SIA 181 Tool 5.6 Online

SIA 181 Acoustics Checker (dB) & Cercle Bruit Simulator for Heat Pumps

Check the acoustic requirements of SIA 181 and simulate the noise circle (“cercle de bruit”) of a heat pump.

Interactive tool

A Air/Water Heat Pump: noise at the neighbour's window (OPB annex 6, Cercle Bruit)

dB(A)
m
dB

Rating level at the neighbour's window

Spherical geometric attenuation (20 log10 d + 11)
Rating level Lr
Planning value
Margin before exceedance
Minimum distance to meet the night-time value

Lr = LwA + Dc − (20 · log10(d) + 11) + Ke + K obstacle, with Ke = +6 dB night-time level correction for technical installations (specification value). Simplified free-field calculation: the competent authority may require the full Cercle Bruit form or a measurement.

B Sound insulation between dwellings (SIA 181 standard)

6 Dwelling status

Sensitivity of the receiving rooms: moderate (living room and bedroom). The measured values are those of the acoustic measurement report of the building.

dB
dB
dB(A)
dB(A)

Criteria check

Measured values compared with the thresholds of the chosen status
CriterionMeasured (dB)Threshold (dB)Verdict

Thresholds from the tool's specification, according to the SIA 181 standard: minimum requirements for rented dwellings, enhanced requirements (+3 dB for airborne noise, −3 dB for impact noise) for condominium property and semi-detached houses. The enhanced level is agreed by contract under the SIA 181:2020 standard.

Embed this calculator on a website page

Paste this code into the page, or write [outil code="5.6"] in the content of a page on the site.

📄 Files and templates linked to this tool (free)

Move from calculation to full management

Keep your references at hand, then automate them in your quotes, bids and final statements.

⚡ Automate this calculation in our ERP / Soumission software (Trial)

Technical reference guide

SIA 181 standard: why the "enhanced requirements" (+3 dB) are mandatory in condominium property (PPE) and semi-detached houses

The SIA 181 acoustics standard dB values sets the minimum insulation between two dwellings against airborne noise (voices, television), impact noise (footsteps, dropped objects) and noise from technical and plumbing installations. It distinguishes two levels: the minimum vs enhanced requirements PPE SIA 181. For a rented dwelling, the tool adopts the minimum requirements; for condominium property and semi-detached or terraced houses, it adopts the enhanced requirements, which improve insulation by +3 dB against airborne noise and by −3 dB against impact noise. A co-owner buying off plan therefore has an interest in demanding this level in the sale deed and on the plans.

Note on the text of the standard. The title of this section takes over the tool's specification, which presents the enhanced requirements as mandatory. Under the SIA 181:2020 standard, only the minimum requirements are those that the authorities enforce; the enhanced requirement level, formulated for detached, semi-detached, terraced houses and apartments in PPE, is agreed by contract. It becomes binding on the parties as soon as it appears in the works contract, the sale deed or the specification: demand it in writing. The decibel values of the tool (specification) were not found in the text of the standard.

Table of limit values for airborne noise insulation (Di) and impact noise (L'nT,w)

The thresholds applied by the tool are as follows: the insulation Di must reach or exceed the value shown, whereas impact noise L'nT,w, installation noise LH,tot and continuous HVAC (CVC) noise must not exceed it.

SIA 181 limit values according to the status of the dwelling
Dwelling statusAirborne noise DiImpact noise L'nT,wBuilding services LH,totContinuous noise CVC
Rental dwelling (SIA 181 minimum requirements)≥ 52 dB≤ 53 dB≤ 33 dB(A)≤ 33 dB(A) (value used by the tool)
Condominium property (PPE) (Enhanced requirements: +3 dB for airborne noise, −3 dB for impact noise)≥ 55 dB≤ 50 dB≤ 30 dB(A)≤ 25 dB(A)
Terraced or semi-detached houses (enhanced requirements)≥ 57 dB≤ 48 dB≤ 30 dB(A)≤ 25 dB(A)

The specification gives no HVAC (CVC) threshold for rented dwellings: the tool applies the value for installations (33 dB(A)). A lower decibel figure is always better for impact noise, installations and equipment, whereas the insulation Di must on the contrary be as high as possible.

Air/water heat pump and neighbourhood: how to pass the Cercle Bruit calculation (OPB annex 6)

The heat pump noise calculator neighbourhood cercle bruit takes over the method of the "Cercle Bruit" implementation guide: you start from the night-time sound power of the machine (LwA), add the directivity correction Dc of the location, subtract the distance attenuation (20 · log10(d) + 11) and add the night-time level correction Ke (6 dB) and the obstacle correction. The result is the rating level Lr at the open window of the nearest neighbour, to be compared with the planning value of the zone.

Example from the tool: a 52 dB(A) pump placed against a facade, 8.0 m from the neighbour's window, undergoes an attenuation of 29.06 dB and gives Lr = 34.9 dB(A): compliant, with a 10.1 dB margin in a GS II (DS II) residential zone (45 dB(A) at night).

Why placing a heat pump in a corner between walls increases the perceived noise by +6–+9 dB(A)

A machine radiating into all of space loses its energy in all directions. Placed on the ground in open country, it radiates into a hemisphere (+3 dB); against a facade, the waves reflect and the machine radiates into a quarter-sphere (+6 dB); in a corner between two walls or under an eave, into an eighth of a sphere (+9 dB). Sound energy concentrated in a smaller space is perceived as louder: for the same power, moving from the facade to the corner adds 3 dB, which forces you to increase the distance from the neighbour by about 40% to get back to the same level.

Effect of the location on the rating level and on the minimum distance
LocationDcLr at 8,0 mMinimum distance without enclosureMinimum distance with 5 dB enclosure
1. In free field / garden (D_c = +3 dB — hemisphere)+3 dB31,9 dB(A)1,78 m1,00 m
2. Against a facade (D_c = +6 dB — quarter-sphere)+6 dB34,9 dB(A)2,51 m1,41 m
3. In a corner between 2 walls or under an eave (D_c = +9 dB — eighth of a sphere)+9 dB37,9 dB(A)3,55 m2,00 m

Meeting the night-time planning value of 45 dB(A) in a residential zone (GS II (DS II))

The noise sensitivity level GS II DS II OPB 45 dB designates the pure residential zone, where the night-time planning value of annex 6 of the Noise Abatement Ordinance (OPB) is 45 dB(A) (day: 55 dB(A)). In a mixed or craft zone (GS III (DS III)), the values rise to 50 dB(A) at night and 60 dB(A) by day. With the same machine against a facade and without an enclosure, the minimum distance is 2.51 m in GS II (DS II) and 1.41 m in GS III (DS III).

Three levers make it possible to meet the night-time value: choose a quieter model (the sound power is on the data sheet), move the machine away from the neighbour's window or take it out of a corner, and install an enclosure or a sound-absorbing wall, which subtracts 5 dB in the tool's calculation. The machine's night mode, which reduces the fan speed, is often the cheapest solution.

The planning values (GS II (DS II): 45/55 dB(A), GS III (DS III): 50/60 dB(A)), the +6 dB night-time correction and the directivity corrections are those of the specification; only the official Cercle Bruit form of your canton is authoritative for the permit.

The 4 site errors that destroy the acoustics of a floating screed (acoustic bridges)

The impact noise floating screed L'nT,w depends less on the product than on its installation: a floating screed insulates as long as it touches nothing but its base layer. The slightest rigid contact, an acoustic bridge, transmits impacts to the slab and the walls. Four errors recur on sites:

  1. A perimeter strip cut too early or a skirting board glued to the screed and the wall. The perimeter strip must stay until the floor coverings are laid, and the joint is filled with an elastic sealant.
  2. A resilient layer that is torn, badly joined or without a covering film. The screed concrete seeps into the joints, hardens against the slab and connects the two layers.
  3. Pipes, ducts or door frames passing through the screed without a sleeve. Every rigid crossing is a bridge: flexible sleeves, insulated pipes, door frames installed on the finished screed.
  4. Heavy partitions or walls placed on the floating screed, or a screed or resilient-layer thickness different from the specification. Partitions rest on the slab and the screed is laid between them.

Any one of these errors can be enough to exceed the 50 dB threshold aimed for in condominium property (PPE), or even the 53 dB threshold for rented dwellings. Acoustic measurement on site, before the final floor covering is laid, makes it possible to correct in time. To calculate the screeds and acoustic insulation item in your budget, see the global CFC budget calculator 0–9.

⚡ Calculate your screeds and your heat pump in Soumission

Frequently asked questions on acoustics, the SIA 181 standard and heat pumps (FAQ)

1. What is the difference between minimum and enhanced requirements of the SIA 181 standard in condominium property (PPE)?

The minimum requirements are those the authorities enforce: according to the tool's specification, airborne noise insulation Di of at least 52 dB, impact noise L'nT,w of 53 dB at most and installation noise LH of 33 dB(A) at most. The enhanced requirements, which improve comfort, move to 55 dB, 50 dB and 30 dB(A) in condominium property, and to 57 dB, 48 dB for semi-detached or terraced houses.

Under the SIA 181:2020 standard, the enhanced requirement level is not imposed by the authorities: it is agreed by contract with the client, and is in practice formulated for detached, semi-detached, terraced houses and apartments in PPE. The decibel values come from the specification and were not verified in the text of the standard: use the values of your contract.

2. What minimum distance should be kept between a heat pump and the neighbour's window to stay at 45 dB(A) at night?

With a sound power of 52 dB(A), the pump placed against a facade (+6 dB), the night-time correction of +6 dB and no enclosure, at least 2.51 m to the neighbour's window is needed to stay at 45 dB(A) (residential zone GS II (DS II)). Placed in a corner (+9 dB), the distance rises to 3.55 m, and a 5 dB enclosure brings the requirement back to 1.41 m. At 8.0 m, the rating level in the example is 34.9 dB(A).

The calculation follows spherical propagation (20 log10 d + 11) and the directivity correction of the specification; the +6 dB at night is a value of the specification not verified in the ordinance. The competent authority may require the calculation of the Cercle Bruit form or an on-site measurement.

3. What is the maximum impact noise level under a floating screed?

Impact noise L'nT,w measures what is heard in the dwelling below when someone walks or an object falls above: the lower the value, the better the result. The thresholds in the specification are 53 dB at most as the minimum requirement, 50 dB in PPE and 48 dB for semi-detached or terraced houses. With the example measurement of 51 dB in PPE, the threshold is exceeded by 1.0 dB.

Measurement on site depends on the screed, the resilient layer, the edges and the laying of the floor covering: an acoustic bridge between the screed and the wall cancels the effect of the resilient layer. Have the building measured before the final floor coverings are laid.

Indicative information prepared on the basis of the SIA 181 standard and the Noise Abatement Ordinance (OPB); it replaces neither an acoustic measurement nor the Cercle Bruit form of your canton.

📥 Ready-to-use pack · free

Download the document

The file is displayed on screen right away and we also send it to you by e-mail.

Your address is used to send you this file. See our privacy policy.