The 3 Major Site Risks
- Financial / Margin: Overall costing error resulting in a margin loss in the range of 10 to 15 %. In the case of a lump-sum price, art. 373 CO stipulates that the contractor cannot claim any increase, even if the work required more labour.
- Legal / Joint Committees / SUVA: Joint and several liability toward subcontractors. Art. 5 LDét provides that the main contractor is civilly liable for non-compliance by subcontractors with net minimum wages, subject to administrative sanctions (art. 9 LDét) and inspections under the Federal Act on Combating Undeclared Work (LTN).
- Administrative / Acceptance: Non-compliance of the tender resulting in exclusion from the procedure (art. 44 LMP). Art. 367 CO requires the client to examine the work and give notice of defects (60-day period for immovable works).
Responding to a call for tenders in Switzerland as a general contractor (GC) or total contractor (TC) demands a thorough command of award procedures. The general contractor commits to delivering the entire physical structure, whereas the total contractor also assumes full planning responsibility. This position entails coordinating subcontractors and guaranteeing an all-inclusive price. In public procurement, the Federal Act on Public Procurement (LMP) governs competitive bidding. The contracting authority evaluates tenders according to specific criteria (art. 29 LMP) and awards the contract to the bidder submitting the most advantageous tender (art. 41 LMP). Preparation requires analysing the specifications, which are often structured according to the CRB Standardised Item Catalogue (CAN).
A successful tender relies on managing contractual risks. When submitting a lump-sum price, the company is subject to art. 373 CO, which rules out any price increase in the event of cost overruns, except in extraordinary circumstances. The SIA 118 standard establishes the general conditions of execution, governing warranties and payments. The contractor must ensure that its subcontractors comply with working conditions, or face joint and several liability (art. 5 LDét). An improperly priced tender exposes the bidder to exclusion from the procedure (art. 44 LMP). This guide sets out the steps required to build a solid submission file, price services accurately, and protect your firm's contractual position before Swiss clients.
Tendering Strategy for General and Total Contractors
Dossier Analysis and Legal Compliance
Preparing a tender as a general contractor (GC) or total contractor (TC) demands a rigorous methodology, particularly when competing in public procurement. The initial review of the tender dossier determines the technical and financial viability of the project. The contracting authority evaluates tenders based on criteria related to performance; it indicates these criteria and their weighting in the call for tenders or the tender documentation (art. 29 LMP). When bids are opened, the contracting authority verifies compliance with formal requirements and officially corrects obvious calculation errors (art. 38 LMP).
The contract award process is grounded in the fundamental rules of the Code of Obligations (CO). A contract is concluded when the parties have reciprocally and mutually expressed their concurrent will, either expressly or tacitly (art. 1 CO). In certain private tender contexts, where the offeror should not, by reason of the nature of the transaction or the circumstances, expect an express acceptance, the contract is deemed concluded if the offer has not been rejected within a reasonable period (art. 6 CO).
For bidders, legal compliance is an absolute prerequisite right from tender submission. For services to be performed in Switzerland, the contract is awarded only to bidders who comply with employee protection provisions and the working conditions in force at the place of performance, reporting and permit obligations under the LTN, and equal pay (art. 12 LMP).
Consortia and Subcontractor Management
Because the general contractor subcontracts a large share of the physical execution, it must structure its partner network during the tender phase. The participation of bidder consortia and subcontractors is permitted, unless the contracting authority restricts or excludes it in the call for tenders or the tender documentation; the characteristic performance must in principle be carried out by the bidder (art. 31 LMP).
Managing this subcontracting chain imposes stringent duties on the successful bidder. The duty of due diligence incumbent on the contracting contractor requires taking the necessary contractual and organisational measures to ensure subcontractors demonstrate compliance with minimum wage and working conditions (art. 8c ODét). Flawed subcontractor selection during the tender phase exposes the general contractor to severe operational risks during construction.
Comparison Table: General Contractor (GC) vs Total Contractor (TC) Models at Tender Stage
| Analysis Criterion during Tendering | General Contractor (GC) Model | Total Contractor (TC) Model |
|---|---|---|
| Scope of Costed Services | Execution of all construction works (CFC 2 and following). | Planning (engineering, architecture) and full execution of the structure. |
| Tender Calculation Basis | Working drawings and descriptive bills of quantities supplied by the client's design team. | Functional specifications or descriptive requirements of expected performance. |
| Design Error Risk | Borne by the client's design consultants (architects, engineers). | Borne entirely by the total contractor, who assumes full design liability. |
| Handling Change Orders | Pricing addenda based on plans revised by site management. | Internal project adjustment within the overall guaranteed budget agreed with the client. |
| Warranty and Defect Liability | Limited to physical execution of the works according to the instructions received. | Comprehensive, covering defects in engineering, design, and physical execution. |
Costing, Lump-Sum Prices, and Frequent Errors
Price Protection and Contingency Management
Costing an overall tender requires absolute control over cost prices, usually structured under the Building Cost Code (CFC) or the Standardised Item Catalogue (CAN). The remuneration model selected during tendering defines how financial risk is shared. Under a lump-sum price, the contractor executes the work for the agreed amount and cannot claim any increase, even if the work required more labour or expenditure; exception: in the event of extraordinary circumstances that were impossible to foresee or excluded by the parties' assumptions, the court may grant an increase in price or terminate the contract (art. 373 CO). Conversely, where the contract provides for a price not fixed in advance or set only approximately, it is determined according to the value of the work and the contractor's actual expenses (art. 374 CO).
Consequences of Abnormally Low Tenders
Bidders are sometimes tempted to slash margins drastically to secure a contract. However, if the contracting authority receives a tender with an abnormally low total price, it must request relevant information from the bidder to verify that participation conditions are fulfilled and that tender requirements have been understood (art. 38 LMP). Failing to provide convincing evidence is fatal: the contracting authority may exclude a bidder on sufficient grounds, particularly if it provided false information or submitted an abnormally low tender without proving it meets participation conditions (art. 44 LMP).
A frequent pitfall involves omitting Site Installations costs (CFC 4) or underestimating the safety measures required by the Construction Works Ordinance (OTConst). Overlooking dedicated scaffolding for installing a ventilated façade can lead to an unrecoverable extra cost of roughly 45,500.00 CHF, deducted straight from your net profit.
Anticipating Warranty Risks
The tender phase must also anticipate project closeout and warranty risks, which directly affect contingency reserves. Following handover, the client must verify the condition of the work as soon as practicable and notify the contractor of defects; for an immovable work, the client has 60 days to give notice, and any shorter contractual deadline is void (art. 367 CO). The general contractor must make financial provision for these liabilities, bearing in mind that the limitation period for the client's rights arising from defects is five years for defects in an immovable work against the contractor, architect, or engineer, and that this five-year period cannot be modified to the detriment of the client (art. 371 CO). The client's rights in the event of defects include rejection, price reduction, remedial repair, or damages; any agreement entered into in advance that limits or excludes the right to remedy defects is null and void where the defect concerns a building (art. 368 CO).
Illustrative practical cases (typical scenarios on Swiss construction sites)
These scenarios are illustrative examples designed to show how tendering rules apply; they do not depict actual construction sites.
Scenario 1: General Contractor Tender for a School Complex (Canton of Fribourg)
Context: A Fribourg municipality issues an open call for tenders for the construction of a school complex. A general contractor submits an all-inclusive tender based on drawings produced by the architect appointed by the municipality.
Problem: To offer the most competitive price, the general contractor relies on quotes from regional subcontractors. When assessing bids, the contracting authority finds that the overall price is 15 % below the competitors' average.
Analysis and Solution: The contracting authority asks the general contractor to justify this price. The company demonstrates that its pricing stems from an innovative execution method for the structural work. However, it must also prove that its subcontractors comply with collective labour agreements (CLA). The contracting contractor is civilly liable for non-compliance by subcontractors with net minimum wages and working conditions (art. 5 LDét). By demanding certificates of joint committee compliance from all partners before lodging the tender, the general contractor secures its submission. Had it neglected this check, it risked disqualification from the procedure, as well as the risk of facing a back-payment adjustment of roughly 32,000.00 CHF in the event of a defaulting subcontractor's bankruptcy.
Scenario 2: Total Contractor Tender for a Residential Building (Canton of Valais)
Context: A private Valais investor intends to build a residential apartment building and issues an invited call for tenders. The client requires a total contractor proposal covering architectural design, civil engineering, and execution, for a guaranteed lump-sum price.
Problem: The total contractor wins the contract and executes the agreement. During earthworks, soil conditions turn out to differ slightly from the initial geotechnical test pits it had commissioned during design development, requiring unanticipated ground consolidation work.
Analysis and Solution: The total contractor attempts to invoice this work as a variation to the client. However, because the contract was agreed at a lump-sum price and design responsibility lies with the contractor, it cannot rely on this claim. Under a lump-sum price, the contractor executes the work for the agreed amount and cannot claim any increase, even if the work required more labour or expenditure; exception: in the event of extraordinary circumstances that were impossible to foresee or excluded by the parties' assumptions, the court may grant an increase in price or terminate the contract (art. 373 CO). Because the geological variation encountered was not deemed impossible to foresee for an experienced design professional, the exception does not apply. The total contractor must absorb the consolidation cost overrun, estimated at 85,250.00 CHF, out of its own profit margin.
Calls for tenders: free tools
Direct public procurement tenders, AIMP thresholds by canton, converting SIA 451 to Excel, quantity takeoff from an IFC model.
Frequently asked questions
What is the difference between a general contractor and a total contractor in a tender?
The general contractor handles the full execution of the works based on plans provided by the client. The total contractor, however, also takes on design and planning services. In both cases, the contract for work and services is governed by art. 363 CO.
How does a general contractor set its price in a public call for tenders?
It generally submits a fixed lump-sum price. Under art. 373 CO, the contractor completes the work for the agreed sum and cannot claim any increase, except in extraordinary circumstances. The contracting authority then evaluates this overall bid against the specific award criteria set out in art. 29 LMP.
Can a general contractor subcontract work after a public contract has been awarded?
Yes, the use of subcontractors is permitted under art. 31 LMP, unless excluded by the contracting authority in the call for tenders. However, the characteristic performance must in principle be carried out by the bidder, and the general contractor remains responsible for working conditions.
What are the risks if a general contractor submits an abnormally low bid?
If the total price is abnormally low, the contracting authority must request clarification under art. 38 LMP. If the bidder fails to prove that it satisfies the participation requirements, art. 44 LMP allows its exclusion from the procedure and the revocation of the award.
Is the general contractor liable for the working conditions of its subcontractors?
Absolutely. Art. 12 LMP requires subcontractors to comply with worker protection provisions. In addition, under art. 5 LDét, the primary contractor is jointly and severally liable for any failure by its subcontractors to pay minimum wages, unless it proves due diligence.
What is the deadline for challenging the award of a contract to another total contractor?
Appeals against an award decision must be filed in writing with statement of grounds within 20 days of notification, in accordance with art. 56 LMP. However, the appropriateness of the decision cannot be reviewed by the authority.
Tendering as a general contractor or total contractor requires thorough mastery of public procurement and private tendering procedures. Careful bid preparation, subcontractor risk analysis and strict compliance with award criteria are essential to winning the contract. To explore Swiss calls for tenders further, consult our dedicated resources:
- Public Procurement and Private Contracts in Switzerland: Procedures, Access and Tender Strategy for Construction Firms
- AIMP and LMP Thresholds: Open, Selective, or Invitation Procedure, Which Applies to Your Contract?
- Exceptional Direct Contract: Conditions Set by the AIMP and Practical Implications for Contractors
- Private Calls for Tenders: Property Management Agencies, Architects and Applicable SIA Rules