Skip to content
Art ConstructionTenders
Practical guide

Winning Sustainability Points: KBOB LCA, Recycled Concrete, and Site Fleet

Maximise your sustainability score in Swiss tenders: KBOB ecobalance, recycled concrete, and low-emission site fleet under LMP public procurement rules.

Table of contents
The 3 Major Site Risks
  1. Financial / Margin: Pricing recycled concrete or low-emission plant without securing regional supply chains exposes the firm to unforeseen procurement cost overruns, which can represent a margin variance of around 4 % to 8 % on the structural work package, with no possibility of adjusting the agreed price under the lump-sum rules of art. 373 CO.
  2. Legal / Joint body / SUVA: Submitting unsubstantiated environmental commitments in a tender exposes the tenderer to the penalties of art. 44 LMP; the contracting authority may exclude the bidder from the procedure or revoke the contract award if it determines that false information was provided or that environmental statutory requirements under art. 12 LMP are not met.
  3. Administrative / Handover: Failing to provide KBOB ecobalance data sheets or delivery notes certifying the share of recycled aggregates during audits by the contracting authority undermines the validation of award criteria set under art. 29 LMP, delaying formal acceptance of the works and the completion record under SIA 118.

In public procurement governed by the LMP, contracts are no longer awarded primarily on the lowest price, but on evaluating the most advantageous tender under art. 41 LMP. The sustainable development criteria set out in art. 29 LMP and aligned with the objectives of art. 2 LMP require structural work and finishing work contractors to provide rigorous technical proof of their environmental performance. Estimators and SME owners must now back their technical proposals with verifiable data to turn environmental requirements into a direct competitive advantage.

This operational guide outlines the methodology for leveraging life-cycle assessments in line with KBOB recommendations, incorporating recycled concrete under contract, and documenting the environmental compliance of the site equipment fleet. By pairing precise technical data sheets with optimised transport logistics, construction firms bolster the technical plausibility of their submissions, eliminate disqualification risks under the LMP, and maximise their overall score before cantonal and municipal award panels across French-speaking Switzerland.

Method for justifying KBOB ecobalance data and leveraging results

To maximise tender scoring under art. 29 LMP, the tenderer must move beyond vague declarations of intent by providing quantified ecobalances based on the KBOB (Coordination Conference of Federal and Cantonal Building and Property Services) life-cycle assessment platform. Public clients award top marks to tenders that incorporate grey energy and global warming potential metrics directly into the cost breakdown, demonstrating contractual compliance governed by art. 364 CO.

Environmental optimisation relies on establishing a material and energy flow matrix, converted into carbon equivalents and environmental impact points using official KBOB emission factors. The estimator must isolate the bill of quantities chapters carrying the greatest environmental impact, primarily excavation, special foundations, and reinforced concrete works. Aligning the tender with these official benchmarks secures the plausibility of the bid under art. 29 LMP and art. 38 LMP during the technical review by the awarding authority.

Incorporating Recycled Concrete and Aggregate Traceability

Using concrete made with recycled aggregates provides a decisive edge over competitors. The technical narrative must detail the exact material specified, distinguishing between crushed concrete aggregate mix and recycled aggregate mixes sourced from general deconstruction. The contractor remains fully liable for the sound quality of the materials supplied pursuant to art. 365 CO, which makes attaching compliance certificates from the partnering ready-mix plant to the tender mandatory.

A tender gains substantial credibility when it details haulage distances. Recycled concrete loses its ecological benefit if aggregate transport journeys are excessive. The tender should formalise a closed logistical loop specifying the origin of excavated or demolished materials, the licensed recycling facility location, and the direct hauling route to the construction site. In accordance with the duty to notify under art. 365 CO, the contractor must inform the client of any conflict between specified mechanical strength requirements and high secondary aggregate replacement ratios.

Evaluation Criteria for Site Equipment Fleets and Decarbonisation

The machinery assigned to site operations forms the third axis of sustainability scoring. The contracting authority evaluates the emission profile of earthmoving plant, hoisting gear, and transport vehicles. Under art. 364 CO, the contractor provides the means and equipment required to carry out the works at their own expense; showcasing a low-emission fleet demonstrates immediate operational readiness.

The environmental brief must divide the equipment list into three categories: heavy machinery fitted with particulate filters compliant with the requirements of the Air Pollution Control Ordinance, compact equipment powered 100 % by electric or hybrid drives for dense urban areas, and temporary construction site power supply systems. For each category, the technical report details the direct savings in fossil fuel and the reductions in noise pollution, factors that are systematically rewarded in cantonal evaluation grids.

Comparison table of environmental levers during the tendering phase

The following table outlines the technical trade-offs between a conventional approach without sustainability tracking and an optimised methodology designed to secure full marks under art. 29 LMP.

Evaluated component Standard low-scoring practice Optimised KBOB / Sustainability solution Required justification and documentation Impact on procurement score
Structural concrete Conventional concrete with virgin aggregate only Recycled concrete with guaranteed minimum secondary aggregate share Batching plant technical data sheet, compliance certificate under art. 365 CO Captures 80 % to 100 % of available points for materials
Overall life-cycle assessment (LCA) General narrative mention without calculations Full quantified assessment using official KBOB emission factors Material flow balance and CO2-equivalent matrix annexed to the tender Maximum score for technical merit and sustainable development
Excavators and loaders Standard diesel machinery without engine specifications Electric or hybrid machines with certified particulate filters Plant inventory sheets, declaration of conformity under OMach, RS 819.14 Decisive differentiator on environmentally sensitive construction sites
Site waste haulage Off-site disposal to landfill without haulage optimisation Short-haul regional recycling circuit (< 15 km) Projected waste tracking manifests, sorting platform service agreement Validation of bid plausibility under art. 38 LMP
Temporary site power Standalone fossil-fuel generator Temporary low-carbon grid connection or battery energy storage Temporary electrical installation schematic, direct emissions reduction calculation Systematic bonus points on emissions and clean-site criteria

Frequent mistakes and their financial impact on tenders

The first mistake lies in committing to recycled concrete replacement ratios that are structurally unviable. If a contractor submits an unrealistic proposal to win a contract under art. 41 LMP, they risk rejected handovers or structural defects governed by art. 368 CO. Remedying or replacing non-compliant concrete elements can result in losses ranging from 45 000,00 CHF to 120 000,00 CHF on the lower storeys of a building alone.

The second pitfall involves overlooking power supply constraints for electric plant. Failing to anticipate the electrical capacity needed for overnight charging on site leads to deploying unplanned emergency generators. This oversight can trigger unforeseen rental overheads of roughly 18 500,00 CHF. Under art. 373 CO, fixed-price contracts rule out any adjustment to the agreed price, leaving the contractor to absorb the entire shortfall.

Finally, submitting carbon footprints calculated with unrecognised foreign databases leads to the cancellation of sustainability points during the technical check under art. 38 LMP. A firm thereby loses the advantage of a competitive financial price, as the contract is awarded to a competitor who substantiated their proposal strictly in line with KBOB recommendations.

Illustrative practical cases (typical scenarios on Swiss construction sites)

The figures and project data shown below are illustrative examples designed to guide estimating and tendering methodology.

Standard Scenario 1: Construction of a School Building in the Canton of Vaud

For a public contract covering the construction of a school complex in Lausanne (total project value estimated at 8 450 000,00 CHF including taxes), the award criteria allocated a 20 % weighting to sustainable development under art. 29 LMP, with price weighted at 50 % and technical merit at 30 %. The structural work contractor deployed an average crew of 12 skilled operatives.

The lowest-priced bidder submitted an offer of 8 120 000,00 CHF, but relied on conventional environmental practices (sustainability score: 11/20). The winning contractor submitted a tender priced at 8 285 450,00 CHF incl. VAT (+165 450,00 CHF difference), specifying 100 % recycled concrete for foundation slabs and retaining walls, backed by a combined rail-and-road transport plan restricted to a 12-kilometre radius and certified by the batch plant.

Backed by quantified calculations from KBOB tables and technical submittals for electric cranes ensuring zero direct emissions on the school playground, the tender earned 19,5/20 on the sustainability criterion. The consolidated evaluation ranked this proposal as the most advantageous tender under art. 41 LMP, demonstrating that investing in environmental traceability easily offsets an initial price premium.

Standard Scenario 2: Municipal Infrastructure Redevelopment in the Canton of Fribourg

An open call for tenders was launched for sewer system upgrades and surface resurfacing in a Fribourg village centre, representing a total contract value of 1 650 000,00 CHF incl. VAT. The contracting authority required strict compliance with statutory environmental protections under art. 12 LMP, including a specific spoil-management criterion weighted at 15 %.

The successful contractor tailored their bid around the on-site crushing of 2 400 m³ of asphalt and clean gravel for immediate reuse as road subbase. This approach eliminated off-site trucking to landfill, avoiding estimated transport and tipping fees of approximately 42 300,00 CHF incl. VAT. By documenting this method with a mobile crushing plant certificate meeting cantonal guidelines and pledging work quality under art. 364 CO, the contractor secured top marks on the circular economy sub-criterion while protecting operational profitability.

Calls for tenders: free tools

Direct public procurement tenders, AIMP thresholds by canton, converting SIA 451 to Excel, quantity takeoff from an IFC model.

View tendering tools

Frequently asked questions

How do you prove the concrete recycling rate under KBOB recommendations?

The tenderer submits technical data sheets from the ready-mix supplier along with representative delivery slips. The contracting authority assesses the ecobalance under art. 29 LMP, rewarding a recycled aggregate content of at least 25 %, which upgrades the tender without an average cost increase exceeding 1500.00 CHF.

What certificates must be provided to substantiate a decarbonised site fleet?

To score maximum points, provide the vehicle registration documents for delivery fleets and emission certificates for earthmoving equipment. The contracting authority assesses environmental compliance under art. 29 LMP, granting a competitive edge to companies that limit diesel transport on a typical contract of 450000.00 CHF.

Can recycled concrete be contractually required from your own subcontractors?

Yes, the general contractor can bind its subcontractors through strict performance clauses in the contract for work under art. 363 CO. This ensures regional supply chains scrupulously comply with the requirements of art. 12 LMP and avoid financial penalties in the region of 5000.00 CHF.

Does the transport distance of materials affect the technical proposal score?

Yes, the sustainability criteria in art. 29 LMP favor short supply chains. A sourcing radius of less than twenty-five kilometers for aggregates cuts the overall carbon footprint in the KBOB life cycle assessment, yielding logistical savings often estimated at around 3200.00 CHF across the entire project.

Can an offer be dismissed if environmental criteria are not documented?

Failing to provide concrete proof results in the lowest possible score for the sustainable development criterion under art. 29 LMP. If mandatory qualification criteria are not met, the contracting authority may formally exclude the bid pursuant to art. 44 LMP, wiping out the initial 8500.00 CHF estimating investment.

Is there any legal recourse if the evaluation panel overlooks a superior KBOB life cycle assessment?

The unsuccessful bidder has a strict deadline to challenge the award decision. Under art. 56 LMP, a substantiated appeal must be lodged in writing within 20 days of notification, provided a clear breach of the award criteria specified in the call for tenders documents can be demonstrated.

Securing your environmental points in public procurement

Rigorously integrating the KBOB life cycle assessment, recycled concrete, and a low-carbon logistics plan turns a routine tender response into a winning bid under the Federal Act on Public Procurement. To reinforce every section of your tender submission and maximize your evaluation score against the requirements of Swiss contracting authorities, consult our specialized step-by-step guides:

Art Construction is an independent company: it is not affiliated with the SIA, CRB, SUVA, or KBOB. Referenced norms and standards point to publications from these bodies; only official versions are legally binding.