestrian pathsFull marks on the logistics section and mitigation of on-site traffic conflicts
Dust emissions and noiseVague mention of protective face masks handed out to personnelWater suppression systems, on-tool source capture and perimeter acoustic sheetingCompliance with Swiss environmental ordinances and reduction in neighbour complaints
Management of posted workersStandard contractual clause referring to subcontractor independenceUpfront document verification procedure, declaration check under art. 6 LDét and site access badgesProof of due diligence under art. 5 al. 3 LDét and safeguards against art. 44 LMP sanctions

Frequent tender mistakes and financial repercussions

The most frequent mistake is copy-pasting a theoretical excerpt from a previous bid. Technical evaluators appointed by contracting authorities spot the lack of site-specific relevance right away. Such an offer receives a poor technical score, which often loses the contract to a better-prepared competitor.

Contractually, when a project is awarded on a lump-sum price basis under art. 373 CO, the contractor executes the work for the agreed amount and cannot claim any increase, even if the work required more labour or expense, subject to art. 373 al. 2 CO in cases of extraordinary circumstances. Omitting collective protection systems, such as a complete perimeter guardrail network, forces the contractor to absorb these costs, typically running between 15 000,00 CHF and 45 000,00 CHF incl. VAT at the Swiss 8,1 % rate.

Furthermore, neglecting safety requirements during tendering can warrant exclusion from the award procedure under art. 44 LMP, or later result in an assessment of anticipated delay under art. 366 CO if project start is halted by labour inspection authorities.

Illustrative practical cases (typical scenarios on Swiss construction sites)

The amounts and figures presented in the following cases are illustrative examples intended to guide pricing and operational planning decisions.

Scenario 1: Heavy refurbishment in an urban centre (Canton of Geneva)

The project involves adding two storeys to an office building in a dense urban setting, with ground-floor retail units remaining open to the public. The public call for tenders under an open procedure (art. 18 LMP) entails simultaneous work by carpenters, bricklayers and roofers, with an average daily workforce of 18 operatives.

In its tender, the firm incorporates a safety concept built around an enclosed materials hoist on the rear elevation and heavy-duty catchment decking over the public road to catch falling debris. The financial breakdown includes a distinct item for debris netting and physical separation of pedestrian zones, budgeted for instance at 28 500,45 CHF incl. VAT (8,1 % rate). This rigour earns top marks on the site organisation criterion and ensures coordinated work without disrupting commercial activity.

Scenario 2: Construction of a commercial and industrial complex (Canton of Vaud)

The project covers bulk excavation and structural work for an industrial warehouse, requiring high-face cuts adjacent to a cantonal road, carried out by a crew of 12 construction workers.

The tenderer rules out simple open-cut battering due to slip risks during wet weather. The technical proposal details the installation of a soil-nailed wall with shotcrete and temporary slope drainage. Sizing and stabilising the excavation face represents an upfront safety budget of around 52 300,80 CHF incl. VAT. By demonstrating this methodology, the tender guarantees programme reliability and road stability to the client, protecting the contractor from claims under art. 365 al. 3 CO concerning ground defects.

Calls for tenders: free tools

Direct public procurement tenders, AIMP thresholds by canton, converting SIA 451 to Excel, quantity takeoff from an IFC model.

View tendering tools

Frequently asked questions

How should a site-specific safety concept be formalised when submitting a tender?

The tenderer includes a descriptive health and safety statement compliant with CFST 6508 and OTConst. This document outlines the analysis of project-specific risks, names competent persons, and details the provisional budget allocation, for instance around 15 250,50 CHF for collective protective measures.

Can the contracting authority evaluate safety as part of the award criteria?

Yes. Under art. 29 LMP, the authority assesses the technical value and operational plausibility of bids. A concept that clearly demonstrates work-station coordination and adherence to SUVA rules secures top marks against competing tenders that gloss over prevention protocols.

What safety obligations apply to subcontractors declared in the tender?

Under art. 12 LMP, subcontractors must comply with the worker protection rules and working conditions in force at the place of performance. The main contractor must verify their organisational suitability, failing which the tender risks exclusion from the procedure under art. 44 LMP during bid evaluation.

How do you cost emergency response and first aid without distorting the bill of quantities?

Emergency measures compliant with OTConst requirements and SUVA directives are charged to general construction site installation costs. A budget allocation of around 4 850,25 CHF covers first-aid equipment and training without compromising price competitiveness.

Can the lack of a specific safety concept invalidate a public tender offer?

Absolutely. Under art. 38 LMP, the contracting authority reviews tender compliance. Omitting required safety documents or failing to satisfy participation criteria justifies formal disqualification of the offer by substantiated decision pursuant to art. 44 LMP, subject to the appeal period under art. 56 LMP.

What advance checks must be performed on posted subcontractor companies?

The contractor ensures compliance with the duty of due diligence stipulated by the LDét and ODét by demanding wage compliance declarations and advance official notification. Any contractual failure compromises tender compliance and exposes the award to immediate exclusion under public procurement legislation.

Ensuring legal compliance and technical performance in your tender

Integrating a rigorous specific safety concept is a decisive lever for winning public procurement and private tenders subject to OTConst, SUVA and LMP requirements. Precise definition of preventive measures demonstrates the tendering firm's technical expertise, ensures tender submission compliance, and protects operating margins from the moment of award.

To explore writing your technical narratives in greater depth and optimise your tender submissions in French-speaking Switzerland, consult our methodological guides: