Table of contents
The 3 Major Site Risks
- Financial / Margin: Incorrect crane positioning or unsuitable access route for heavy transport generating extra costs in the range of 15 000,00 CHF to 45 000,00 CHF incl. VAT (auxiliary mobile crane, roadway reinforcement). Under art. 373 CO, with a lump-sum price, the contractor bears unforeseen expenses that do not constitute extraordinary circumstances.
- Legal / Joint Body / SUVA: Inability to guarantee base stability or safety clearances during assembly, leading to inspection service interventions or a breach of art. 364 CO regarding the contractor's duty of care and liability in supplying machinery.
- Administrative / Handover: Commissioning halted due to lack of municipal permit for heightened use of public property or an unsigned oversailing agreement with neighbours, delaying site kickoff and exposing the firm to default consequences under the Code of Obligations (CO).
The mandatory site visit is a critical step for bidding contractors in Switzerland, especially during procedures governed by LMP or private contracts under SIA 118. Thorough inspection of the plot is not just a quick visual check: it dictates the technical feasibility of the construction site setup, the turning radii, and the geotechnical positioning of heavy lifting equipment. Any misjudgement of road constraints or overhead utility lines immediately jeopardises the financial balance of the offer before tenders are even opened.
For the estimator and the site manager, this field inspection compares the call for tenders drawings with actual topography and ground conditions. Under art. 365 para. 3 CO, the contractor must immediately notify the client if the designated land or local conditions display defects likely to compromise the proper execution of the works. Methodically using a 35-point critical checklist ensures rigorous foresight regarding cantonal or municipal permits required for heavy transport, assembly pads, and oversailing adjacent plots.
Site inspection methodology and crane access constraints
Technical assessment during the mandatory site visit determines site feasibility and the pricing structure submitted in the bid. The tenderer must examine topographical constraints, public roadway layout, and ground bearing capacity. Under art. 364 CO, the contractor is liable for proper execution of the works and provides necessary means, machinery, and tools at its own expense, unless agreed or customary otherwise. A misjudgement regarding crane clearance or plot layout directly engages its contractual liability.
The delivery route for tower crane sections or the mobile crane requires a point-by-point route check from the main road network down to the installation pad. Turning radii at municipal junctions, permissible gradients for articulated lorries carrying counterweights, and the presence of protected trees or fixed street furniture require special authorization requests from the building police and highways departments.
Spotting overhead power lines and underground utilities is an absolute priority. Under art. 365 para. 3 CO, if the ground designated by the client proves defective or if any other circumstance compromises the orderly or punctual completion of the work, the contractor must inform the client immediately, under penalty of bearing the consequences. The estimator must report any spatial clash between the crane jib when weathervaning freely and neighbouring buildings or oversailing easements recorded in the land register.
Operational site visit checklist: 35 checkpoints
This field audit matrix divides site inspection into six operational areas, making it possible to lock down construction site setup items before finalizing the tender:
- 1. Access geometry and clearances: Minimum municipal road width, vertical clearance beneath bridges or gantries, turning radii at critical junctions, tonnage limits on bridges or slabs crossed.
- 2. Assembly zone layout: Exact position for parking the mobile assembly crane, clearance needed for jib telescoping, rear counterweight slewing clearance, alignment with track centreline or base frame.
- 3. Platform and geotechnical base: Crane foundation soil type, natural slope, presence of uncompacted fill, proximity of embankments or open excavations, need for piles or load-spreading beams.
- 4. Airspace and oversailing easements: Safe distance from medium- and high-voltage power lines, oversailing agreement with adjoining plots, interference with other working cranes nearby, non-building easements, or aeronautical clearances.
- 5. Underground networks and inspection chambers: Surface water and foul sewers beneath the haul road, pressurized gas mains, shallow electrical cables, telecommunications chambers requiring steel spreader plates.
- 6. Temporary site utility connections: Distance to temporary electrical supply box, available amperage for the hoist motor, drinking water network pressure and flow rate, discharge point for site runoff after settlement and neutralisation.
Comparative table of access and installation parameters
| Site parameter | Dense urban environment | Industrial / commercial zone | Mountainous or restricted-access area | Regulatory or contractual requirement |
|---|---|---|---|---|
| Permit for heightened use of public property | Mandatory, municipal coordination with time restrictions | Usually limited to roadway crossing | Subject to agreement from private owners and municipality | Municipal police regulations and art. 364 CO |
| Minimum carriageway width | Major constraint, removal of parking bays required | Sufficient width for standard haulage and semi-trailers | Narrow tracks, temporary widening of bends required | Roadway design standards and art. 364 CO |
| Oversailing third-party buildings | Formal written agreement, potentially with compensation | Rarely blocking, customary neighbourly agreement | Adjacent building land often absent | Civil Code (CC) and art. 365 para. 3 CO |
| Bearing capacity of foundation soil | Checked on parking deck or existing basement slab | Soft ground requiring soil replacement or spreader mats | Outcropping bedrock or moraine with variable bearing capacity | Geotechnical report and art. 365 para. 3 CO |
| Main power supply | Direct mains connection subject to transformer availability | High capacity available on distribution network | Inadequate overhead line, generator set often required | Utility provider guidelines and art. 373 CO |
Common assessment mistakes and financial impacts
Overlooking site-specific physical conditions during the visit exposes the awarded contractor to immediate operating losses. Art. 373 para. 1 CO establishes the lump-sum price rule: the contractor must complete the work for the agreed sum and cannot claim any increase, even if the work required more labour or expenditure. Extra equipment costs remain solely at its expense.
Underestimating ground bearing capacity where the crane sits is a classic technical mistake. If the crane must stand on loose, unstabilised fill, installing unexpected foundation micropiles or a heavy load-spreading raft leads to unforeseen extra costs in the range of 18 500,00 CHF to 38 000,00 CHF incl. VAT. Without prompt notice to the client under art. 365 para. 3 CO before signing the contract, this additional expense cannot be claimed via an addendum.
Failing to coordinate with neighbours regarding the oversailing of private plots can prevent crane commissioning. An interrupted assembly with a mobile telescopic crane standing idle incurs standby costs of around 3 200,00 CHF incl. VAT per day of delay. In public procurement governed by LMP, such an organisational failure threatens the overall project schedule, triggering contractual liquidated damages under art. 160 CO and 161 CO.
Illustrative practical cases (typical scenarios on Swiss construction sites)
Figures presented in the following scenarios are illustrative examples prepared for technical analysis and do not represent actual construction sites.
Standard scenario 1: Residential building in dense urban area (Canton of Vaud)
A contractor tenders for a multi-family housing development in a Vaud municipality. The planned crew includes 14 workers for the structural work. During the mandatory site visit, the estimator spots a dead-end access road only 3,20 metres wide, lined with older buildings, and a low-voltage overhead power line crossing the unloading path.
The initial technical approach planned for a tower crane with a 45-metre jib erected using a heavy-tonnage mobile crane. Access dimensions rule out heavy transporter passage. The contractor includes in its tender the temporary removal of a municipal fence section, insulating line covers, and the use of a compact self-erecting tower crane paired with a boom pump mixer truck. Anticipating this during tender preparation allows a specific logistics item of 14 580,00 CHF incl. VAT to be added to the quote, protecting profitability under art. 373 CO.
Standard scenario 2: Office building on sloping ground (Canton of Fribourg)
For a cantonal public call for tenders involving 20 team members, the site visit reveals sloping terrain with a 6-metre height difference between the cantonal road and the working platform. The tender documentation makes no mention of requirements for constructing a heavy access ramp.
On-site analysis indicates the 100-tonne mobile crane cannot drive down to the platform without rollover risks. The contractor opts to install the crane on an anchored base at the upper level alongside the roadway, requiring a 10-metre jib extension to cover the entire building footprint. This cost adjustment of 22 680,00 CHF incl. VAT is incorporated right from tender submission in accordance with art. 364 CO, preventing post-award dispute during execution.
Calls for tenders: free tools
Direct public procurement tenders, AIMP thresholds by canton, converting SIA 451 to Excel, quantity takeoff from an IFC model.
Frequently asked questions
Does missing a mandatory site visit disqualify you from a public tender?
Yes. In tenders governed by LMP, the contracting authority automatically disqualifies the defaulting tenderer under art. 44 LMP for failure to meet participation conditions. Physical absence or failure to sign the attendance sheet renders the offer inadmissible, with no subsequent remedy or useful appeal under art. 56 LMP.
Who bears the extra cost of a mobile crane not specified in the tender documents?
Under art. 364 CO, the contractor provides required equipment and machinery at its own expense. If the site visit made it possible to detect that installing a static crane was impossible, the contractor absorbs the difference, with an illustrative extra cost around 14 595,45 CHF incl. VAT.
How should you react if the designated site reveals dangerous overhead lines?
Art. 365 CO requires immediate notification of the client, under penalty of bearing the consequences of conditions that compromise performance. During tendering, this finding is raised through a formal inquiry or an explicit reservation referencing OTConst requirements and municipal permits.
Can the client enforce a lump-sum price despite unusable site access?
Under art. 373 CO, the lump-sum price binds the contractor, unless extraordinary circumstances impossible to foresee arise. Access difficulties visible during the site visit do not qualify as unforeseeable: the contractor must factor transshipment costs into the initial pricing.
What is the legal status of the site visit report drawn up by the site management?
The minutes formalise the joint findings and serve as authoritative proof for any construction site tolerances granted. Under standard SIA 118, they form part of the tender conditions, binding the parties as soon as the contract is concluded under art. 1 CO.
Can you enter a reservation regarding crane foundations after the contract award?
No. Under art. 41 LMP and art. 364 CO, the award finalises the technical commitments of the tender offer. Discovering ground instability after signing without having flagged it during the site inspection prevents you from claiming compensation for a platform costing around 18 920,35 CHF incl. VAT.
The site inspection establishes the scope of work and secures your costing against unforeseen road access or craning conditions. Continue refining your tender offers with our analysis resources:
- Tender Package Analysis, Site Visit and Plan Take-Off
- Order of Priority of Tender Documents: Discrepancies Between Drawings and Quotes Under Standard SIA 118