In a project set up according to the BIM method, the one described in Switzerland by the SIA 2051 technical guideline, the engineer's model often carries the concrete volumes of the slabs, walls and columns. For the structural contractor, this saves time, provided you know what these quantities represent: gross or net volume, openings deducted or not.
The BIM-IFC 3D viewer and inspector studio displays the concrete quantities contained in the IFC model, where the author has filled them in: it does not recalculate volumes. You isolate the IfcSlab, IfcWall and IfcColumn categories, read the area, volume and weight of each element in the inspector, and export the quantities by category as CSV. 3D dimensioning is used to redo the calculation by hand on a sample element.
Worked example: IfcSlab, IfcWall and IfcColumn concrete volumes of a building
A masonry contractor responds to a tender for the structural shell of a small 5-level building in French-speaking Switzerland. The engineer's IFC model contains 5 identical slabs, walls, 12 columns of 40 × 40 cm, 3.00 m high, and 8 beams. The quantity surveyor exports the quantities and checks one slab by hand.
| Component | IFC class | Number of elements | Net volume read (m³) |
|---|---|---|---|
| Slabs | IfcSlab | 5 | 212.40 |
| Walls | IfcWall | 38 | 96.80 |
| Columns | IfcColumn | 12 | 5.76 |
| Beams | IfcBeam | 8 | 7.20 |
| Total concrete | 4 classes | 63 | 322.16 |
3D dimensioning of one slab gives 18.00 × 11.50 = 207.00 m² gross, for a thickness of 0.22 m. Two openings are to be deducted: the stairwell, 2.60 × 4.80 = 12.48 m², and a duct shaft, 1.20 × 0.80 = 0.96 m². The net area is 207.00 − 12.48 − 0.96 = 193.56 m², and the net volume 193.56 × 0.22 = 42.58 m³. The model states 42.48 m³: the difference is 0.10 m³, that is 0.2%. The gross volume, 207.00 × 0.22 = 45.54 m³, exceeds the net by 2.96 m³ (6.5%).
The five slabs give 5 × 42.48 = 212.40 m³, the total of the category. For the columns, 0.40 × 0.40 × 3.00 = 0.48 m³ each and 12 × 0.48 = 5.76 m³: the model and the calculation agree. The total of 322.16 m³ can serve as a basis for the tender. Wastage and the rule for deducting openings are to be confirmed according to the specification.
The model states 322.16 m³ of concrete; checking one slab gives 42.58 m³ against 42.48 m³ read, a difference of 0.2%, whereas the gross volume would have added 6.5%.
3 common mistakes when reading the concrete quantities of an IFC model
Adding gross volumes to net volumes
The inspector may display a gross volume and a net volume for the same element. The first ignores the openings, the second deducts them: a 6.5% difference on the slab in the example. Use the same quantity for all categories.
Believing that every slab and every wall carries a quantity
If the author exported the volumes for only part of the elements, the total is incomplete and the 3D drawing does not show it. In the CSV export, compare the number of elements in the category with the number of elements that carry a value.
Counting the concrete twice at junctions
Depending on the modelling, a wall may run up into the thickness of the slab, or a column pass through the floor. The same concrete then appears in two elements. Place the section box on a slab-to-wall junction to see where each element stops.
How to read IFC concrete quantities in 3 steps
- Open the model and isolate the concrete
Open the .ifc or .ifczip file in the studio. In the explorer, isolate the slabs (IfcSlab), then the walls (IfcWall), the columns (IfcColumn) and the beams. - Read the quantities of a sample slab and recalculate it
Select a slab and open the inspector: area, gross volume, net volume and material are displayed if they have been filled in. Use 3D dimensioning to take the length, width, thickness and openings, then redo the calculation by hand. - Export the concrete quantities by category as CSV
The CSV file opens in your spreadsheet and gives, for each IFC class, the quantity, its total, its unit, the number of elements in the category and the number of elements that carry a value.
What the free studio does not do for concrete quantities
The studio calculates no volume from the geometry: a model without quantities yields none, and a wrong volume in the file stays wrong on screen. It gives no concrete grades, formwork or reinforcement if the author has not filled them in. The quantities read do not replace the contractual bill of quantities of the tender documents.
Plans Pro (2D/3D) keeps the model in the site's private storage, saves your annotated views with their versions and allows teamwork. The Portail chantier passes your questions to the site management as tickets, with the viewpoint and the elements concerned.
Frequently asked questions
Does the studio calculate the concrete volume from the IFC model?
No. It displays the quantities the author has written into the file and adds them up by category. Without quantities in the model, you have to take off from drawings or ask for a new export.
What is the difference between gross and net volume for an IfcSlab?
The gross volume corresponds to the solid outline of the slab; the net volume deducts the modelled openings. In the worked example, the slab goes from 45.54 m³ gross to 42.58 m³ net.
Can these concrete quantities be used as they are in a tender?
They serve as a basis, provided they are checked. Recalculate at least one element per category, state the origin of the quantities in your take-off and confirm the deduction rule according to the specification.
What does the SIA 2051 technical guideline say about quantities?
It is the Swiss reference document on the BIM method. It does not replace the measurement rules of the contract: the information the model must contain is agreed between the project parties.