The 3 Major Site Risks
- Financial / Margin: Fine of up to 5000 CHF (art. 9 LDét) for breach of the duty of due diligence, reducing the main contractor's profit margin at the tender stage.
- Legal / Joint / SUVA: Joint and several civil liability of the contracting employer for non-compliance with minimum wages by subcontractors (art. 5 LDét), leading to joint body proceedings.
- Administrative / Handover: Exclusion from public procurement if subcontractors breach working conditions or notification requirements (art. 12 LMP and art. 44 LMP).
When preparing a bid for a public or private contract in Switzerland, subcontracting is a strategic lever for construction firms. However, delegating works means assuming increased liability as a main contractor under the Posted Workers Act (LDét). Involving partners in your tender requires strict verification of each subcontractor's compliance with the minimum working conditions guaranteed in Switzerland. Under art. 5 LDét, the contracting employer bears civil liability, and potentially joint and several liability, for any breach of these standards by its subcontractors in construction. This provision imposes a strict duty of due diligence right from the call for tenders, requiring the main bidder to demand formal guarantees before the award.
In public procurement, the Federal Act on Public Procurement (LMP) reinforces these obligations. Art. 12 LMP states that contracts may only be awarded to tenderers and their subcontractors who comply with worker protection provisions at the place of performance. An advantageous bid can thus be dismissed if the main contractor fails to monitor its partners. To avoid this risk of exclusion and the administrative sanctions under art. 9 LDét, the contractor must implement appropriate contractual and organisational measures in accordance with art. 8c ODét. This means requiring signed declarations guaranteeing net minimum wages or proof of adherence to local collective labour agreements (CLA). Mastering these legal requirements right from bid preparation is essential to secure the contract award.
Legal framework and admission of subcontracting in Swiss contracts
Subcontractor involvement in a tender process is generally permitted by law, unless the contracting authority formally restricts or excludes it in the call for tenders documents. Art. 31 LMP specifies, however, that the characteristic performance must in principle be carried out by the tenderer itself. Consequently, the main contractor submitting the bid bears overall responsibility. For works performed in Switzerland, the contract is awarded only to tenderers who comply with worker protection provisions and working conditions in force at the place of performance, as well as equal pay. Art. 12 LMP expressly requires subcontractors to comply with these very same provisions.
In the building, civil engineering and finishing work sectors, where activities involve the construction, repair or alteration of structures under art. 5 ODét, price pressure often drives firms to hire foreign companies. This is where the contracting employer's heightened liability comes into play. Art. 5 LDét stipulates that the contracting employer is civilly liable for any failure by subcontractors to respect net minimum wages and working conditions. This liability becomes joint and several once debt collection proceedings against the subcontractor have proven unsuccessful or cannot be initiated. If the subcontractor disappears or goes into bankruptcy, the main contractor must pay the outstanding wages out of its own funds, instantly destroying the profitability projected during the tender.
The duty of due diligence: cornerstone of exemption
Faced with this major financial exposure, the law offers the main contractor an exit route, provided the matter is addressed during the call for tenders phase. The contracting employer can obtain exemption from joint and several liability by proving it fulfilled its duty of due diligence under art. 5 LDét. Failing this proof, the administrative sanctions set out in art. 9 LDét may be imposed, including a fine of up to 5000 francs or a ban on offering services in Switzerland for one to five years.
This duty of due diligence entails specific operational obligations. Art. 8c ODét requires the contractor to put in place the contractual and organisational arrangements needed to require subcontractors to prove compliance with minimum wage and working conditions. In practice, while assembling the bid, the main contractor must obtain documented guarantees before even signing the works contract with its partner.
To demonstrate compliance with minimum conditions, art. 8b ODét lists the records the contracting employer may demand. These include, in particular, a posting certificate, a signed declaration guaranteeing minimum wage conditions, an attestation from the joint enforcement bodies, or listing of the subcontractor in a compliance register. The wage to verify is the net minimum wage, defined by art. 8a ODét as the minimum wage under art. 2 LDét after deducting employee contributions remitted by the employer for social insurance and withholding taxes.
Comparison table: Assessing subcontractors during tendering
| Regulatory check item | Risky practice (Common error) | Compliant practice (Proof of due diligence) |
|---|---|---|
| Verification of net minimum wages (art. 8a ODét) | Accepting an abnormally low quote without requesting a breakdown of labour costs. | Requiring a signed declaration guaranteeing minimum wage conditions (art. 8b ODét). |
| Notification of posted workers (art. 6 LDét) | Allowing the subcontractor to start works the day after contract signing. | Checking the written notification submitted to the cantonal authority and observing the eight-day waiting period. |
| Characteristic performance of the contract (art. 31 LMP) | Subcontracting the entire main package to operate merely as a financial broker. | Retaining execution of the characteristic performance and subcontracting only specialised trade packages. |
| Contractual provisions (art. 8c ODét) | Using a standard works contract lacking any LDét compliance clause. | Incorporating strict organisational clauses enabling verification of compliance proofs at any time. |
| Joint body attestations (art. 8b ODét) | Relying on an oral promise of compliance with collective labour agreements. | Collecting the attestation from the joint enforcement bodies or verifying inclusion in a compliance register. |
Common tendering errors and financial consequences
One of the most damaging mistakes when preparing an offer is including a foreign subcontractor's price without running a plausibility check. If the contracting authority receives a tender with an abnormally low total price, art. 38 LMP requires it to seek clarification from the bidder to verify that participation conditions are met. If the main contractor cannot substantiate its subcontractor's wage costs, it risks outright exclusion from the tender. Indeed, art. 44 LMP allows the contracting authority to exclude a bidder that submits an abnormally low bid without proving it meets participation requirements, or if outstanding taxes or social contributions have not been paid.
Another critical mistake lies in schedule planning. Art. 6 LDét requires the employer to report in writing to the designated cantonal authority the particulars required for monitoring before the assignment begins. Above all, work may only commence eight days after the assignment has been notified. Overlooking this waiting period when building the tender schedule leads to immediate delays on the construction site. Non-compliance with this reporting duty exposes the company to administrative fines of up to 5000 francs under art. 9 LDét.
Finally, careless drafting of subcontract agreements is a widespread vulnerability. Without the contractual and organisational arrangements required by art. 8c ODét, the main contractor forfeits its right to exemption. If an audit by joint parity commissions uncovers wage dumping, joint and several liability under art. 5 LDét will inevitably apply should the subcontractor vanish. Back payments claimed to settle wage shortfalls, unpaid social security contributions and inspection costs can rapidly reach tens of thousands of francs, turning a seemingly profitable contract into a financial pitfall.
Illustrative practical cases (typical scenarios on Swiss construction sites)
The figures and scenarios shown below are illustrative examples and do not correspond to any actual construction site.
Scenario 1: Tender for a public renovation contract (Canton of Vaud)
Type of structure: Energy retrofit of a municipal administrative building.
Workforce involved: 10 posted electrical installers.
Approach chosen during tendering: To win the call for tenders, the general contractor includes an extremely aggressive quote from a foreign subcontractor. It signs the works contract without requesting an attestation from the joint enforcement bodies or a signed declaration guaranteeing minimum wage conditions.
Justification and consequences: Six months after work begins, an inspection reveals that workers are receiving less than the net minimum wage (art. 8a ODét). Put on formal notice, the subcontractor files for bankruptcy and debt recovery proves impossible. Unable to show that it implemented the required contractual and organisational arrangements (art. 8c ODét), the general contractor cannot claim exemption. Under art. 5 LDét, it is jointly and severally liable for unpaid wages. The reassessment, estimated at 55 000 CHF, is drawn entirely from the main contractor's working capital, wiping out the project's profit margin. In addition, the cantonal authority considers revoking the contract award for non-compliance with participation requirements (art. 44 LMP).
Scenario 2: Private contract for a residential development (Canton of Geneva)
Type of structure: Construction of three residential buildings in PPE.
Workforce involved: 6 specialised facade installers.
Decision taken during the tender: Acting on behalf of the total contractor, the site management selects a cross-border subcontractor. Starting from the negotiation phase, it requires the submission of a posting certificate and a signed declaration guaranteeing minimum wage conditions (art. 8b ODét). The subcontract integrates strict on-site inspection clauses.
Justification and consequences: During execution, the cantonal authority conducts an inspection and notes a minor irregularity regarding the reimbursement of expenses related to posting (art. 2 LDét). The subcontractor delays rectifying the situation. However, the total contractor produces its documented tender file, proving it fulfilled its duty of due diligence exhaustively. Thanks to this foresight, it frees itself from joint and several liability (art. 5 LDét) and avoids the administrative sanctions of art. 9 of the LDét, thereby safeguarding its profitability and reputation in the Geneva market.
Calls for tenders: free tools
Direct public procurement tenders, AIMP thresholds by canton, converting SIA 451 to Excel, quantity takeoff from an IFC model.
Frequently asked questions
Is the main contractor liable for unpaid wages of its subcontractor?
Yes. Under art. 5 LDét, the contracting employer bears civil liability for any failure by its subcontractors to pay net minimum wages. This liability becomes joint and several if debt collection against the subcontractor proves unsuccessful. The company can secure exemption by proving it fulfilled its duty of due diligence.
How do you prove due diligence regarding a subcontractor during a tender?
Art. 8c ODét requires taking contractual and organisational measures. The main contractor demands documents proving compliance with minimum conditions, such as a signed declaration, a certificate from joint enforcement bodies or entry in a inspection register pursuant to art. 8b ODét.
Can a foreign subcontractor start work immediately after the contract is awarded?
No. Art. 6 LDét requires the employer to report the assignment in writing to the cantonal authority before work begins. Work on the construction site can only start eight days after this official notification, under penalty of administrative sanctions.
What are the penalties if the subcontractor fails to comply with working conditions?
If the main contractor breaches its duty of due diligence, art. 9 LDét provides for severe administrative sanctions. These include a fine of up to 5000 CHF or a formal ban on offering services in Switzerland for one to five years for the contracting entrepreneur.
Is subcontracting always permitted in Swiss public procurement?
Art. 31 LMP allows the involvement of subcontractors, unless the contracting authority expressly limits or excludes it in the call for tenders. However, the characteristic performance of the contract must in principle be delivered directly by the main tenderer who won the award.
Does the contracting authority check subcontractors during the tender evaluation?
Yes. Under art. 12 LMP, the contract is only awarded to tenderers who comply with employee protection provisions and working conditions. Subcontractors are also required to comply with them, and the contracting authority may exclude a tender in the event of proven non-compliance.
Managing subcontracting right from the tender stage is an absolute necessity for any construction firm in Switzerland. The liability imposed by the Posted Workers Act demands constant vigilance. The main contractor must incorporate due diligence requirements into its contracts and verify its partners' joint certificates. Negligence exposes the company to financial penalties and exclusion from future calls for tenders. To deepen your knowledge of contract award procedures, consult our dedicated resources:
- Public Procurement and Private Contracts in Switzerland: Procedures, Access and Tender Strategy for Construction Firms
- AIMP and LMP Thresholds: Open, Selective, or Invitation Procedure, Which Applies to Your Contract?
- Exceptional Direct Contract: Conditions Set by the AIMP and Practical Implications for Contractors
- Private Calls for Tenders: Property Management Agencies, Architects and Applicable SIA Rules